THE London and
Birmingham Railway is unquestionably the greatest public work ever
executed, either in ancient or modern times. If we estimate its
importance by the labour alone which has been expended on it,
perhaps the Great Chinese Wall might compete with it; but when we
consider the immense outlay of capital which it has required — the
great and varied talents which have been in a constant state of
requisition during the whole of its progress — together with the
unprecedented engineering difficulties, which we are happy to say
are now overcome — the gigantic work of the Chinese sinks totally
into the shade.
It may be amusing to some readers, who are unacquainted with the
magnitude of such an undertaking as the London and Birmingham
Railway, if we give one or two illustrations of the above assertion. The great Pyramid of Egypt, that stupendous monument which seems
likely to exist to the end of all time, will afford a comparison.
After making the necessary allowances for the foundations,
galleries, &c., and reducing the whole to one uniform denomination,
it will be found, that the labour expended on the great Pyramid was
equivalent to lifting fifteen thousand seven hundred and
thirty-three million cubic feet of stone one foot high. This labour
was performed, according to Diodorus Siculus, by three hundred
thousand, and by Herodotus, one hundred thousand men, and it
required for its execution twenty years.
If we reduce in the same manner the labour expended in constructing
the London and Birmingham Railway to one common denomination, the
result is, twenty-five thousand million cubic feet of material
(reduced to the same weight as that used in constructing the
Pyramid) lifted one foot high, or nine thousand two hundred and
sixty-seven million cubic feet more than was lifted one foot high in
the construction of the Pyramid; yet this immense undertaking has
been performed by about twenty thousand men in less than five years.
From the above calculation has been omitted all the tunnelling,
culverts, drains, ballasting, and fencing, and all the heavy work at
the various stations, and also the labour expended on engines,
carriages, wagons, &c.; these are set off against the labour of
drawing the materials of the Pyramid from the quarries to the spot
where they were to be used — a much larger allowance than is
necessary.
As another means of comparison, let us take the cost of the Railway
and turn it into pence, and allowing each penny to be one inch and
thirty-four hundredths wide, it will be found that these pence laid
together, so that they all touch, would more than form a continuous
band round the earth at the equator.
As a third mode of viewing the magnitude of this work, let us take
the circumference of the earth in round numbers at one hundred and
thirty million feet. Then, as there are about four hundred million
cubic feet of earth to be moved in the Railway, we see that this
quantity of material alone, without looking to any thing else,
would, if spread in a band one foot high and one foot broad, more
than three times encompass the earth at the equator.
It will be evident that such a work as this could only have been
undertaken in a country abounding with capital, and possessing
engineering talent of the highest order. The steps, by which the
science of Railways has arrived at its present position, were slow
yet progressive. Railways of wood and stone were in use, as well as
the flat iron or tram-rail, in the middle of the seventeenth
century, particularly among the collieries of the north, and were
gradually improved from time to time; they still, however, retained
a character totally distinct from those structures which will soon
form the means of transport through all the principal districts of
the kingdom.
At length we lived to see the splendid creations of GEORGE
STEPHENSON, one of those gifted beings who are
destined by one unerring stroke to annihilate all those bonds which
limit the fame of ordinary men. Watt and Stephenson are of no
country; they belong, not even to Europe; they are citizens of the
world in the truest and best meaning of the word. Centuries hence,
when with few, very few, exceptions, even the deeds as well as the
names of the heroes, the conquerors, and the politicians of the
present day will have become engulfed in one common oblivion, those
of Watt and Stephenson will be found rolling imperishably down the
stream of time, and fertilising the whole habitable globe with the
magnificent creations of their genius.
The first performance to which Mr. Stephenson directed the resources
of his mind was the Stockton and Darlington Railway. This was
certainly a great attempt; the ice was broken, the old track was
fearlessly abandoned; yet it was but the planting of that ladder by
which he was to ascend to his present eminence — he scaled that
eminence on the Liverpool and Manchester line. It was there the
system was shown in all its bearings, and at one blow a full and
entire revolution was effected in all our habits and manners, and in
our customs and feelings; a revolution which every person will
confess is of such extent, that its consequences and its bearings on
all the circumstances of civilised life are not capable of being
even guessed at, but which even now almost justifies Bishop
Wilkins’s idea, that in some future time a man would be as likely to
call for his wings as he than did for his boots. It is certainly a
splendid sight to see one man, by the magic powers of his mind —
more than realising the far-famed boast of Archimedes — taking a
railway for his fulcrum, and moving the world.
It will readily be supposed, that in such an enterprising country as
this, a successful experiment like that of the Liverpool and
Manchester Railway, would at once be followed out in all directions,
bearing in mind that the expense of such enormous works will, at all
times, limit them to main lines of travelling, in order to insure a
proper return of capital to the spirited individuals who embark
their property in them. Lines from the Liverpool and Manchester
Railway to Birmingham, and from Birmingham to London, were among the
first which were projected; and, in fact, surveys and other
preparations, for the London and Birmingham line were in progress,
prior to the opening of the Liverpool and Manchester Railway,
(September, 1830,) and the projectors were waiting only the
successful result of that event to mature their plans. Some of these
surveys were mode us far back as 1825.
In 1830, two lines were proposed; one by Sir John Rennie, taking the
Banbury and Oxford line of road, and the other by Mr. Giles, taking
its course by the way of Coventry. Companies were formed in each
case, and were duly marshalled against each other, with their
various staff appointments fully organised, directors, secretaries,
engineers, solicitors, bankers, &c., and great were the rejoicings
in Westminster Hall.
If the battle had been waged, and if any poet could have been found,
capable of bringing into harmonious numbers such uncouth sounds as,
cuttings and embankments, blocks and sleepers, and slopes of one
thousand eight hundred to one, Homer’s ghost might have trembled
till all Pluto’s dominions gave a simultaneous sympathising shake,
like those comical clocks furnished with Hardy’s “Noddy,” where the
one cannot rejoice in a little irregular motion, without the other
telling tales by instantly wagging about too. But, fortunately, all
parties were too wise, and they deemed it much more prudent, instead
of throwing away their money in an uncertain Parliamentary contest,
at once to consult, as far as possible, the interest of their
several proprietories, by selecting that line which a majority
should consider the best, and thus unite the two companies into one.
George Stephenson had, a little prior to this, been engaged by the
parties who had chosen the Coventry line for the Railway, and as he
also gave his opinion in favour of that route, it was finally
decided that the London and Birmingham Railway should go via
Coventry, and George Stephenson and his son were appointed engineers
to the now united “London and Birmingham Railway Company.”
It may he thought that this period of time is passed over too
lightly; but it is best. Why should the party feelings, the hopes
and the fears, the disagreements, the quarrels, and the
heart-burnings of five or six years ago, he perpetuated? It would be
in excessive bad taste, to say the least of it, and anything but
amusing to the public at large; all every nerve for the interests of
the proprietors, to the best of their ability and judgment, and who
could do more? It may be just observed that, through the proprietors
principally residing in Lancashire, and, from their proximity to the
Liverpool and Manchester line, being to a certain extent practical
men, they were better able to take a leading part, and to judge what
was most advantageous; and they had heavy votes enough to oblige
their judgments to be executed.
There was this object also to be kept; in view, in forming such a
line as the London and Birmingham Railway — that it is a grand trunk
from the metropolis, towards the northern part of England, and that
numerous branches would, in all probability, fall into it at no very
distant period; that the Irish traffic would all come along it, and
most probably the Scotch. It was also to be remembered, that not
only the towns near the line would be benefitted, but others far
distant.
The impulse to travelling which has been given from the facilities
afforded by railways, and the cheapness of this mode of conveyance,
has been astonishing; and will, of course, continue to improve the
more they are brought into use. The increase has varied in all
proportions up to the ratio on the Stockton and Darlington line,
where the passengers are now eighty times as many as they were
before it was in operation.
On September the 11th, 1830, the two Companies united themselves,
selecting eight persons from each as a provisional committee. Much
had been done previously to this in preparing the public mind, and
in endeavouring to obviate opposition, which, however, still
continued very strong among those who either could not or would not
see the advantages of establishing this means of communication. This
has, however, perhaps worked good rather than evil; for it could
only be met by the free use of the press, in order to enlighten all
those who were willing to receive information on the subject of
railways, and this was done to such an extent, that it soon became
apparent our danger would be in having too many railways instead of
too few.
In the latter end of 1830, a committee of survey was appointed to
establish a regular communication with the Engineers, by way of
periodical reports, and to correct errors, make improvements,
confirm friends, and conciliate enemies. In October, Messrs.
Stephenson and Son reported, that the line, as laid down by Mr.
Giles, from Islington to Chipping Barnet, South Mims, Leverstock
Green, and Hemel Hempstead, was exceedingly rough, and incurred deep
and extensive excavations, and that they would recommend it to leave
London near Hyde Park, running almost parallel with the Edgware
Road, to Watford, Hemel Hempstead, Great Berkhamsted, and Ivinghoe.
It was also proposed to enter Birmingham on the south side, by a
tunnel, so as to gain a central terminus. Another plan was to pass
up the Tame Valley from Stone Bridge, and join the Grand Junction
Railway at Wednesbury, having a branch line to Birmingham; this was
done with a view to the advantages of the whole line from London to
Liverpool. Both companies were to have stations in Broad street, —
the Grand Junction on the north-west side, on a piece of ground of
about seven and a half acres; and the London and Birmingham on the
south-east side, containing about nine acres, with another station
at the Bell Barn Road.
In the summer of 1831, Mr. Creed examined another line, with the
mountain barometer, from Northampton, through Bedford, Baldock, and
Hertford, to near the West-India Docks; another line through
Buckingham, Brackley, and Warwick, was surveyed, and many other
attempts at improvement were made, each line having its advantages
and disadvantages; the chief things next to the traffic to be kept
in view being, to select that line where there is the least
difference between the highest and lowest levels, and also that
which is least expensive, even if it is not the most direct.
The country between London and Birmingham is a series of basins or
low districts, separated from each other by considerable ridges of
hills; the object to he gained was, therefore, to cross the valleys
at as high a point as possible, and the hills at as low an one. The
low districts are — the London basin — the valley of the Colne,
extending from Brentford by Watford, to St. Albans — the lowland in
the neighbourhood of Leighton Buzzard, on to Stoke Bruerne — the
valley of the Nene, in which is Northampton — and, the basin of the
Avon; which last from its great depth, low level, and abrupt
termination on the south, by the high ridge of hills on which
Daventry, Kilsby, and Crick are situated, and on the north side of
the Meriden ridge, required particular attention.
The high grounds which bound these districts are — the county
boundary between the London basin and the valley of the Colne — the
Chalk ridge at Ivinghoe, which rises between the Colne valley and
the Leighton Buzzard district — the Blisworth ridge, which forms the
southern side of the valley of the Nene — and the Kilsby and Meriden
ridges, forming the abrupt sides of the valley of the Avon. The
whole will, therefore, stand thus:—
1. The basin at London formed by the Thames.
2. The summit at Oxhey, near the division of the counties of
Middlesex and Hertford.
8. The basin of the Colne river.
4. The summit at Tring.
5. The basin of the Ouse, near Stoney Stratford.
6. The summit at Blisworth, opposite Towcester.
7. The basin fanned at Weedon by the streams flowing into the river
Nene at Northampton.
8. The summit at Kilsby, opposite Daventry.
9. The basin of the river Avon, crossed near Wolston, about five
miles south of Coventry.
10. The summit of the Meriden ridge.
11. The basin at Birmingham, formed by the river Rea, which flows
into the Tame.
From this sketch of the nature of the ground it is evident what care
was required in searching for the best line of road. Mr. Robert
Stephenson examined the country in the autumn of 1830, and was
ordered to prepare the necessary plans and sections to deposit with
Parliament in the November of that year. The time, however, was much
too short; and it was only by great haste and force of numbers that
the preliminary step of depositing these plans was accomplished.
The standing orders of the Houses of Parliament, although not then
so strict or minute as in the present day, required more labour and
closer attention than the time would admit of, and the result of all
this hurried preparation was by no means satisfactory, and
particularly so to the Engineer, who felt that he had not been able
to devote that time and consideration to the project which it
demanded. After some further preliminaries, therefore, it was
determined to defer the application to Parliament for a bill till
the following year, and thus give the Engineer the opportunity of
examining and selecting such a line as he could confidently report
on as being the best the country would afford. When this was done,
the plans and sections were deposited with Parliament in the
November of 1831, showing a line almost identical with that which is
now executed, where the steepest gradient (except where the line has
been extended from Camden Town to Euston Square) is sixteen feet per
mile.
During the preparation of these plans it was, of course, necessary
that, before they could be made out, the Surveyors and Engineers
should go upon the different properties through which the line was
to pass, for the purpose of taking the necessary levels, and
obtaining the data on which they were to found their drawings. This
is a subject which merits the attention of our legislators in no
small degree. Parliament orders certain plans and sections of any
proposed public work, for which an act is sought to be obtained, to
be deposited with their clerk, and with all the respective clerks of
the peace for the counties through which such public work is to
pass. This is a wise and prudent regulation, as it enables every
landed proprietor, or other person interested in property which will
be interfered with by the work in question, to go and inspect the
nature of this interference, and thus ascertain if any and how much
damage will he done to his interests, and to provide against injury,
by making a special agreement for the necessary compensation; or he
may oppose the bill altogether.
This provision is so far good — but no farther. When Providence
ordained that human beings should eat, it was at the same time
ordained that the earth, on which they were to live, should afford
them food. The legislature has not thought it necessary to follow
this wise example: it has ordained that plans and drawings shall be
made, but it has not provided the means by which this is to be done;
consequently the engineers and surveyors are completely at the mercy
of any opponent who holds land, through which the projected line is
to pass, as he can at all times prevent them from making the
necessary surveys. Indeed, if he be not an opponent, but happen to
have had a bad digestion, or his bilious organs disturbed from any
cause whatever, he warns them off his land, and they are left to
make their survey how they can, while the measure in question, no
matter how advantageous to the public, is put in jeopardy through
the want of one or two of Abernethy’s blue pills.
A great deal of this opposition was encountered in making the
surveys for the London and Birmingham Railway, and although, in
every case, as little damage was done as possible, simply, because
it was the interest of those concerned to conciliate all parties
along the line, yet in several instances, the opposition was of a
most violent nature: in one case no skill or ingenuity could evade
the watchfulness and determination of the lords of the soil, and the
survey was at last accomplished at night, by means of dark lanterns.
On another occasion, when Mr. Gooch was taking levels through some
of the large tracts of grazing land, a few miles from London, two
brothers, occupying the land, came to him in a great rage, and
insisted on his leaving their property immediately. He contrived to
learn from them that the adjoining field was not theirs, and he
therefore remonstrated but very slightly with them, and then walked
quietly through a gap in the hedge into the next field, and planted
his level on the highest ground he could find — his assistant
remaining at the last level station, distant about one hundred and
sixty yards, apparently quite unconscious of what had taken place,
although one of the brothers was moving very quickly towards him,
for the purpose of sending him off. Now, if the assistant had moved
his staff before Mr. Gooch had got his sight at it through the
telescope of his level, all his previous work would have been lost,
and the survey must have bean completed in whatever manner it could
have been done; — the great object, however, was to prevent this
serious inconvenience. The moment Mr. Gooch commenced looking
through his telescope at the staff held by the assistant, the
grazier nearest him, spreading out the tails of his coat, tried to
place himself between the staff and the telescope, in order to
intercept all vision, and at the same time commenced shouting
violently to his comrade, desiring him to and knock down the staff.
Fortunately for Mr. Gooch, although performed their office very
badly, and as he could not see distinctly what Mr. Gooch was about,
the hedge being between them, he very simply asked the man at the
staff what his (the enquirer’s) brother said. “Oh,” replied the man,
“he is calling to you to stop that horse there which is galloping
out of the fold yard.” Away went clodpole as fast as he could run,
to restrain the unruly energies of Smolensko the Ninth, or whatever
other name the unlucky quadruped might rejoice in, and Mr. Gooch, in
the meanwhile, very quietly took the necessary sight; he having,
with great judgment, planted his level on ground sufficiently high
to enable him to see over the head of any grazier in the land; but
his clever assistant, as soon as he perceived that all was right,
had to take to his heels, and make the shortest cut he could to the
high road.
In another instance, a reverend gentleman of the Church of England
made such alarming demonstrations of his opposition, that the
extraordinary expedient was resorted to of surveying his property
during the time he was engaged in the pulpit, preaching to his
flock. This was accomplished by having a strong force of surveyors
all in readiness to commence their operations, by entering the
clergyman’s grounds on the one side, at the same moment they saw him
fairly off them on the other, and, by a well-organised and
systematic arrangement, each man came to a conclusion with his
allotted task just as the reverend gentleman came to a conclusion
with his sermon; and when he returned to his orthodox “jolly full
bottle,” the deed was done — the sinners had all decamped,
“And, like the baseless fabric of a vision,
Left not a wreck behind.” |
These are a few specimens of what is really a very great hardship,
and a hardship which might easily he prevented by Parliament. Whenever a measure of importance to the public comes to such a stage
as to render surveys necessary, in order to comply with the standing
orders of either branch of the legislature, the parties should he
enabled to comply with those orders, or it is manifestly the old
plague of the Israelites re-enacted — making bricks without straw.
At last, however, the business was all completed, and the share list
being filled, a bill to enable the Company to make a Railway from
London to Birmingham was read a first time on February the 20th,
1832, and a second time on February the 28th, 1832, after a division
of one hundred and twenty-five to one hundred and forty-six. It went
into committee in the Commons, April the 5th, 1832, and witnesses
were examined till the 13th of April; the committee then adjourned,
and the examination was resumed on the 21st of May, and on the 5th
of June the bill passed the committee, after the examination of
nearly a hundred witnesses of various kinds, among whom were
merchants from London and Birmingham, manufacturers, carriers by
land and water, farmers, gardeners, graziers, &c.
It may safely he said that no private bill was ever more strictly
scrutinized than was that of the London and Birmingham Railway; the
opposition to it being confined more to the cross-examination of the
witnesses in its favour than in producing any direct evidence
against is, which, it must be confessed, would have been rather a
difficult task. There was not a single fact proved against, the
great utility of the measure, while its advocates clearly
established in its support the following important points, viz. —
that the exporting of goods suffered material loss and great
inconvenience by the present slow mode of traffic — that goods for
the Baltic trade were often detained by the frost for the whole
winter, through a very short delay in shipping them — that
considerable orders were frequently lost from the impossibility of
completing them in time — that merchants keep 1arge stocks of many
sorts of articles in London to meet these emergencies, at a
consequent outlay and loss — that some particular trades have been
almost ruined through the impossibility of getting goods forwarded
in time, the coach proprietors having refused to take articles of
considerable weigh — that nothing is so invaluable in the export
trade as expedition and certainty — that in fancy articles it is
almost indispensible, orders being frequently sent subject to the
condition of their being shipped in a particular vessel — that
returns of money were sometimes made in eighteen months instead of
nine; through this delay in the shipment of the goods ordered — that
farmers would be able to send to London a different kind of produce
altogether, and a much better one, particularly lambs, calves, dairy
produce, &c., saving also a great expense in their carriage —
besides which, cattle were often driven till their feet were sore,
and they could go no further; they were then sold on the road for
what they would fetch: in the same manner, sheep were continually
being left in every town on the road at a ruinous sacrifice in price
— that many estates along the line of railway would be increased in
value at least thirty per cent. — the consumer being also benefited
as well as the producer.
It was also proved in evidence — that killed meat was repeatedly
putrid in summer before it could be sent to the proper market — that
the cost of carriage limited the vast supply of manure to a short
distance round London; whereas, by a railway, its application would
be most materially extended — that all cattle became deteriorated
considerably when driven even a moderate distance to market, and
produced a proportionately less price; for instance, a sheep driven
eighty miles lost eight pounds in weight.
In addition to the speed and comfort of railway travelling, the cost
would be reduced; a person living at Malvern would require sixteen
hours and a half to get to London, and pay forty-three shillings;
while, by the railway, he would be eight hours and a half, at a cost
of thirty-two shillings.
In these days of political agitation the rapid transmission of
bullion forms a subject of considerable importance, and even one
hour saved would be sometimes the means of preventing the stoppage
of a hank. Marked evidence was given to this effect.
In like manner, the rapid conveyance of troops was most essential. It was clearly shown, that a less number would be required in any
tract of country possessing railway conveyance, as they could he
concentrated on any given spot, in aid of the civil power, in the
same or shorter time than could now be done with a larger number of
men; and the fact was stated, that a regiment of eight hundred men,
and a large quantity of baggage, were only three hours in going from
Manchester and being shipped at Liverpool.
On the Leeds and Liverpool Canal, being the one most interfered with
by the Liverpool and Manchester Railway, the traffic had actually
increased at the time; and it was a curious fact, that, by the Stamp
Office returns, there was one more coach licensed at Liverpool and
Manchester the year after the railway was opened than the year
before. Every coach but one had been taken off the road between
those towns, but they were still running with the addition of one at
the two termini, for the purpose of feeding the railway.
It was also shown, than so invariably had it been found that land
was benefited by a railway passing through it, that in
advertisements for the sale of estates, this circumstance generally
formed a part of the advantages detailed — then, again, there were
the vast sums expended in labour — the materials bought from the
surrounding country — the lowering of the poor rates, not only by
the employment given to the local population, but by the large
payments to these rates by the railway companies themselves. The
extensive cuttings were also taken advantage of for draining by the
adjoining occupiers, and altogether new life was infused along the
whole extent of country through which the works were progressing.
The above is a short abstract of the leading points which were
proved in evidence before the House of Commons; it now remains to be
stated what the probable cost of this great work would be, and what
return for their risk and outlay the proprietors might reasonably
expect — the Estimate laid before Parliament was as follows: —
|
£ |
£ |
Excavations
and Embankments . . . . . |
179,000 |
|
Tunnelling
. . . . . |
250,286 |
|
Masonry . .
. . . . |
350,574 |
|
Rails,
Chain, Keys, and Pins . . . . |
212,940 |
|
Blocks and
Sleepers . . . . |
102,960 |
|
Ballasting
and laying Rails . . . . |
102,960 |
|
Fencing . .
. . |
76,032 |
|
Land . . .
. |
250,900 |
|
Water
Stations and Pumps . . . . |
3,600 |
|
Offices,
&c. . . . . |
16,000 |
|
Locomotive
Engines, Wagons and Coaches . . . . |
61,000 |
|
Contingencies . . . . . . |
294,648 |
|
|
|
2,500,000 |
Before drawing to a conclusion with the present work, we shall more
particularly allude in the increase which has taken place in this
sum. It will, therefore, he sufficient at present to say, by way of
explanation, that in all undertaking of this kind, there are certain
works which are of a fixed nature, and which can be fairly taken at
the current prices of the day; but there are also others variable
both in quantity and price.
For instance, the engineer knows he has, at least, a certain
quantity of earth to move, and that, as he crosses over or under a
given number of public highways, he must have a determinate number
of bridges. All these things are positive data for an estimate, and
constitute the principal sums in what are called the contract works;
these formed an item of £1,649,155 in the revised estimate of the
engineer, and they were actually let for £1,62l,821 or £27,334 below
the estimate; to this, £76,160 has to be added, for the extension
from Camden Town, where the railway originally began, to Euston
Square.
From the great increase in prices, which took place almost
immediately after the letting of the works, no less than seven
contracts were thrown on the Company’s hands, and of course these
were the most difficult and expensive parts of the works, and in
each case, the directors had to purchase all kinds of implements and
materials at a vast expense, including five locomotive engines,
while, from the times at which these seven contracts took to
complete them, there was very little possibility of transferring
these implements (technically called the Plant) from one contract to
another. This, although a very expensive process, was the only one
to be followed, or the line could not be opened under at least a
year beyond the time contemplated.
It is a well-known fact, that, from the great rise in prices, there
is hardly one of the contractors who has made a sixpence by the
three years’ labour, and some have absolutely lost money, but have
spiritedly performed their engagements whenever it was possible for
them to do so. The difficulties of particular works will be adverted
to in a future place; in the mean time the reader may be reminded of
another class, namely, the variable one.
The contract works, consisting of definite portions of the whole,
being let, as the land agents advanced in their labours a series of
what are called extra works arose; these consisted of bridges over
private roads ― of bridges to join lands severed by the railway ―
of culverts, drains, watering places, new roads, gates, fencing,
approaches to bridges, &c., forming a large portion of the whole,
and which could only be ascertained as the agreements were entered
into between the owners of the land and the Company’s agents.
It is obvious the engineer can have neither a knowledge of the
extent of these, nor of their cost, except in a very general way; he
only gains full information as he has extracts sent him from time to
time from these agreements, showing what has been consented to on
the part of the company, and he then gives his orders for the
various works to be done. It is evident, therefore, that the total
amount of these constantly increasing and variable works, many of
them, as in the case of bridges with extensive approaches, costing
several thousand pounds, cannot be fully ascertained till the line
is nearly completed.
Among the variable items are also those denominated additional
works. These are the alterations of different kinds, which must
constantly arise during the progress of all great undertakings, such
as increasing the slopes in particular parts where, on cutting into
the ground, it is discovered to assume a different character to that
of the borings taken right and left of it, from which borings alone
could a judgment be formed in the first instance; in some cases
springs of water are cut into, and have to be drained, in others
rock is come upon, where no geological indications, or any result
from the borings, would at all lead to a suspicion of its proximity;
from similar causes bridges have to be enlarged in their
foundations, and where the slopes have been increased, in their
superstructure also; water has to be procured for the adjoining
occupiers of land at considerable expense; and there is a constant
and unavoidable increase in the outlay from these and other causes,
over which no human foresight can, by any possibility, have the
least control.
It could scarcely have been supposed that under the article of extra
works, the following curious specimen of the impositions which the
company has suffered, would have taken place. In one portion of the
line, on the Birmingham division, some land was passed through in
such a way, that it was evident the reverend proprietor
(considering, doubtless, that his own temporal advantage was
essential to the spiritual good of his parishioners) required, in
reality, no accommodation in the way of bridges at all. At the first
outset, however, he demanded five; but, in the coarse of the
discussion, come down to four, with an equivalent in the price of
the land. It was absolutely necessary to obtain the land, or the
contractors would have been stopped in their operations, so that,
after a great deal of argument, the company was forced to submit to
this enormity, and the agreement was signed, sealed, and delivered,
guaranteeing to the proprietors bridge at A, another at B, another
at C, and another at D.
Soon after the money had been received, the proprietor wrote to say,
he thought he could dispense with a bridge at A, and if the company
would give him about half its value, he would do without it; of
course, as this would save expense, it was agreed to, and bridge A
done away with, the proprietor receiving about half what it would
have cost in building.
When this quantity of hard cash had been a little time warming in
his pocket, he discovered he could do without bridge B, and offered
to commute that with the Company on the some terms as bridge A. This
being agreed to and paid for, he in succession found out that he
could dispense with bridges C and D on exactly the some terms; and
thus every bridge he had so pertinaciously demanded, were one after
the other found to be totally unnecessary, as every body knew very
well at first; but it is to be supposed that he found it a very
agreeable way of getting a few cool hundreds; at any rate, such are
the facts — he has been paid for all the four bridges, none of which
have been built.
There was no end to the enormous compensations demanded of the
Company where, in many cases, no injury was done; the necessary land
being estimated by the professional valuers on the most liberal
scale, keeping in view the fact that companies of this kind are
generally made a dead set at. Under this impression they gave in as
a full and ample sum for all that would be required £250,000,
exclusive of fourteen acres for the Euston Extension and Station
which cost £74,505. Now what is the fact? £620,000 has now been
paid, and there are yet some little outstanding claims remaining no
be settled — the Birmingham division averaging about £315, and the
London division £335 per acre.
Peers paid for their votes — opponents paid to gain their consent —
£3,000 given for a piece of land, and the enormous sum of £10,000 as
a compensation for consequential damages, when, instead of damages,
the land has been improved; these and similar transactions soon run
away with all reasonable estimates, and yet we firmly believe that
in every instance the best plan that could be devised was followed
to procure the land as low as possible, taking into consideration
that to gain time was in most cases the principle object.
One rather original character sold to the Company some land, and was
loud and long in his outcries for compensation, ringing the changes
on all sorts of damages which the railway could not fail of bringing
on him. Well his mouth at last was stopped; he was paid, and in a
few months a little additional land is wanted from the same
individual, when, surprising as it may appear, for some adjoining
parts of this land — so deteriorated by the railway, on which the
Company’s Works had brought such inevitable destruction, and for
which reasons so high a sum had been paid — he actually required a
much larger price than was given him before, and on the Company
expressing the surprise which was natural on hearing such a demand,
he very coolly replied, “Oh, I made a mistake than in thinking the
railway would injure my property; it has increased its value, and,
of course, you must pay me an increased price for it.”
Another reverend and afflicted proprietor complained bitterly that
his privacy was ruined — that his daughters’ bedrooms were exposed
to the unhallowed gaze of the men working on the railway — that he
must remove his family to a watering-place, to enable him to do which
he must engage a curate. All this was considered in the compensation
demanded, and paid; yet no curate has been engaged; no lodgings at a
watering-place taken; the unhappy family have still dwelt in their
desecrated abode, and borne with Christian-like resignation all the
miseries heaped upon them. The gilding of the pill, it seems, has
rendered it palatable, and we have no doubt that, if his daughters
have a back window as well as a front one, he would he exceedingly
glad if a railroad was carried across that at the same price.
Sometimes, however, either by good fortune or artifice, the
unconscionable attempts of the landowners were frustrated. We
remember a case which, although the amount involved was
inconsiderable, may suffice to show the animus. The drainage of a
road was demanded from the Company, and the claimant would have
undertaken it for a sum of money to be paid him. It appeared,
however, that the Company could do it much cheaper by taking the
drain across the corner of one of his own fields; this he of course
refused to permit. Matters stood thus when he happened to be called
to London, and after his return discovered one fine morning, that
the Company had made his drain for him their own way, having in fact
quietly tunnelled through the comer of his field without committing
a trespass.
The remaining part of the Parliamentary evidence which may be
adverted to is, the probable result of the traffic to he expected on
the line. Some time before the application to Parliament, the
Company had secured the able services of Captain C. R. Moorsom, R.
N., as one of their secretaries, and it was on a new and original
plan of his that the writer of this work calculated the traffic then
existing on the main roads and surrounding country, which would be
available to the railway when opened. In ascertaining the data for
this he travelled no less than two thousand miles.
The way in which these things are usually got up for Parliament is
so vague and undetermined, as to merit no other name than a guess,
and not a good one either; hence has arisen the common saying with
all great undertakings of this kind, “halve the receipts and double
the expenditure if you wish to know any thing about it.” In the
present case, however, the traffic was actually counted on the roads
during a fortnight, and the results thrown into a table, to which
were added the probable traffic now existing, which at any rate
could come along the line in less time, and for less money than by
any other route; by this means, and by using the Stamp Office
returns for all that coaching which was not actually counted on the
direct road, a sure foundation was formed for a correct
determination of what could be done, and as no increase on the
traffic already existing was assumed for the additional facilities
which the railway would afford, it is fair to conclude that the
estimate is not too large, particularly as only a part of the canal
traffic — namely, light goods — was taken into account.
The bill was read a third time in the Commons on the 19th of June,
1833. Its first reading in the Lords was on the 19th of June, the
second reading on the 22nd of June. No division took place on
either, and it was sent to the committee of the Lords on the 22nd of
June, where a similar mass of testimony was again gone through for
seven days, and, notwithstanding the overwhelming weight of evidence
in favour of the measure, and the total absence of all reasonable
testimony against it, the following, among other members of the
hereditary legislature, resolved on breaking the bill, after all the
expenses which the Company had been put to:—
ABINGDON,
BEAUCHAMP,
BEAUFORT,
BROWNLOW,
CLARENDON,
COLVILLE of Culross,
DIGBY,
HASTINGS,
KENYON,
MACCLESFIELD
MOUNT EDGECUMBE,
MUNSTER,
SOUTHAMPTON,
VANE,
VERULAM. |
The following peers were distinguished as supporters of the bill:—
AYLESFORD,
CALEDON,
DARTMOUTH,
DENBIGH,
HOOD,
LYTTLETON,
NORTHWICK,
SLIGO,
SUFFIELD,
WHARNCLIFFE. |
Lord Brownlow headed the opponents of the bill, and knowing that if
evidence was attempted to he produced against the measure, its
weakness would but add to the strength of those who were promoting
it; he determined to “knock it over,” as he elegantly phrased it, by
brute force alone, in which he succeeded; for on the 10th of July,
having mustered all his forces, (according to the approved practice,
that noses are the grand things,) the moment Mr. Follett, one of the
counsel for the bill, had concluded summing up in favour of the
measure, and when we expected our opponents to commence opening
their case against it, Lord Brownlow made the following motion; in
reading which, the peruser is requested to ascertain in which
language it is drawn up, whether English as spoken in the nineteenth
century, or as we may imagine it in use when the tower of Babel was
left off.
“That the case for the promoting of the bill having been concluded,
it does not appear to the committee that they have made out such a
case, as would warrant the forcing of the proposed railway through
the land and property of so great a Proportion of dissentient
land-owners and proprietors.”
This is one more example of the blessings of hereditary legislation. In the elective branch of our constitution, composed of men chosen
either from their influential position or their talents, and who are
obliged to possess some common knowledge of the current affairs of
life, — to these individuals it did appear that the measure was,
what now is universally allowed — namely, one of vital interest to
the community at large, and accordingly they passed it by a large
majority; but to the before-mentioned members of the hereditary
branch, who are not obliged to know anything, it did not appear that
such a noble undertaking should be suffered to proceed; ergo, if a
certain number of hereditary legislators have on unusual obtuseness
of intellect, and cannot see a thing when it is put before their
eyes, a great public company is to be stopped for twelve months from
pursuing a project of such vast importance to the whole country, in
almost every relation between man and man, and the twenty-five
thousand proprietors, some of whom have been laying eight years out
of their money, are to be put to the expense of no less than £72,869
before they are allowed to benefit the country by establishing one
of the greatest public works ever achieved by mortal man.
Yes, reader, in every half-yearly report of expenditure sent forth
to the twenty-five thousand proprietors, foremost in the items is
recorded the appalling fact, that public-spirited men, who are
willing to risk five millions of their money, and lay out of a part
of it for seven or eight years, in order to complete such a splendid
undertaking as the London and Birmingham Railway, must, before they
can obtain permission to commence this work, submit to place down
upon their records, as the first item of their outlay —
PAYMENT FOR OBTAINING THE
ACT OF INCORPORATION
£72,868.18s.10d.
The nature of the opposition, and the mode in which that opposition
was conducted, will be much better appreciated by the remark which
fell from one noble lord, as he came out of the committee room,
after the division by which the bill was lost, than by any more
lengthened explanation. The following speech, tolerably pithy and
significant, was spoken out with a warmth of heart, which showed
every one it was meant; it needs no comment. — “By G—d,” said the
noble lord alluded to, “it is one of the d—st rascally things I ever
saw in my whole political existence.”
We had now to commence afresh all our operations, this was done in
October, 1832, and plans and sections were deposited again with
Parliament by the 31st of November, corresponding as nearly as
possible with those of the preceding year, the only alterations
consisting in a slight change between Harrow and London, and an
alteration in the terminus of the railway by stopping at the
Hampstead road, close to its intersection with the Regent’s Canal,
where the Camden Town Station now is, instead of going nearly to
King’s Cross.
Much was said out of committee during the progress of the bill, on
the subject of o more direct line than that which had been chosen. Mr. R. Stephenson and Mr Gooch spent a great deal of lime in
investigating this question; examining the country and taking levels
in all practicable directions in order to ascertain the merits of
the route referred to. This was intended to branch off from the
present line near Tring, and leaving Aylesbury a little to the
south-west, passing near to, and on the easterly aide of Bicester,
thence on to Buckingham and Banbury, and crossing the river Avon
between Leamington Priors and Warwick, was to join the present line
again in the neighbourhood of Hampton-in-Arden.
The saving in distance, however, would not have exceeded four or
five miles, and in addition to the many difficulties and expensive
works on this route, the crossing of the valley of the Avon, near
Warwick, was at once a fatal objection, the 16 feet per mile, which
is now the maximum rate of inclination, except on the Euston
Extension, must have been abandoned if this line had been selected.
The crossing of the river Avon forms one of the basins, or lowest
points to be passed over, as we have before explained, and the
intersection of the high ground between it and Birmingham, called
the Meriden Ridge, one of the summits. On the present line the rate
of inclination, between the Avon and Meriden Ridge, is 16 feet per
mile only. Now, on the direct line, the Meriden Ridge must have been
crossed as well as in the present line, but in a less advantageous
place; for the distance between the high and low points ― namely,
the river Avon and the ridge in question ― would only have been
four miles, whereas on the present line it is eight miles. To have
gained 16 feet per mile on the direct line, as it was called, would
have been impossible without an enormous outlay; whereas it is
obtained on the present at a reasonable expense, this in itself was
a sufficient objection, inasmuch as the river Avon, near Warwick, is
very considerably lower than at Wolston, where we now cross it, and
the Meriden Ridge would have been intersected at a higher point than
at present, besides these high and low points being twice as near as
they are where the road now passes through. Hence it is quite
evident that a line in this direction, although the shortest by four
miles, would be encountered by such sudden and extensive variations
of level as to render it a permanently bad locomotive line as
compared with the one chosen.
The line by the way of Coventry, Daventry, Stoney Stratford,
Leighton Buzzard, Berkhampstead, and Watford, may therefore be
pronounced the very best line the country would admit of, and an
unobjectionable one for locomotive engines, having no rise greater
than 1 in 330, or 16 feet per mile, and this the opponents of the
bill were no doubt perfectly aware of; as they never brought forward
the direct line, or any other as being better than that which is now
executed.
Our bill passed the Commons’ committee, March 15, 1833, and the
Lords, April 29th, 1833, receiving the Royal Assent, May the 6th,
and the means the directors were obliged to resort to, must be left
to the imagination of the reader; suffice it to say, that no
variation, sufficient to account for the different features of the
case, took place in the numerical value of the assenting or
dissenting landowners, [See Lord Brownlow’s English (?) motion,
page
19.] between the time of the first application being thrown
determinately out by the Lords’ committee, and the time when our
bill was passed by them, without hearing any witnesses, making any
opposition, or, in fact, doing any thing but going through the
necessary forms of the Upper House.
Although we have found during the progress of this great work
numerous and severe difficulties, there was nothing to indicate any
thing like what we have experienced, and without expending vast sums
in boring, they could never have been anticipated. The district
through which the line passes is peculiarly interesting in a
geological point of view, and through the railway crossing the
different strata, at nearly right angles, it probably intersects a
greater number of formations than any other line will do in the same
distance.
The strata which are crossed extend from the London clay to the
borders of the Coal Measures, and the various deep cuttings and
tunnels show most interesting sections of each formation. These have
had considerable attractions for the geologists, and have been very
numerously visited; they are now, however, becoming rapidly a sealed
book; for, as the various works successively approach completion,
the sides of the excavations and embankments are either covered with
turf, where it can be got, or, where it cannot, with good soil, and
sown with grass seed; this method of finishing the slopes being a
great support to them, through the tenacity of the roots.
The rivers forming the basins are generally near the division of two
formations.
The London clay is penetrated by the Primrose Hill Tunnel, and
presents a close, compact, and dry appearance. This tunnel was
perfectly free from water, but a more than ordinary thickness of
brick lining was necessary, arising from an extraordinary pressure,
probably caused by the swelling of the clay on exposure to the
atmosphere. The plastic clay and sands were well shown in the deep
cuttings at the first summit from London, in the neighbourhood of
Oxhey, before approaching Watford.
At Watford, near the Colne, the chalk first made its appearance
underneath the plastic clay. It extends along the line to the Tring,
or second summit, where a good section of the lower chalk is given
by the deep cutting at that place.
The Watford and Northchurch Tunnels give also good sections, the
former of the upper chalk. A coating of gravel, varying in
thickness, overlies the whole of the chalk, and, in some instances,
forms the actual surface for arable purposes; and, if we may judge
from their very flourishing condition, this appears to agree well
with turnips. The gravel is most abundant in the neighbourhood of
Watford, covering the upper chalk, which in many places it
penetrates, or, in other words the large fissures, or rents in the
chalk, are filled with the gravel, and as this latter material was
very loose and mobile, it was the occasion of much difficulty and
danger in the excavation of the Watford Tunnel; for, at times, when
the miners thought they were excavating through solid chalk, they
would all in a moment break into loose gravel, which would run into
the tunnel with the rapidity of water, unless the most prompt
precautions were taken.
As the lower chalk is approached, the gravel and also the flints
disappear; and at Tring there is scarcely a trace of either. The
strata at the bottom of the cutting almost approaches chalk marl. The great thickness of the chalk is very clearly shown by the long
line of intersection it makes with the railway, which crosses it
here nearly at right angles.
In descending from the Tring summit towards Leighton Buzzard, the
chalk marl, green sand, and weald clay formations are met with; but
they are only intersected by the shallow cuttings. The presence of
these formations is, however, made sensibly evident by the birdlime
properties of the soil, which by no means facilitates the field
labours of a Parliamentary campaigner when time is an object of
great importance. In such cases it is usual for all surveying
parties, when in motion, to attempt to run; but in this district
walking was a toilsome matter, and running quite out of the question
altogether.
At Leighton Buzzard the line crosses the iron-sand formation, which
is found here in cliffs and abrupt hills. One of these is pierced by
the Leighton Buzzard Tunnel. The nodules of ironstone found mixed
with the iron-sand forms some of the best ballasting in use upon the
whole line.
The oolitic series are next crossed, making their first appearance a
little to the northward of Leighton Buzzard, and extending to the
crossing of the river Avon at Wolston. This distance includes the
Blisworth and Kilsby summits, as also the basins of the Ouse and
Nene.
The Blisworth summit is made passable for the railway, by a deep and
long cutting through the oolitic limestones with beds of shale
intervening, and the Kilsby summit is passed by means of a tunnel,
two thousand four hundred yards long, chiefly through lias shale
containing much water, and partly through a stratum of diluvial sand
full of water. This, as will be seen hereafter, has been a source of
much difficulty and expense in the execution of this work.
The organic remains, both at Blisworth and Kilsby, are very
numerous, particularly at the former place. In some parts of the
excavation for Kilsby Tunnel, there is hardly a cubic inch to be
found without shells and other remains presenting themselves to the
eye, in all directions, and in all stages of preservation; and, as
the earth taken out here has been principally laid into spoil, there
will be ample opportunities, for some time yet, for their further
examination, which we are certain would well repay either the
scientific inquirer or the cabinet collector.
The red marl, or new red sandstone, is first intersected at the
river Avon, which at this place, appears to separate this formation
from the lias shale, and the red marl continues to Birmingham. Good
geological sections were shown at Coventry, Berkswell, Yardley, and
Birmingham, and also by the Beechwood tunnel through the Meriden
Ridge.
Till within a late period this formation has been generally thought
destitute of organic remains, and it is now a doubt with many
whether such really exist. There are, however, some facts which lend
strongly to confirm a belief in the presence of these remains, and,
at all events, we can safely affirm that the formation is not
totally destitute of organic matter, inasmuch as a live toad was
discovered in the deep cutting near Coventry, safely housed in a
small smooth cell, in the centre of a mass of red sandstone rock,
perfectly solid, with the exception of the small cavity occupied by
the toad.
Fragments of silicified wood have also been found in the Hearsall
Common cutting, and we believe in the road excavations in the
neighbourhood of Coventry; but it is a matter of great doubt whether
these belong to the red sandstone or to the superstratum of diluvium
which overlies some parts of the red marl. We have never seen them
in situ, but Dr. Ward, and Mr. Gooch, the assistant engineer of that
district, found some of this wood lying loose in the Hearsall Common
Excavation, where the red rock extends almost to the surface.
At Wolston, and near Tring, Roman vases and vessels have been met
with in the railway cuttings; in fact, as may naturally be supposed,
in works of such magnitude, hardly an excavation of average depth
has been got out without some relic of ancient days turning up, or
some geological specimen worth preserving, having been found, and in
the largest excavations they have been both numerous and interesting
in the highest degree.
The following are the different contracts for the principal works
along the line, including all the formation of the embankments and
cuttings, the erection of bridges, and the laying of the rails. The
materials for the road — namely, the rails, chairs, blocks,
sleepers, &c., were not provided by the contractors who laid them
down, but were furnished by the Company in order to insure their
being of is good quality.
Name of Contract |
Original Contractor |
Date |
Price £ |
Second Contractor |
Euston Extension |
W. and L. Cubitt |
Dec. 1835 |
76,860 |
|
Primrose Hill |
Jackson and Sheddon |
May 1834 |
119,987 |
L&BR, Nov. 1834 |
Harrow |
J. Nowell and Sons |
May 1834 |
110,227 |
|
Watford |
Copeland and Harding |
May 1834 |
117,000 |
|
King’s Langley |
W. and L. Cubitt |
Sept. 1835 |
38,900 |
|
Berkhamsted |
W. and L. Cubitt |
Sept. 1835 |
54,660 |
|
Albury |
Richard Parr |
Sept. 1835 |
14,500 |
|
Tring |
Thomas Townshend |
Sept. 1834 |
104,496 |
L&BR, Oct. 1837 |
Leighton Buzzard |
James Nowell |
Sept. 1835 |
38,000 |
|
Stoke Hammond |
E. W. Morris |
Sept. 1835 |
39,303 |
|
Bletchley |
John Burge |
Sept. 1835 |
54,500 |
|
Wolverton |
William Soars |
Oct. 1834 |
67,732 |
L&BR, June 1837 |
Wolverton Viaduct |
James Nowell |
Feb. 1835 |
25,226 |
|
Castlethorpe |
William Soars |
Oct. 1834 |
49,735 |
Craven, July 1835 |
Blisworth |
William Hughes |
Feb. 1835 |
112,950 |
L&BR, Dec. 1836 |
Bugbrooke |
John Chapman |
Feb. 1835 |
53,400 |
|
Stowe Hill |
John Chapman |
Feb. 1835 |
23,050 |
|
Weedon |
Edward Beddington |
May 1835 |
23,090 |
|
Brockhall |
J. and G. Thornton |
May 1835 |
34,157 |
|
Long Buckby |
J. and G. Thornton |
May 1835 |
42,582 |
|
Kilsby Tunnel |
J. Nowell and Sons |
May 1835 |
98,988 |
L&BR, Feb. 1836 |
Rugby |
Samuel Hemming |
Feb. 1835 |
59,283 |
L&BR, Nov. 1837 |
Long Lawford |
W. and J. Simmonds |
Feb. 1835 |
20,330 |
|
Brandon |
Samuel Hemming |
Feb. 1835 |
40,000 |
L&BR, Jan. 1838 |
Avon Viaduct |
Samuel Hemming |
Nov. 1835 |
79,070 |
|
Coventry |
Greenshields and Cudd |
Nov. 1834 |
101,700 |
L&BR, May 1837 |
Berkswell |
Daniel Pritchard |
Nov. 1834 |
53,248 |
|
Yardley |
Joseph Thornton |
Aug. 1834 |
68,032 |
|
Saltley |
James Diggle |
Aug. 1834 |
32,878 |
|
Rea Viaduct |
James Nowell |
Aug. 1834 |
13,644 |
|
It will be seen by the above that out of those thirty contractors no
less than ten have broken down, and the works have been completed by
a second party; this has mainly arisen from the great increase in
the price of labour and materials, which took place soon after the
principal ones were let, rendering it impossible for the contractors
to complete their respective works, without incurring considerable
pecuniary loss. When this was discovered, of course, a complete want
of energy soon became apparent, and the Company were under the
necessity, at whatever cost, of getting them into their own, or some
other persons’ hands as quickly as possible, as it was clear that
whatever additional outlay might become necessary on this account,
would be much more than counterbalanced by the time which would be
gained. In fact, the leading object at all times kept in view, was
the opening of the line as speedily as could he done consistent with
safety.
There is always one feature which strikingly distinguishes the
construction of railways from that of canals, and this is the
employment of the surrounding agricultural population. When the
reader is informed, that for nearly three years, from fifteen
thousand to twenty thousand men were engaged on this work, taken
almost invariably from the adjacent towns and villages, and that, in
actual labour, nearly four millions have been expended (in
earth-work, brick-work, brick-making, &c.) among the local
population, he will have some idea how this would influence
pauperism and the poor rates: whereas, in the making of canals, it
is the general custom to employ gangs of hands who travel from one
work to another and do nothing else.
These banditti, known in some parts of England by the name of
“Navies” or “Navigators,” and in others by that of “Bankers,” are
generally the terror of the surrounding country; they are no
completely a class by themselves as the Gipsies. Possessed of all
the daring recklessness of the Smuggler, without any of his
redeeming qualities, their ferocious behaviour can only be equalled
by the brutality of their language. It may be truly said, their hand
is against every man, and before they have been long located, every
man’s hand is against them; and woe befall any woman, with the
slightest share of modesty, whose ears they can assail.
From being long known to each other, they in general act in concert,
and put at defiance any local constabulary force; consequently
crimes of the most atrocious character are common, and robbery,
without an attempt at concealment, has been an everyday occurrence,
wherever they have been congregated in large numbers; but they were
so thinly scattered over the London and Birmingham Railway, that
their depredations partook more generally of a deceptive character,
and acts of open violence were rare.
These deceptions were sometimes not a little amusing, as for
instance, the following;— A navigator engaged on the Berkswell
contract, about ten miles from Birmingham, went one day into a
village public house, and made the enquiry, “Have you got any gin?”
laying great stress on the word gin; the landlord quickly responded
that he had plenty, “Oh,” said the navigator, “I am glad of that, I
have been to the other public house and broke him of all he had, I
wanted two gallons and he had only got one, so I have had to come
here for the other one.” The gallon was quickly measured out, and
put into that which he had before in the bottle. He was than very
coolly walking out of the shop; mine host, however, soon reminded
him that there was a little process to go through which appeared to
have escaped his observation — namely, the paying for the gin. To
this the “Navie” shrugged up his shoulders, and said he would pay on
Saturday night; Boniface, however, was not to be had quite so easy,
and the gallon measure was quickly refilled again out of the
“Navie’s” bottle, and he departed looking very indignant at not
being trusted till his pay-night. It only remains to inform the
reader, that what he had originally in the bottle was a gallon of
water — not a gallon of gin — and consequently his ingenuity was
rewarded by his getting clear off with half a gallon of “mine host’s
best cream of the valley,” in a state quite ready for drinking.
It would be a curious thing, if we could analyse the ideas of those
residents in the central parts of England, who have outlived the
ordinary limit of human life; those, for instance, whose memories
will carry them hack for seventy years. We have it from indubitable
authority, that within that period, the carrying trade for Yorkshire
and Lancashire, from Birmingham and the West of England, was worked
by Mr. Worthington with pack horses! as is done in the present day
in South America and other countries.
When the canals were opened it was suggested to him by the late Duke
of Bridgewater to establish boats; after some discussion this was
done, and the wants of Liverpool, Manchester and Birmingham, were
supplied by two boats, weekly, each way, which two boats not being
able to procure cargoes at Birmingham, went on to Wolverhampton to
complete their load; there are now, in addition to other facilities,
150 boats going through the some route.
In these olden times the Edinburgh coach to London, took fourteen
days to go this journey of 400 miles; the London to York took six
days to go its journey of 200 miles; the London to Exeter thirteen
days for 175 miles; and as late as 1742, the London to Oxford
managed to get to High Wycombe in ten hours, when the passengers
were carefully put to bed, and were allowed to continue their
journey in the morning. From this system we improved till we got to
a horse per mile one way, for a fast coach, for the cost of £25
each, and £150 for the coach; the receipts for which must be £5 per
double mile to pay the proprietors, and now even those exertions are
in their turn despised, and we have doubled, and will probably
treble the utmost that ever this expensive system could accomplish.
It will take of course some time to clear away long-established
customs; ― the curfew bell still tolls at Tring, close to the London
and Birmingham Railway; we hope the enginemen will not, through fear
of William the Conqueror, put their fires out at the ominous sound.
There is nothing in the construction of a railway any more than in
other affairs to show, that politics and honesty are in any way
connected. There are some reformers along our line who might well
begin by reforming themselves. One of these owned a sand hill near a
part of our works, and the material being a very good article for
ballast, the contractor asked the Railway Company, as a favour, to
treat for its purchase, under the powers of their Act of Parliament. This was done, and the moderate sum of £300 per acre, turned out to
be the demand of the proprietor. Of course the Railway Company at
once desisted, telling the contractor they would have willingly
assisted if they could, but on no considerations would they become a
party to this enormous demand, for what would be only a temporary
occupation. The contractor thus left upon his own legs, has found
means to get the said sand hill for £30 per acre, or just one-tenth.
The labours of the engineers, it is almost needless to state,
commenced long before the ground was broken. In fact, many of them
were employed in getting assents to our Bill, from the land-owners
who have shown themselves so wise in their generation. Then came the
various surveys and levellings required for fixing the line; then
the designing and drawing of bridges and other works in detail, in
order that approximate estimates of costs might be laid before
Parliament. When the period arrived for executing the works, it was
necessary to calculate the time which those of the greatest
magnitude would be likely to occupy, so that they might be let to
the contractors in such an order, that the whole might he
simultaneously completed, as for as possible, with reference to the
successive openings of portions of the whole line, which was
desirable, not only as a measure of pecuniary interest, but to get
the road in good repair, and to drill every one into his particular
duty. The order of letting the contracts having been decided,
assistant and sub-assistant engineers were appointed, as required,
upon the general principle of dividing the whole line into four
districts, and each district into three lengths, so as to place
about ten miles under the immediate superintendence of one
sub-assistant engineer; thus each assistant engineer had three
sub-assistants, being all subordinate to one engineer-in-chief.
When any particular portion of the works was to be prepared for
letting, the sub-assistant engineer, under the direction of his
superior, had to revise all the Parliamentary surveys and levels
with the utmost care, and draw to a large scale very accurate plans
and sections of the land, in order that the quantity of excavations
and embankments might be obtained as nearly as possible. It was also
necessary to make detailed plans and working drawings, elevations,
and sections of every bridge and culvert which curried a road or
stream across the railway, or which carried the railway over a road
or stream. These, being roughly sketched by the engineer on the
spot, were sent to the chief office, to be fairly drawn out with
full details, and upon a uniform system laid down by the principal
engineer; the object being to put them in such a shape that parties
wishing to tender for any of the contracts might clearly understand
the nature of the works, and make accurate estimates from the
drawings without difficulty. The limits of each contract were
defined with reference to the most convenient execution of the
works, regard being had to the disposition of the earth work, so
that each contractor might make his embankments with the materials
yielded by his excavations, as far as it was practicable; care being
taken that the aggregate amount of the contract should not exceed
the means of the generality of persons in the habit of tendering for
such works.
A contract of £100,000 was thought a very responsible undertaking;
and the experience of the London and Birmingham Railway has shown
that those amounting to or exceeding that sum, have called for
extraordinary exertions. Of these there have been seven upon the
whole line; four were very soon relinquished by the parties
originally contracting for them, and the remaining three executed
with great difficulty.
The drawings being completed, and the limits of the contracts fixed,
detailed specifications were drawn up, under the engineer-in-chief’s
superintendence; the whole was then submitted to the inspection of
parties willing to tender for the works, who on an appointed day,
delivered in their respective estimates; and the lowest tender was
generally, but not invariably, accepted, regard being always had to
the character and means of the parties. The whole of these extensive
and important works were let at prices which were under the estimate
of the engineer-in-chief.
The original contract drawings were signed by the engineer-in-chief
and the contractor, and preserved as documents. Three copies of
each, however, had to be made out — one for the use of the
committee, one for the engineer-in-chief, and one for the assistant
engineer.
When it is borne in mind that the engineering works of the whole
railway, in accordance with the above system, were divided into
thirty separate divisions, each requiring its own set of drawings,
estimates, and specifications, and that all these works, with two
unimportant exceptions, were let to various contractors, between
May, 1834, and October, 1836, it will be perceived that an extensive
and efficient drawing establishment must have been kept at work. Speaking in round numbers, we may say, that for eighteen months, not
less than thirty drawings per week, each requiring two days’ work
from one pair of hands, were turned out from the engineer-in-chief’s
office.
As the undertaking proceeded, talent of a higher order was brought
into requisition — the heaviest and most difficult parts of the work
being, in several instances, thrown on the Company’s hands by the
contractors, after much loss of time, which could only be regained
at a vast sacrifice of money. We shall state a few of these cases. Take, for instance, Primrose Hill tunnel. The construction of this
was attended by difficulties of a rather peculiar kind which deserve
to be noted, as they may tend to point out the most advantageous
mode of executing works corresponding in nature and magnitude.
The tunnel is carried underneath the ridge of high ground which
extends from Hampstead to Primrose Hill, near Chalk Farm, and
consists of the blue clay belonging to the London clay formation of
geologists. The extreme mobility of this material, when in the
slightest degree moistened, is notorious among those who have had to
execute engineering works in the neighbourhood of London. In
tunnelling, therefore, the greatest care was required, that the
excavation as it advanced might be properly supported. For this
purpose all the means usually adopted in tunnelling were employed;
but the works had not proceeded far, before it became apparent that
timbering and supports of ordinary strength were altogether
insufficient, the dimensions of the tunnel for exceeding anything of
the kind previously executed in the same material.
The tunnel which was attempted of somewhat similar dimensions
several years ago, near Highgate, ended in a complete failure;
because the great pressure of the clay was not adequately resisted
by the lining of brickwork. Having an example of this kind before
them, the engineers were naturally led to prepare themselves with
every precaution calculated to avert a similar result. In the
progress of the works, therefore, the first step was to excavate in
advance of the brickwork about nine feet, and support this portion
by the strongest timbering, for the purpose of preventing the
falling of the clay. The bricklayers then proceeded to build the
lining of brickwork which was carefully laid with the best mortar.
As the works advanced, it was soon discovered that the mortar was
squeezed from the joints, and the inner edges of the bricks were
found to be in contact; thus by degrees the bricks were grinding to
dust, and the dimensions of the tunnel insensibly, but irresistibly,
contracting. The evil was augmented by the form of the bricks,
which, according to the custom in and near London, were made with
hollow surfaces, and consequently by no means adapted for
withstanding pressure, as their edges only could come in contact. The difficulty hence arising was one which seldom occurs in
tunnelling, the completion of the brickwork being generally
considered to make all perfectly safe.
To obviate the impediment it was immediately suggested that very
hard bricks should he used, and Roman cement substituted for mortar. The cement, it was anticipated, would set hard previous to the
external pressure becoming so great as to bring the bricks into
actual contact with each other; thus the whole surface of the brick
would withstand the pressure, and not a small portion of it, as in
the case just described, where the bricks were pressed together
before the mortar had become sufficiently hard. These expedients,
the use of Roman cement, and harder bricks, fully answered the
intended purpose; but it was deemed prudent, also, to increase the
thickness of the brickwork, in order to remove the slightest risk of
accident, or symptom of weakness in the arching. The thickness of
the brickwork in some portions of the tunnel is 18 inches, but in
the major portion, 27 inches, all of which, with the exception of a
few yards, is laid in Roman cement.
The extraordinary pressure which the London clay exerts above others
is an interesting object of enquiry; for neither its specific
gravity, nor external appearance, would justify us a priori in
concluding that it was likely to produce excessive pressure upon the
brickwork in the manner described, and this too after the completion
of the arching. In ordinary tunnelling, where the material is of a
gritty nature, which is the case with the generality of clays, or
where it partakes of a loose, rocky character, the fragments cannot
of necessity move amongst themselves with freedom, and generally may
he considered to wedge each other into particular positions, thus
lessening the weight with which they press downwards by a quantity
equal to that which would represent the friction or resistance to
movement.
If this view be correct, it appears reasonable to conclude, that, in
the case of a tunnel, the pressure which the surrounding mass
exerts, is in some inverse proportion to the friction or resistance
to motion amongst the parts themselves of which it is composed. We
ought, accordingly, to find the fragments of the London clay moving
with extreme freedom against each other; and this is eminently the
case, as is continually evinced by the flat slopes which it is found
necessary to give to the sides of all excavations made in this
peculiar clay. The general inference to which these considerations
reach seems to be that the difficulty of tunnelling, or the strength
required in the timbering and brickwork, through different
materials, is proportioned to the rate of slope found necessary in
excavating through the same materials respectively.
These, and other difficulties, were contended with at such an
enormous expense, that this one contract, which was let in the first
instance at £120,000, cost no less than £280,000, although every
attention to economy was used, in all cases, through the whole
progress of the work.
Another instance, in which difficulties of no ordinary magnitude
were encountered, was at the Kilsby Tunnel, about six miles on the
London side of the Rugby station. This tunnel is about 2,400 yards
long, and was originally intended to be chiefly built eighteen
inches thick; but it was found necessary to increase this, in most
cases, to twenty-seven inches; and the whole has been built in
either Roman or metallic cement.
The works were commenced about the middle of June, 1835, by J.
Nowell and Sons, contractors; but such serious difficulties were met
with, at an early stage of the proceedings; that they gave up their
contract on the 12th of March, 1836, and nearly the whole had to be
performed by the Railway Company. Previous to the commencement of
the works, trial shafts were sunk in several parts of the line of
the tunnel, in order that the nature of the material through which
it would have to pass might be ascertained, and it was found to be
generally lias shale, with a few beds of rock, in some places dry,
in others containing a considerable quantity of water.
In sinking the second working shaft, it was found that a bed of sand
and gravel, containing a great quantity of water, lay over part of
the tunnel, and this was such a perfect quicksand, that it was
impossible to sink through it in the ordinary way. By repeated
borings, in various directions near this part of the tunnel, the
sand was discovered to be very extensive, and to be in shape like a
flat-bottomed basin, cropping out on one side of the hill. The
shafts had accidentally been sunk on each side of this basin, so
that it had entirely escaped notice until the sinking of the working
shaft.
Mr. Stephenson was led to suppose that the water might be pumped
out, and that under the sand thus drained the tunnel might be driven
with comparative facility; this proved to be the case, but the
expense was of course enormous. Engines for pumping were erected,
and shafts sunk a little distance out of the line of the tunnel. These shafts were carried through the sand by means of wooden tubbing, and from them, headings were driven into the quicksand to
allow the water to flow with freedom to the pumps. The pumping was
continued nearly nine months before the sand was sufficiently dry to
admit of tunnelling, and during a considerable portion of that time
the water pumped out was two thousand gallons per minute.
When the sand became sufficiently dry to allow the working shafts to
be sunk in the ordinary manner, headings were driven to each of them
from the pumping shafts at the level of the bottom of the tunnel, by
which means the water was prevented, not only in the shafts, but in
the tunnel, where the work was going on.
The quicksand extends over about 450 yards of the length of the
tunnel, and its bottom dips to about six feet below the arch. Great
care was required, during all the time of getting through this part,
that the sand did not run, it being in some places so fine that
great quantities would slip through a very small crevice. It has
been effected, however, with only one run of importance.
In May, 1836, one of the large ventilating shafts was commenced, and
completed in about twelve months. This shaft is sixty feet in
diameter in the clear, and 132 feet deep; the walls are
perpendicular, and three feet thick throughout, the bricks being
laid in Roman cement. The second ventilating shaft is not so deep by
thirty feet. These immense shafts were all built from the top
downwards, by excavating for small portions of the wall at a time,
from six to twelve feet in length, and ten feet deep.
In November, 1836, a large collection of water burst suddenly into
the tunnel, in a part where there were no pumps; of course it rose
very rapidly, and, in order to prevent the ground being loosened by
it at the far end, where it was excavated, a rather novel mode of
building the brickwork was resorted to, as the getting in of the
brickwork was the only thing to save it. This method was by forming
a large raft, and on this the men and their materials were floated
into the tunnel, and with considerable difficulty and danger
performed their task.
All the impediments were at last conquered, and the tunnel finished
in October, 1838; but, of course, the expenses were increased to a
very great extent. The work was let for £99,00, and it has cost more
than £320,000, or upwards of £133 per yard.
To give some idea of the magnitude of this work: — There are thirty
millions of bricks used in it, which, at ten hours for a working
day, if a man counted fifty in a minute, it would take one thousand
days to get through them all. There is above a million of bricks in
the deepest ventilating shaft, and its weight is 4,034 tons.
The weight of the whole tunnel is 118,620 tons; or it would freight
four hundred ordinary merchant ships, of about three hundred tons
each; and if these bricks were laid end to end, they would reach
4,260 miles.
It is not a little curious to turn back, and watch the first
beginnings of a work of such magnitude as this railway, which will
cost more than £5,000,000. In November, 1830, there was to be one
line of rails only, and the work was to be done for £6,000 per mile. The capital was then one million and a quarter, and no greater
velocity contemplated than eight miles on hour. Shares got up to
nine and ten premium on the above prospectus, at which many hundreds
were sold. Then it was determined to have two lines; and at that
announcement the shares fell directly to a discount. In 1831, the
proposal was for four lines; and the capital was £3,081,642, with a
proviso that the land, although taken at £300 an acre, was not so
high as that required for the Liverpool and Manchester line, through
the enormous and unreasonable sums required by some proprietors
beyond the real value of the land. We wonder what the speculators of
those days would have thought, if they could then have been informed
what the real cost of the present two lines would be. One thing is
certain, there would not have been a railway between London and
Birmingham for many a year.
Resuming our account of some of the leading difficulties, we may
notice the Wolverton embankment, nearly in the centre of which
stands the Wolverton Viaduct. On the north side of the Viaduct, the
material is composed of blue clay, lias limestone, gravel and sand.
This part of the embankment stood very well except in one place,
where it slipped, not on account of its being composed of bad
material, but from the ground itself actually yielding, when the
weight of the embankment came on it. The length of the embankment
being one mile and twenty-eight chains, (deducting the Viaduct) and
the height of a great part of it forty-eight feet, some accidents
were to be expected, especially in bad weather; but no one could
have imagined what would take place on the south side of the
viaduct. Here the material, at the commencement, was composed of
sand, gravel, and blue clay. This stood very well; but when we got
deeper into the cutting, we worked out some black, soapy clay, very
wet; this was tipped on to a turf bottom, and the weather being also
very unfavourable although every care was taken to mix dry stuff
with the wet material, yet there occurred one of the worst, if not
the worst slip along the whole line. Earth was tipped in for days
and days, and not the slightest progress was made; as fast, in fact,
as it was tipped in at the top it kept bulging out at the bottom,
till it had run out from 160 to 170 feet from the top of the
embankment; and at last a temporary wooden bridge was formed, and by wagoning the earth over this, the embankment between the slip and
the viaduct was formed, by first digging a trench five feet deep,
and nearly the whole width of the embankment, and forming a mound on
each side to prevent it from slipping.
In fine summer weather the bridge was removed, and that part of the
embankment, where the slip had been, was filled up; but away it went
again, just as it did before, and the yawning gulf appeared to be
insatiable. It was months before it was conquered, and this was done
at last by barrowing as much earth to the outer part of-the slip, as
would balance the weight on the top.
There seemed to be no end to the vagaries of this unhappy
embankment. There was a portion of alum shale in it, which contained
sulphuret of iron; this becoming decomposed, spontaneous combustion
ensued, and one fine morning we had the novel sight of a fifty feet
embankment on fire, sleepers and all, to the great surprise of a
host of beholders. The inhabitants of all the neighbouring villages
turned out, of course, in no small amaze on the occasion; and
various were the contending opinions as to the why and the
wherefore; some said, “The Company were hard up for cash, and were
going to melt some of the rails;” others, “that it was a visitation
of Providence, like the Tower of Babel.” At last one village Solon
settled the point.—“Dang it,” said he, “they can’t make this ere
railway, arter all; and they’ve set it o’fire to cheat their
creditors.”
Another troublesome and expensive part of the line was the Coventry
contract. This did not arise through any peculiar difficulty in the
nature of the work, but from the supineness and incapacity of the
contractor. The work went on without spirit or energy, and the time
was rapidly going by which would enable it to be completed with the
other parts of the line at that end; the opening of the railway
would hence be delayed, and it was difficult to foresee all the
consequences. In this dilemma the Company could do nothing but take
the work into their own hands; and by great exertions, and a
corresponding outlay, it was completed in time.
It was in this contract the toad was found, which has been before
alluded to. Mr. Gooch, the assistant engineer on that part of the
line, has kindly furnished us with the following account of
it:—
“During the progress of the excavations through the Park Gardens
at Coventry, on the line of the London and Birmingham Railway, at
about nine o’clock in the morning of the 16th of June, 1835, the
workmen were engaged in removing the material to the depth of eleven
feet from the surface, the upper portion of the excavation
consisting of — first a stratum of soil, eighteen inches thick, than
a mixture of sand and clay, three feet thick, and the remaining
depth of six and a half feet consisting of masses of new red sand
stone, sound and perfectly formed, somewhat severed by backs and
fissures, but still in large solid masses, obliged to be worked away
by means of iron bars and wedges, and frequently blasted by
gunpowder.
“Two of the workmen, John Horton and Thomas Tilley, having, by means
of an iron bar, loosened from the solid mass near the bottom of the
said eleven feet a piece of rock, about eighteen inches long,
fifteen inch wide, and five inches thick, it was lifted up by
Horton, and thrown by him towards the wagons which were in waiting
to receive the excavated material, and convey it to the embankment
which was forming across the valley of the Sherbourn; the piece of
rock, however, did not alight in the wagon, as was intended, but
fell by the side of it upon the bottom of the new formed excavation,
and was, by the fall, broken nearly through the centre into two
parts, which lay upon the ground an inch asunder.
“Thomas Tilley immediately took up one of the fragments, and threw
it into the wagon, and was on the point of taking up the other, when
his attention was arrested by the sight of a toad in a cavity or
cell of the remaining fragment; instead of taking it up he kicked it
with his foot, which caused it to fall out upon the ground; he then
called to his companions, and told them that he had found a toad in
the stone; Horton having joined him, they examined the fracture of
the other piece of rock and found a corresponding cavity, so that
when the pieces were put together the stone was to all appearance
perfectly solid, yet there was an oval or egg-shaped hole in the
centre. The other workmen, to the number of thirty or forty, soon
collected to examine the toad. Its colour when first seen was a
light brown; in the space of ten minutes, however, it gradually
changed, and the bright brown became a black. The animal seemed to
labour under a severe oppression as from heat or weight, or both
combined, and gasped frequently. It was rather under the usual size,
but it was plump, and apparently in good condition. During the day
it remained in the possession of the men who found it, and was seen
by many persons, and was often exposed to the sun which was very
hot, and to the warmth of the hand; the head appeared slightly
injured, supposed to be occasioned by the breaking of the stone.
About four o’clock in the afternoon I visited the works; the toad
was shown to me, and I fitted one piece of stone upon the other
while the toad was in the recess. I found that the rock fitted
closely, and I could observe no appearance of an opening or fissure
of any kind into the cavity; the stone on every side appeared
perfectly sound and solid. A portion of the cavity was much more
round and smooth than the other, being, as I suppose, the lower side
upon which the toad had rested. Throughout the whole cavity there
was a thin black deposit or lining, but this was more visible on
that side which was most rounded, and there were evident marks where
the lining was scratched off, as if by the claws of the toad.
“The cavity was three inches long, and one and three-quarters inches
broad. The two pieces of the stone, with the toad in them, were
brought to my office that evening; and I endeavoured, by closing the
fracture of the stone with clay, to exclude the heat and air as much
as possible, in the hopes of keeping it alive as long as I could;
this I succeeded in doing more than three days. During that time,
however, it was frequently exposed, as there were many persons who
were desirous of seeing it; but it seemed gradually wasting away.
The injury in its head, also, became much worse, and doubtless
hastened its decay. It lived, however, nearly four days from the
time of its discovery.“
We suppose the above is the best authenticated account extant. It
was written out and signed by Mr. Gooch (now engineer-in-chief of
the Manchester and Leeds Railway), Horton, and Tilley, with a
witness to their signatures.
We will next draw the reader’s attention to the difficulties
experienced at Blisworth. This cutting is one of the largest on the
line, and according to the original estimate would have contained
800,000 cubic yards; in consequence, however, of the necessity which
was found of adding to the length of the wide part of the cutting,
which proved to be requisite during the execution of the work,
together with the material arising from numerous slips in the upper
part of the cutting, the total quantity removed approximated to one
million cubic yards, besides additions which were required to form
the adjoining embankments.
The material to he excavated consisted of clay and limestone. The
greatest depth is about 66 feet, and the total length a mile and a
half. The clay and rock may be described generally an running into
strata, not far from parallel with the line of rails, which are
arranged to rise from each end of the cutting towards its centre, at
an inclination of 16 feet in a mile.
The quantity of rock excavated was about one-third of the total
contents of the cutting; and a considerable portion of the
engineering difficulties of this work arose from the circumstance of
the bottom of the rock not reaching so low as the level of the
railway — a bed of clay in the deepest part, about 20 feet thick,
occurring between two. To secure this from bulging our, it was
necessary to build retaining walls of considerable thickness. The
sides of the excavation are laid at two slopes; for that portion
which reaches from the railway to the top of the rock, they are at
one quarter to one, and for that portion above the rock the
inclination is at two to one, — a ledge or benching, of nine feet in
width, being formed where the two slopes meet. The object of the
benching is to catch any loose portions of the clay which might be
detached from above; they have also been found very useful as
affording foundations for walls of pebble-stone, which it has been
found necessary to erect upon them in many places, to retain the
numerous slips of the clay above. The excavation has now been about
three years in execution. During the first year and a half the
progress was extremely slow, owing to the want of proper energy on
the part of the contractor, combined with general bad management. It
was, in fact, one more instance of the sort adverted to before. The
time was frittered away without any thing like a proper quantity of
work being done; and if this was evident at the commencement, where
there were no particular difficulties to grapple with, what might be
expected towards the end, when it was fully believed that nothing
but the most energetic measures could ensure success? A last, the
Company were obliged to get rid of the contractor, by any means, and
take the work into their own hands, with the knowledge, that in
pulling up for the lost time the expenses would be considerably
increased.
From the moment it came into the Company’s hands, no trouble or
expense has been spared to remedy the evil of the previous slow
progress, as much as possible; and nothing could exceed the
animation of the scene which these works presented when in their
most active state, with from 700 to 800 workmen all vigorously
employed ― numerous barrow and wagon runs in continual motion ― a
steam-engine in constant activity, pumping out the water ―
locomotive engines at each end, away long trains of wagons full of
earth, or bringing the empty ones back, — and blasts of the rook
continually deafening the ear. In fact, the whole cutting seemed
alive; and the busy hum of labour, resounding from the one end to
the other, gave ample testimony to the zealous exertions of the
engineer.
Of course, the expense was considerable. The article of gunpowder
alone was, in many cases, twenty-five barrels, of 100 lbs. each, per
week: enormous quantities were used before the whole rock was got
out. The mode of blasting made use of was by drilling a hole in the
stone, about one inch in diameter; the depth being determined by the
thickness of the bed. This is done by means of a round iron bar shod
with steel, which is lifted up, and than struck down in the hole,
water being used with it, causing the stone to cut more readily,
till the hole is drilled to the requisite depth.
When the hole sufficiently deep, it is dried out; a piece of fuse,
of the requisite length, is then put in, and the gunpowder is poured
all round it, in the requisite quantity, and secured by a covering
of pounded brick or stone. Several charges being thus prepared, the
ends of the fuses are lighted, and the workmen retreat to a
sufficient distance for security. In a few minutes the whole
explode, tearing up large masses of the rock, and sending the
lighter pieces high into the air. The least noisy of these
explosions are generally the most effective, rending up the larger
masses of the rock. This is another instance of the truth of the old
adage, — “The more noise, the less work.”
This excavation is crossed by five bridges, some of which are to be
of a considerable span, and will present a fine appearance from the
Railway; they are to be composed of a mixture of stone got out of
the cutting, and brickwork. The different beds of rock in this
excavation abound with fossil shells, in a good state of
preservation: they consist of nautilus, terebratula, oysters, &c. There were also two or three fossils, of very considerable
magnitude, discovered; they were of the Saurian tribe, and were
found imbedded in a stratum immediately on the top of the rock,
which is a species of half-formed stone, of considerable hardness
when dry, but becoming soon softened when exposed to the air and
damp.
One of the chief difficulties met with in the course of this work
was want of lodgings for a sufficient number of workmen, in the
surrounding villages of Hanwell, Ashton, Roads, and Ellsworth; and
inns found indispensably necessary, soon after the Company took the
contract into their own hands, to erect a considerable number of
cottages, ― one row of which contains sixty houses. The necessity
for this will be readily understood, when, as before stated, there
were from seven to eight hundred workmen, all employed in the space
of about a mile and a half, besides others at a greater distance.
It was originally intended, that the whole of the material which
came out of the excavation should be used in the formation of the
embankments at each end of it; but, owing to the slowness with which
the work advanced while under the contractors’ hands, it was found
necessary to throw out of it about 150,000 cubic yards into spoil. The land for receiving this, together with that necessary to make up
the corresponding deficiency in the embankments, of course, will
still farther increase the expense of the work.
The material which was taken from the south, or London end, had to
be conveyed an average distance of about a mile and a half, and
considerable difficulty was found in the formation of the embankment
near the village of Ashton, owing to the unsound state of the valley
which formed its base. Immense quantities of material were teemed
daily, which, as in the case of the Wolverton embankment, totally
disappeared, and the natural surface of the ground actually burst up
outside the limits of the Railway, in consequence of the enormous
pressure. A culvert near the spot was entirely destroyed from this
cause.
The same embankment gave much annoyance from a slip, which took
place in it near one of the bridges, and to such an extent, and so
high, did the slipping materials reach, as to throw down two
cottages, although the utmost exertions were made to save them. At Bugbrook Downs, not for from this contract, there is a slip at four
to one.
The embankment at the north, or Birmingham end of the excavation,
has more earth in it than the other; but the substratum on which its
deepest part rests is of a better description, and no slips of any
importance have when place in that portion of the works; but a
culvert of considerable length was in great danger of being crushed
in; the expedient, however, of completely filling it with
pebble-stone was resorted to, that material fortunately being at
hand; notwithstanding this precaution, it was carried considerably
out of its straight direction, so much so that the light can but
just be perceived when it is looked through.
It may, perhaps, be thought uninteresting to mention works of so
small a magnitude as culverts; but no person who has in any way been
connected with their erection, when having to sustain embankments of
forty or fifty feet in height, could feel otherwise than nervous
during the process of bringing the material over them. An engineer
can be wished no worse fortune than to be required to construct
culverts under a deep embankment, upon a soft foundation.
From the above view of the nature and extent of this contract, and
the means which were resorted to, in order to make up for the
serious delay which occurred while the work was under the
contractor’s hands, every body will he quite prepared to expect that
a sum of about £130,000 has been expended beyond the original
estimate; and been expended wisely, too, us the loss would have been
considerably greater if these exertions had not been made.
Another unpleasant affair for the Company arose from the person who
had the Tring contract becoming bankrupt — a matter least expected,
perhaps, of any. He was a man of capital and talent, and had
established a reputation for years as an able contractor. The works
he had on his hands were of the most extensive nature, and ought to
have paid him well; when, to the surprise of every one who knew him,
he was suddenly declared to he in difficulties through his contracts
on the Grand Junction line, and ultimately went into the Gazette,
leaving the works at Tring, including the heavy cutting through the
chalk, to be finished as it best might.
Another heavy loss occurred through a change which took place in the
form and weight of the rails. Those who wish to enter into the
question at large may consult Professor Barlow in favour of long
bearings [Fellows, Ludgate-street], and myself in favour of
short ones [Simpkin and Marshall, Paternoster-row]. It will
be sufficient here to state, that the line of railway was originally
intended to be laid with rails of 50 lbs. per yard, of the shape
denominated fish-bellies; but an opinion prevailed, among several of
the influential proprietors, that these were too light. After much
discussion, it was decided that the weight of all those laid down in
future should he 60 lbs. per yard. Professor Barlow’s opinion
was then taken; and he recommended the parallel at 75 lbs. per yard,
and that the length of the bearings should be increased to five feet; or,
if liked better, a rail 64 lbs. to the yard, at a bearing of four
feet. These have not been found to answer in practice. They would,
no doubt, have been sufficiently strong, except under extraordinary
circumstances; but, in consequence of having fewer supports, they
were found to get out of gauge much sooner than those of 50 lbs. to
the yard, at bearings three feet long, although the latter had more
weights going over them, and the consequent expense of keeping the
way in repair would be permanently increased.
Decided experimental proofs having been received of this and other
defects, and it having been ascertained that wagons and engines had,
in consequence, frequently got off the rails on some parts of the
line, an additional sleeper was ordered to be put on all the
embankments of thirty feet high and above, thereby reducing the
bearings to two feet six inches; and this not being found a
sufficiently extensive alteration, the rails then to be put down
were ordered to be laid with bearings of three feet nine inches, in
cuttings as well as on embankments. Unfortunately, during the time
occupied in the discussion, the price of iron rails rose no less
than £4 per ton; so that the additional cost, added to the
additional weight amounted to a very serious sum.
The subject of stations soon began to claim especial attention, as
so much depends on having convenient access to the arrival and
departure places, combined with appropriate offices to carry on the
large business which the Company naturally expects. At the London
end of the line, the first Act of Parliament only authorised the
Railway to be made from Birmingham to Camden Town, at the spot where
the present goods’ station is; and as this was much too far for the
convenience of the London residents, it became necessary to see
which would be the readiest way to bring it closer in; and after
full deliberation, the present plan of extending it to Euston Square
was adopted, and an Act of Parliament obtained July 3rd, 1836,
authorising this extension. This was another heavy but necessary
expense; both land and buildings being, of course, from their
proximity to London, at a proportionate price.
The same Act allowed a deviation to be made from the original line
near Weedon, by which a very awkward curve was considerably
improved. Power was also given to the Company to alter the course of
the rivers Ouse and Avon — to purchase fifty additional acres of
land for stations — to build a viaduct of six arches, of sixty feet
span, at Wolverton — and to construct a drawbridge, to carry the
Railway over the Ordnance canal at Weedon. This Act also repealed
the provision in the former one, which enacted that the distance
between the outside edges of the rails should not he more than five
feet one inch; and also the clause which provided that the directors
of the Company were to be, in certain proportions, residents at
London and Birmingham, or within twenty miles. It also provided that
general meetings might be called by fifty instead of one hundred
proprietors, holding in the whole two thousand shares; and allowed a
toll or rate of one shilling per passenger for the extension line
from Camden Town to Euston Grove, — the goods not going further than
Camden Town.
By the first Act the Company were empowered to borrow on mortgage
£835,000; the second Act increased that sum to £l,000,000, with
leave to enlarge the capital to that amount, if thought advisable;
and by a third Act, passed June 30th, 1837, they were authorised to
raise another £l,000,000, on bonds, with power, if they thought fit,
to create new shares for these two additional millions.
The third Act also repealed the clauses of the farmer ones which
provided that the half yearly general meetings, and the special
general meetings, should he held in either London or Birmingham, and
directs that they may both be held wherever the directors think
proper. It also alters the number of the directors, there may now be
any number between twelve and twenty-four; and it limits the passage
of trains across Curzon-street, in Birmingham, to twelve times per
day. This latter clause is rather amusing; because, by unhooking the
carriages, they may be crossing it all day long, as it requires at
least two carriages, of some sort or other, to constitute a train.
It was a matter of some moment to determine on the plan and nature
of the Stations at the termini of the line; the intermediate ones
simply required a booking office — waiting room, with the necessary
conveniences ― a room for the police inspector ― and one for the
porters: these, thrown into a neat building, form all that is
required. They are placed, of course, so as to suit, as far as
possible, the surrounding population; and the quality of the water,
and its situation, determines a pumping engine to be necessary or
not. The number of these stations will, in time, very probably
be
increased; in fact, the greater facilities the public find in these
and all other respects, the more will the money pour into the
pockets of the Company.
At the termini, it was decided that the plan should be on a scale
commensurate with the magnificence of the whole undertaking, and the
question of expense was not to he entertained. When it is considered
that on the convenience and appropriateness of the buildings at the
termini so much of the regularity and good-working of the Railway
must depend, too great pains could not be taken on such an essential
subject. Every thing depends so much on rapidly working, for a short
space of time, that no means should be neglected which can at all
conduce to that end.
At the London end the entrance is through a magnificent gateway,
having offices for parcels, &c., on each side. A very handsome medal
of this entrance has been struck by Mr. Hardwicke, the architect,
under whom it was erected. Inside is a building containing, on the
ground floor, the necessary booking-offices and waiting-rooms, also
a room for the superintendent of police; on the upper floor is the
board room for the directors, a waiting-room, secretary’s room,
offices for clerks in the audit and finance department, and the
office of the superintendent of the coaching department.
On the farther aide of this building are the arrival and departure
stages, covered in with a light handsome iron roof. The stages are
built up to nearly the height of the carriage floors, so that the
passengers are not obliged to climb up, but have merely to walk in. There are four lines of rails between the stages; and the Company
have ensured the means of considerably enlarging the whole, by
making it a double station, should the traffic render it desirable
to do so, which is more than probable.
At the end of the departure stage is a small building, for keeping
lamps, grease, and tools of all kinds, required for the station. On
the opposite side, next the arrival stage is another small building,
containing a waiting room for persons coming to meet their friends,
a room for lost luggage, and various other useful offices. A little
distance from the arrival stage is the carriage-house, containing,
on two floors, ample room for either making or repairing a large
establishment of carriages; and also storing those not immediately
required for use. A short way from this an endless rope is laid down
on iron sheaves, to which the trains are attached by a selvagee,
fixed on the foremost carriage, the other end of the rope
communicates with a steam-engine of sixty-horse power, by which the
train can he drawn up to Camden Town, in ordinary circumstances, at
twenty-five miles an hour. This inclined plane, although not a
desirable thing, was unavoidable, on account of the difference of
level between the two stations. The steam-engine is entirely underground; but its chimney and that of the reserve engine, form
conspicuous objects, from the beauty of their figure and form.
It is not because locomotives cannot draw a train of carriages up
this incline that a fixed engine and endless rope are used, for they
can and have done so; but because the Company are restricted, by
their Act of Parliament, from running locomotive engines nearer
London than Camden Town. The trains, on their way to London, run
down this incline by the effect of gravity, under the guidance of a
careful man, denominated a Bankrider, who has the charge of the
train during its passage. We may here mention a useful fact relative
to inclined planes. It has generally been supposed that, on a slope
of one in two hundred and fifty, well made carriages would barely
stand still, and this inclination has been termed the angle of
repose; but at an incline of one in three hundred and thirty, on the
London and Birmingham Railway near Beechwood Tunnel, a wagon ran
away and could not be caught till it got to the Coventry Station,
into which it came at eight miles an hour.
The Station at Camden Town is appropriated for all the traffic in
goods, the offices for which are seen to the right. The nearest
building to the Railway is the locomotive engine house, in which the
engines, tenders, coke and water, are kept, and where, as at
Birmingham, engines receive small repairs; but any repairs of
consequence are to be done in large premises, erected for that
purpose, at Wolverton, near the middle of the line. Coke ovens are
also built at this station, the chimney of which is seen to the
right.
The Birmingham Station is somewhat differently arranged, the ground
not being so advantageous. The station for the goods is on the one
side of Curzon-street, and the passenger station on the other; and
on this plan the ground was excavated, and the goods’ offices and
stables built, the earth being wanted to fill up the other puts of
the station. The board room for the directors, the secretary’s
offices, and the offices of the finance and correspondence
deportments, the engineer’s office, and the parcels’ office, are all
contained in one building, handsomely fitted, and having four noble
Ionic columns in the front, and four three-quarter columns at the
back. The entrance to the station is to the left of this building as
you approach it from the town, and the exit on the right; the
booking-offices, waiting-rooms, a temporary parcels’ office, are
contained in the long building having a colonnade in its front. The
arrival and departure stages are about the same height as those in
London; but the roof over them is much larger, there being six lines
of rails under it instead of four. The London roof is eighty feet
wide; by some strange mistake, Mr. Roscoe has stated this to be only
“about fifty feet,” in his publication.
This roof being one of the finest (if not the finest) in the world,
some few particulars of its various parts may be interesting. It
covers a space of 217 feet long and 113 wide. It is formed of
wrought iron in two spans of 56 feet 6 inches each, and the length
is divided into 33 bays or spaces between each principal rafter,
making 34 double, or 68 single, sets of principal rafters, a double
one being considered to go across both spans, or the whole width of
113 feet, and the single one going across the 56 feet 6 inches only.
These principal rafters are supported by three tiers of open
ornamented arched girders made of cast-iron, each tier running the
whole length of the roof, or 217 feet; the girders are supported by
three rows of cast-iron columns, one at each side of the roof, and
one in the middle; these likewise run the whole length of the roof,
and the row, next the booking-offices, are firmly attached to that
building by wall plates, inside and out, with connecting bolts.
The feet of the principal rollers are tied in by tension rods
running across, and rising in the middle a little above the
horizontal line; these are connected with the upper angle of the
principle rafter by a king bolt, and each half of the principal,
right and left of the king bolt, has two queen bolts and diagonal
braces, the lower ends of which slope in towards the king bolt, and
are connected at the bottom to the tension rods. There are 804
longitudinal stretchers fixed between the principals at the top, to
tie them firmly together, and 201 longitudinal stretchers at the
bottom in a line with the tension rods.
Twenty-two wrought iron coupling plates are introduced along the
tops of the girders to secure them together, going over the tops of
the columns, and being firmly fixed to them. The principals are
covered — first, with one inch deal boarding, laid diagonally, so as
to form a perfect brace and tie to the whole roof — and, on the
hoarding, the whole is slated in the usual way. The gutters are of
cast-iron in 9¾ feet lengths, and the rain water is delivered by
them into the cast-iron columns, which convey it down to the drains
below.
The weight of the cast-iron in columns, girders, bases, gutters, &c.
is about 80 tons.
The weight of the wrought iron in principal rafters, tie rods,
tension rods, &c. is also 80 tons.
The weight of the planking is 76 tons.
The weight of the slates is 90 tons.
Making an allowance for nails, screws, pins, bolts, and other
matters of that kind, the total weight of the roof may be taken at
326 tons: over the departure step sashes have been introduced with a
view to obviate any shade being thrown on the interior of the
building to which the roof is attached. The general appearance and
the airy lightness of the whole of this handsome covering to the
station, have been remarked by every one, particularly when looked
at from either end.
It consists of the following parts:—
Cast Iron columns . . . . |
52 |
|
――― ――― girders . . . . |
39 |
|
――― ――― gutters . . . . |
66 |
|
――― ――― bases to columns . . . . |
52 |
|
――― ――― water pipes . . . . |
33 |
|
|
|
242 |
Wrought Iron principal rafters . . . . |
136 |
|
――― ―――tension rods . . . . |
136 |
|
――― ―――king bolts . . . . |
68 |
|
――― ―――longitudinal tie rods . . . . |
201 |
|
――― ―――braces . . . . |
408 |
|
――― ―――queen bolts . . . . |
272 |
|
――― ―――longitudinal stretchers . . . . |
804 |
|
――― ―――coupling plates . . . . |
22 |
|
――― ―――plates to connect ditto . . . . |
40 |
|
――― ―――wall plates . . . . |
34 |
|
――― ―――eye bolts to connect tension rods
. . . . |
34 |
|
――― ―――connecting plates,
securing the braces, king and queen bolts, to the
principal . . . . |
680 |
|
――― ―――octagon plates at top and bottom
of king bolts . . . |
136 |
|
――― ―――plates for braces . . . . |
816 |
|
|
|
3,787 |
――― ―――pins . . . . |
578 |
|
――― ―――bolts and nuts . . . . |
2,200 |
|
――― ―――rivets . . . .
|
2,380 |
|
――― ―――split keys . . . . |
1,156 |
|
――― ―――gibs and keys . . . . |
442 |
|
――― ―――screws . . . . |
65,780 |
|
|
|
72,536 |
Planks |
1,721 |
|
Slates |
36,000 |
|
Nails |
72,000 |
|
Iron straps |
292 |
|
|
|
110,013 |
|
|
186,578 |
At the and of the departure stage is a small building, containing
the lamp and grease room, police office, porters’ waiting-room, and
store room for lost luggage. Farther on is the locomotive engine
house, which is exceedingly well adapted for its purpose; although
it is rather in the way of the lines of rails, and occasions thereby
an awkward curve, which has several times thrown the carriages off
the road.
The locomotive engine house is a building with sixteen sides,
capable of holding sixteen engines and tenders, or thirty-two
engines alone: those stand with their ends towards the sixteen sides
of the building, one against each, on sixteen ways, all meeting on a
turn-plate in the centre, by which the engines are got out along the
respective lines of rails, which run from the engine house to the
station. Under each engine is a pit, about three feet deep, which
enables the engine-men to get underneath the engine to examine,
clean, or repair it. There are eight water-cocks near the pits, so
that a pipe and hose can be got to every engine, without crossing
any other. The water laid on by the Birmingham Water Company has so
great a pressure on it, that it will, through a contrivance by Mr.
Henry Rofe, their engineer, make its way into the engine boilers
when the steam is up, and has even forced through the pores of
cast-iron, three inches thick; notwithstanding which, fish both live
and thrive with more than this additional weight upon them, the
pressure at the engine-house being 180 feet, and fish in excellent
condition have been found in air vessels where the height of the
water was at least 250 feet. It will, perhaps, give a better idea of
the pressure when it is stated, that a boy not long since,
endeavouring, in more play, to get out a wooden plug, driven into
one of the water-ways in the town, at last succeeded, when it flew
out like a shot, beating in his skull, and killing him on the spot.
In the front of the engine-house are store-rooms, offices, and
workshops, over which is a tank, holding one hundred and seventy
tons of water. It is provided with a steam-engine to work pumps from
a well below, in case the supply from the Water Works Company should
fail. The engine-house is built on land about twenty feet lower than
the present surface, under which are store-rooms for coke, and a
communication to a large coke vault underground, which opens out to
the canal.
There is a great deal more difficulty than would at first be
imagined in laying out a railway station; and, perhaps, in every one
now in existence, if it had to be entirely built over again, some
change would be desirable: there are so many things to be
amalgamated, and such various accommodation to be provided, that the
business becomes exceedingly complicated. A convenient access for
the engines and trains, without bad curves — a good situation with
regard to the town — an easy access, to and from the engine house,
and to the carriage shed and repairing shops — a proximity to water
— a convenient situation for the store department: these are a few
among the many desiderata, which render it a very difficult thing to
make them all fall into the necessary arrangement; but we may say of
our stations, that as much has been made of the ground as could, by
any possibility, be done under the circumstances of the case — these
circumstances having repeatedly changed.
During the progress of the works temporary buildings were erected at
Camden Town, for the purpose of constructing second-class carriages,
horse boxes, wagons, carriage trucks, &c.; the whole of which were
made there at, of course, a considerable saving: workshops were also
built at Birmingham, where, amongst other things, all the wedges for
the rails, on the Birmingham division of the works, were made at
about half the price they could have been got by contract. It was
originally intended to have three classes of carriages — the first
class as at present. The second class were to be closed on the
outside, but with all three bodies open to each other on the inside,
and without lining or cushions — these were both put out to be
manufactured by contract. The third class were similar to those now
used, except that they had no roof; but it was found desirable to
omit the middle class, put a roof to the third class and call it the
second class — thus retaining only two kinds, except the night
trains; in these the original second class closed coaches are used,
and the open ones by day. All these arrangements, however, are as
yet only in a state of transition.
If we now take a review of the progress of the works, we shall see
the respective steps by which this gigantic undertaking has been
brought along the stream of time. The early part of 1835 may be soon
enough to commence our view. It was at this time the rails question
had begun to he agitated; and at a general meeting of the
proprietors, held at Birmingham, in the month of February, it was
decided that, until the results of the experiments in malleable iron
bars, of different forms, which the directors had undertaken at the
suggestion, and under the direction, of Professor Barlow, should be
ascertained, all the rails to be ordered should be of the parallel
form, the upper and under tables alike in size, and the weight as
nearly 60 lbs. to the yard as might he compatible with the most
advantageous manufacture of the iron; that the weight of the chairs
should be correspondingly increased, and the rails firmly secured to
them by a filling-in piece; that the use of patent felt and wooden
keys, on a plan similar to that recently adopted by the North Union
and Liverpool and Manchester Companies, and also of the “Lewis,” for
securing the chair to the sleepers, be recommended to the immediate
attention of the engineer of the Company — consideration being given
to the advantage which may be gained in strength, by placing the
chair nearer to each other than three feet, from centre to centre;
that the blocks should contain not less than five cubic feet each,
and granite to be used, if the expense be found not materially to
exceed the cost of limestone, or grit of the best quality — in which
case measures were to be promptly taken for ensuring a sufficient
supply of granite, to be exclusively used for all blocks on the
railway in future; these were excellent provisions in the main. It
would have been well if they had never been departed from.
Fifty-eight miles of the railway were at this time let to the
contractors; they had possession of the land and were going on
satisfactorily, except at Wolverton, where the work was partially
retarded by the Grand Junction Canal Company, who refused to allow
the contractor to erect a temporary bridge over their canal, and a
decision had to he obtained in the Rolls Court.
The Euston extension had been surveyed; and as no opposition was
expected to an Act of Parliament for it, (the terms on which land
could be got, likewise showing it to he the most advantageous line
of approach into London,) it was decided on to apply for the Act
forthwith, which also embraced the alterations at Wolverton, Weedon,
and Brockhall, by which two tunnels and a had curve were avoided.
At that time a great prejudice existed against tunnels, arising
entirely from ignorance; and the directors, in order to set the
minds of the public at rest, had a special visit to the Primrose
Hill Tunnel made by Drs. Paris and Watson, Surgeons Lawrence and
Lucas, and Mr. Phillips, the Lecturer on Chemistry at St. Thomas’s
Hospital; the object of the visit was to ascertain the probable
effect of such a tunnel on the health and feelings. The length is
3,750 feet, height twenty-two, width twenty-two; ventilated by five
small shafts, six to eight feet only in diameter, and from
thirty-five to fifty-five feet in height.
The experiment was made under unfavourable circumstances; the
western extremity of the tunnel being only partially open, which, of
course, made the ventilation less perfect than when the whole would
be complete. The steam of the locomotive engine also was suffered to
escape for twenty minutes, while the carriages were nearly
stationary at the end of the tunnel. Even during their stay near the
unfinished end of the tunnel, although the cloud caused by the steam
was visible near the roof, the air, for many feet above their heads,
remained perfectly clear, and apparently unaffected by steam or
effluvia of any kind, neither was there any damp or cold
perceptible.
The atmosphere of the tunnel was found to be dry and of an agreeable
temperature, and free from smell. The lamps of the carriages were
lighted; and in their transit inwards, and back to the mouth of the
tunnel, the sensation experienced was precisely that of travelling
in a coach by night, between the walls of a narrow street. The noise
did not prevent easy conversation, nor appear to be much greater in
the tunnel than in the open air.
Judging from this experiment, and knowing the ease and certainty
with which thorough ventilation may be effected, these gentlemen
were decidedly of opinion that the dangers incurred in passing
through well-constructed tunnels were no greater than those incurred
in ordinary travelling upon an open railway, or upon a turnpike
road; and that the apprehensions which have been expressed, that
such tunnels are likely to prove detrimental to the health, or
inconvenient to the feelings of those who may go through them, are
perfectly futile and groundless: and to these opinions, thus
strongly expressed, they all signed their names.
The money expended on the railway at this time was £399,554, every
thing included; among which must not be forgotten the £72,569, paid
for obtaining the Act of Incorporation.
The next meeting was in August, 1835. The money than expended was
£639,051; and eighty-six miles of the railway were let to
contractors, below the estimates of the engineer-in-chief, and
two-thirds of the whole land purchased. This was the season of
brightness and hope; no reverses had come on, and all was sunshine
and harmony, except the unfortunate discussions on the rails
question.
In February, 1836, the money expended was £1,054,612. The whole line
was now let to contractors, under the estimates; yet it was foreseen
that the original capital would be exceeded; for, besides the
contracts let, there were the extra works, which, it was found would
exceed ten per cent. on the contract; also the additional expense of
permanent way materials — the rise in the price of iron — the larger
quantity of land which was found to be required, together with its
very enormous price — those circumstances occasioned the directors
to publicly state that the total outlay would be considerably beyond
the original estimate.
The contractor for the Euston extension line was put under a penalty
to complete the works by January, 1837; and there was no reason to
doubt his ability to fulfil this engagement. It was expected that,
in the spring of 1837, the first twenty-one miles of railway out of
London, would he opened; and that, in the summer of that year, ten
miles more up to Tring, together with the part from Birmingham to
Coventry, would be finished; and that the whole line would be
completed in the summer of 1838. The quicksand had been discovered,
and it was seen that Kilsby and Blisworth would be the latest
portion of the works; but the great mishaps were yet in the womb of
futurity.
In August, 1836, the expenditure had reached to £1,492,101; and the
expectation was still confidently held out, that the whole line
would be opened in the summer of 1838, and the first twenty-one
miles in the spring of 1837. The Primrose Hill Tunnel, 1,105 yards
long, was completed, except 114 yards; the Kensal Green Tunnel was
finished, and traversed by the Company’s engines; 1,423 out of the
1,793 yards of the Watford tunnel were done; and the difficulties
which were presented by the quicksand in the Kilsby Tunnel were at
this time so far surmounted, as to leave no doubt that they would
not delay the opening of the line beyond the period mentioned. Every
exertion was used with all the other portions of the line, so as to
give the proprietors the benefit of a revenue at the earliest
possible period. Although it was well known that, for the attainment
of that object, an additional expense would he incurred, the
advantage to be derived was expected to be more than commensurate
with the additional outlay which would be required.
The directors at this time had entered into a contract, under the
guarantee of two responsible sureties, with Mr. Edward Bury, of
Liverpool, an able and experienced builder of locomotive engines,
for the conveyance of passengers and goods on the Railway, by
locomotive power, to whatever extent might he required, at a fixed
rate of remuneration, — the Company providing engines of Mr. Bury’s
specification; and Mr. Bury, on his part, keeping them in repair:
the contract to be in force for three years, from the opening of the
whole Railway. The Company thus assured to themselves the advantage
of locomotive power, at a moderate and uniform rate, and under a
system of management which it is the interest of the contractor to
render mutually beneficial to the Company and himself. Such
locomotives, and a portion of the carriages which would be first
wanted, were at this time contracted for.
On referring to the bills for railways connected with the London and
Birmingham, a great source of gratification was no doubt felt by the
proprietors, as there would, in consequence, be an increased
traffic: this might be fairly anticipated, from the direct
communication opened with the northern and eastern parts of the
kingdom, by means of the Midland Counties, North Midland, and
Birmingham and Derby Railways, besides the line connecting
Birmingham and Gloucester.
A line was also surveyed to join Leamington and Warwick with the
London mid Birmingham Railway, at Coventry. This proposition
afterwards fell through; but it can only be for a time, as those
places will, doubtless, not contentedly sit down while all around
them are receiving the benefit of railway transit.
Great as the scale of expenditure now appeared, the proprietors,
there is no doubt, felt confident that, if the works proceeded with
an energy proportioned to that expenditure, they should hail its
increase as on additional evidence of the approach of the great
undertaking to completion. £443,800 had now been taken up by loan,
and there appeared not the least difficulty in getting as much money
no would be wanted.
In February, 1837, the expenditure was £2,385,321. Contracts were
now entered into for the stations at London and Birmingham. At the
London end of the line, near Camden Town, the Company have about
thirty-three acres of land, which is the depot for the buildings,
engines, wagons, goods, and various necessaries of the carrying
department of the Railway; at Euston Grove there are seven acres in
the passenger station — the two are connected by the extension line,
on which are four lines of rails. At the Birmingham end the stations
contain about ten acres. The London station, except the entrance,
was contracted to be done in June, 1837, and the Birmingham, by
November, 1837; the intermediate stations were also put in progress.
The expectation of opening the first twenty-one miles in the spring
of 1837, was now doomed to be disappointed. Owing to the late
unexampled season, this idea had to be abandoned till the summer:
the continued bad weather for the last four months, had defeated the
calculations of the engineer, in a degree which no former experience
could anticipate. In some descriptions of soil, this delay could not
have taken place to such an extent as in the London clay, which was
exemplified by the progress of the works on the other parts of the
line, where the material was more favourable; but in the London
district, the incessant falls of rain had rendered it quite
impracticable to proceed uninterruptedly ― the excavations and
embankments on the Primrose Hill contract were persevered in, till
the extra expense was such, that the directors, as well as the
engineer, saw the full propriety of suspending further operations.
The works on the extension line only required six weeks of fair
weather to finish them; the works of the Primrose Hill contract,
which were in the Company’s hands, were nearly completed, except the
Brent embankment; the Primrose Hill Tunnel was finished, and
traversed by the Company’s engines: and great part of the permanent
way laid on the first twenty-one miles. The embankment on the north
of the Brent might be called finished; while that on the south side
required only 60,000 cubic yards of material to complete, which, in
an ordinary state of the weather, would require only three months.
From that point to Watford all was progressing as well as could be
wished. The Watford Tunnel was finished, and but little remained in
the excavation. The state of the three succeeding contracts was also
very satisfactory. The North Church Tunnel was finished, and, with
the some exertions on the part of the contractors which had hitherto
been evinced, there appeared no reasonable doubt but that the works
might be all completed, and the line opened to Tring, by the autumn. The quantity of water, however, yielded by the Tring cutting, in
addition to that which had fallen in rain, together with the
argillaceous character in the chalk in that cutting, rendered it
absolutely necessary to stop all proceedings on that embankment; it
had, in fact, been proceeded with, till it was at last quite
impossible.
The heavy Wolverton Embankment had now been divided between two
contractors, and the works there were proceeding satisfactorily. The
Blisworth works were in the possession of the Company, by an
agreement with the contractor; and all the skill of the engineers,
and the pecuniary resources of the Company, were to be at once
brought to bear, in endeavouring to make up for the lost time; the
rate of progress, of course, depending on the quantity of water and
rock, the precise nature of the latter not having yet been
ascertained.
Two lengths of the quicksand in the Kilsby Tunnel were bricked in;
that work, therefore, began to assume the character of ordinary
tunnelling; and, unless a very unexpected quantity of water should
be found, where, at present, no signs of it existed, there was still
every hope that the whole line would be opened in the summer of
1838, and that part between Birmingham and Rugby by the end of 1837.
A Bill which was at this time proposed, for carrying a line from
Tamworth to Rugby, by the Birmingham and Derby Railway Company, and
which was to be continued on to Stafford by another company, was
opposed by the directors of the London and Birmingham Company, as a
competing line.
As the contract approached completion, it was found that the
contemplated works for the efficiency of the railway, in the
carrying department, as well as for the road itself, would require
the sum of one million more than was expected, and that the total
outlay would probably reach four millions and a half. This
additional cost was stated to arise ―
1. From additions, alterations, and extras to the original plan of
the works.
2. From the extension line to Euston Grove.
3. From the additional quantity of land (eight hundred acres) and
the much higher price the company had been compelled to pay for it,
— a price in some degree exhorted by the necessity of obtaining
possession at an earlier period than, by the provision of the Act of
Incorporation, the company could legally enforce.
4. From the increased price which it had been found necessary to
give for all the materials forming the permanent way — such as
rails, blocks, sleepers, chairs, &c., as well as for the additional
weight of the rails and chairs, which experience had shown it to be
prudent to use; and from the greater expense of conveying them to
their destination than was anticipated.
5. From the unforeseen difficulties in the Primrose Hill, the
Blisworth, and the Kilsby contracts.
6. From the ample provision made in the carrying department, and
particularly with reference to the traffic to he expected from other
railways, for which Acts have been obtained since the original
calculations were made.
The estimated cost of the railway, at this time, was as follows: —
EXPENSES OF OBTAINING
THE ACT OF PARLIAMENT |
£72,869 |
|
Land and
compensation . . . . |
£506,500 |
|
Contract
works for forming the road . . . . |
£2,146,068 |
|
Permanent
way materials, and incidental expenses . . . . |
£693,822 |
|
Station
buildings . . . . |
£154,521 |
|
Locomotive
engines . . . . |
£100,215 |
|
Carriages,
wagons, &c. . . . . |
£153,500 |
|
Euston
extension . . . . |
£255,722 |
|
Interest on
loans . . . . |
£114,262 |
|
Law
proceedings, including two new Acts . . . . |
£12,000 |
|
Conveyancing . . . . |
£53,800 |
|
Engineering
and surveying . . . . |
£127,100 |
|
Direction .
. . . |
£13,300 |
|
Office
charges . . . . |
£27,515 |
|
Printing
and advertising . . . . |
£4,800 |
|
Sundries including travelling expenses . . . . |
£10,600 |
|
|
|
£4, 446,594 |
The increase in the permanent way materials may be accounted for
thus: —
The
increased weight in the rails, and rise in the price of
iron . . . . |
£258,000 |
The
additional price of blocks and sleepers, and incidental
charges thereon . . . . |
£21,485 |
Increase in the number
of stations on the line, and consequent addition of
rails, &c. . . . . |
£47,000 |
The addition in cost of the works forming the road is as follows: —
From an increased width
in the Railway, increased slopes, and increased
dimensions of bridges, the revised exceeded the
Parliamentary estimate by . . . . |
£110,240 |
The whole contracts were let below the revised estimate. The excess
of expenditure chiefly arises in the following contracts :—
Primrose Hill — Including the tunnel, total
length six miles, additional outlay from the extremely
disadvantageous circumstances under which the Company
was compelled to take up the contract . . . . |
£21,636 |
|
Ditto. — In new roads, bridges, and sewers,
required by diverting existing roads, through Camden
Town depot, and in other places . . . . |
£27,552 |
|
Ditto.—In additional strength in the two tunnels
from the peculiar nature of the London clay . . . . |
£34,151 |
|
Blisworth. — Additional outlay required to make
good the loss of six months‘ time, and for the
completion of the costly parts which have fallen to the
Company to execute . . . . |
£60,000 |
|
Kilsby. — The occurrence of an extensive bed of
quicksand, lying over nearly one-fourth of the length of
the tunnel, and requiring to be drained by powerful
steam-engines, which must be kept at work till the
completion of the contract; the other parts of the
tunnel abounding in water, and rendering it necessary to
increase the number of shafts to an extent which could
not have been foreseen . . . . |
£140,000 |
|
Extras on
the remaining contracts . . . . |
£48,659 |
|
|
|
£442,238 |
|
|
|
The loans
taken up to this period were (at 4 per cent.) . . . . |
£560,061 |
|
Ditto
ditto ditto (at 4½ per cent.) . . . . |
£49,300 |
|
|
|
£609,361 |
On the 20th of July the first part of the Railway was opened to the
public, up to a place called Boxmoor, twenty-four miles from London;
and although, in consequence of the works still going on connected
with the entire completion and finishing off this portion of the
Railway, only three trains per day could be run from each end, the
traffic proved very considerable, and also to be increasing. A great
advantage arose from thus gradually opening the line, by which means
an opportunity was afforded of organising the arrangements required
in the various departments, progressively improving on a small
scale, and benefiting from experience previous to more extended
operations.
In August, 1837, the money expended was £3,102,272, and the loans
received £1,045,717. It was fully expected at this time that the
Railway would be opened from London to Denbigh Hall, and from
Birmingham to Rugby, being 77 miles, by the first of January, 1838;
but this expectation was, of course, understood as contingent on the
works not being retarded by causes which it was not in the power of
an engineer to control.
The Railway was opened to Tring in the month of October, as had been
anticipated; but a winter of unusual severity and duration, by
retarding the remaining works, made the further opening in January,
1838, impracticable; so intense, in fact, was the cold, that the
ground was frozen two feet in depth, and although, by means of large
fires and using hot mortar, brickwork was in some cases carried on,
every one at all conversant with such works, will readily know how
much time must necessarily be lost under weather which for weeks
kept the thermometer at nearly zero.
The suite of the different contracts in the middle of February,
1838, will be best shown by Mr. Stephenson’s Report, which was as
follows:—
“In reporting on the present state of the works on the line,
and our prospects as to future openings, it will not be necessary to
treat in detail of that portion between London and Tring which is
already open to the public, nor mention specially the quantifies of
fencing, brickwork, &c., which remain to be done on each contract,
as stated in the estimates already delivered, — such works being,
comparatively, unimportant, and not likely to interfere, in any way,
with the opening of the line. It may, however, be stated, with
reference to that portion between London and Tring, that the
permanent road is in tolerably good order, except on the Brent
Embankment near London, and on the Colne Embankment near Watford. Both these works have continued to subside, with scarcely any
intermission, more or less rapidly since their formation; the
former, from the slippery nature of the material which composes it;
the latter, from the unsoundness of its sub-stratum in the valley of
the Colne. The gradual subsidence of embankments admits of no other
remedy than maintaining the level of the railway by the constant
supply at new sound material, adapted for ballasting, which, in the
present case, may fortunately be obtained from a convenient spot,
and at a moderate expense; for there is in the Company’s possession,
at the south end of the Watford Tunnel, a large store of excellent
gravel and chalk, sufficient to meet all the demands of the line and
stations between Watford and London for some years.
“The only other points between London and Tring which call for
remark, are the Boxmoor Embankment and some portions of the Aldbury
contract, where we found it very difficult, at first, to keep the
rails in working order; but they are now in much better condition,
and will continue to improve rapidly during the ensuing spring and
summer. By this period we may expect that all the embankments will
become so consolidated, as to admit of the engines working over them
without any necessity of reducing the speed below the proposed
average speeds to be adopted with the passenger trains.
“The Tring contract, which comprehended the most extensive
excavation on the line, is now nearly completed. The whole of the
excavations and embankments are ready for the further opening to
Denbigh Hall, except that about four thousand yards of permanent
road remain to be laid — not in one length, but made up of several
smaller portions. The greatest quantity to he laid continuously is
about one mile, at the south end of the great excavation; for
executing which quantity, as well as all the other unfinished parts
of the permanent road in three weeks, every arrangement was made at
the latter end of December. It has, however, been impracticable to
proceed as intended, owing to the intense and protracted frost,
which set in a few days after the beginning of the year, continuing
up to the present date, without a single available interval of one
day. The contractors have been urged, and every expedient resorted
to, for the purpose of proceeding with the permanent road, so as to
expedite the approaching opening, but without success. There still
remains work which, as nearly as can be calculated, must require
three weeks to perform, after a thorough thaw has taken place. The
embankments throughout this contract consist almost entirely of
chalk, which being already well consolidated, and little liable to
subsidence, the immediate use of the permanent road may be reckoned
upon as soon as completed.
“The Leighton Buzzard contract is in a very similar position to the
last, though in a more forward state. The excavations and
embankments are completed, and the permanent road laid with the
exception of about a mile, made up of separate portions. The
ballasting is all on the ground, and nothing remains to be done but
laying the rails and blocks, which are also on the spot. The Linslade Tunnel is completed, one line of permanent road laid
through it, and the fronts so far advanced, that executing; the
remainder of the stone and brickwork will form no impediment
whatever to the opening.
“In the Stoke Hammond contract the excavations and embankments are
completed, except a small portion left on the slopes of the
cuttings, which cannot interfere with the permanent road. Of this
there remains little more than a mile to lay in different places.
“The Bletchley contract is completed, except 350 yards of permanent
road. This contract terminates at Denbigh Hall, where a station is
now being formed for the temporary terminus of the London division
of the line. The shed for the engines and coaches is erected — the
necessary turn-plates fixed — the sidings stopped by the frost, but
in a state to be finished in a fortnight — the huts for the
engine-men are ready to be inhabited — the stables for Chaplin and Co.
are in a forward state — a small office erected on the bridge over
the Turnpike-road, and an approach to the level of the railway from
the Turnpike-road, are nearly completed.
“From the above statements relative to the work remaining to be done
between Tring and Denbigh Hall, it is evident that the time of
opening through this district depends on, and must he regulated by,
the completion of that portion of the permanent road remaining
unfinished at the south end of the Tring excavation.
“The whole of the works on the Wolverton contract have, for some
time past, been advancing in the most satisfactory manner. The
quantity remaining, in the Denbigh Hall excavation, does not now
exceed 50,000 yards; part of which is to be conveyed into the
Wolverton Embankment, and the remainder thrown into spoil. The
present rate of progress will justify the calculation that the
cuttings and embankments, including the Wolverton Embankment, will
be closed in eight weeks from this time. The permanent road is also
in an advanced state. The unfinished portion is less than two miles,
the greater part of which will he laid before the excavations are
finished. We may, therefore, calculate upon the permanent road being
extended from Denbigh Hall to Wolverton in eight or nine weeks.
“The Wolverton Viaduct contract is completed, with the exception of
the permanent road, which cannot be commenced until the embankment
is brought up to both ends.
“In the Castlethorpe contract the excavations and embankments may be
regarded as completed ― the latter are entirely so. On the slopes of
the excavations a quantity of rock is left purposely, the chief part
being intended for ballasting the permanent road, of which there is
yet to be completed a length of two miles and a half. This does not
much exceed the quantity stated as remaining on the last contract;
and, as the excavations become more advanced, the period for
completion may be reckoned the same.
“The progress made throughout the works of the Blisworth contract
has upon the whole, exceeded the estimated average. Hitherto this was
to have been expected, from the favourable position of the material
excavated, and the large quantity thrown into spoil; but the
character of the excavation is now more difficult; and as it gets
deeper, the space for employing men gradually becomes more confined. The material is increasing in hardness; and within the last few
weeks, there has also been a greater quantity of water. These
impediments naturally render any estimate of the quantity which may
be yielded by the south end of the excavation for the embankment
southwards, in some degree uncertain. An arrangement has therefore
been made, and is at present acted upon, for throwing an additional
quantity into spoil from the centre of the excavation, and supplying
the deficiency in the embankment by a corresponding quantity of
side-cutting at the southern extremity of the contract. The object
thus aimed at is the completion of the south portion of the contract
in May, nearly at the same time with the Wolverton and Castlethorpe
contracts; at which period an extended opening may be made from
Denbigh Hall to the village of Roade, situate on the turnpike road
leading from Stoney Stratford to Northampton, and only five miles
from the latter town. This position appears highly advantageous for
the next temporary terminus, which must remain the terminus for the
London division, until the opening of the whole Railway.
“In the Blisworth Cutting there now remain about 100,000 cubic yards
of material, which will be disposed of nearly in the following
manner:—
30,000 cubic yards to Ashton Embankment.
35,000 -—-— -—-—to Blisworth ditto.
35,000 -—-— -—-—to spoil. |
The first quantity is that which relates to the opening of the line,
as far us Roade; and, reckoning the south end of the cutting to
yield at the rate of 10,000 yards per month, this may be effected in
three months, allowing the necessary time for joining the permanent
road.
“The completion of the Blisworth Embankment will probably not much
exceed the end of May, from which date the undersetting will
commence. By the time this has advanced to the site of the spoil, it
is expected the excavation will be cleared to the level of the
permanent rails. The undersettng being a work of a novel character,
and placed in a situation where contingencies will in all
probability occur, there is some difficulty in calculating the time
it will require. After giving the subject the most attentive
consideration, I do not deem it advisable to state this at lees than
three months from the time of the excavation being entirely cleared
or bottomed — bringing to the end of September the completion of the
contract, as regards readiness for the opening of the line.
“The future methods of procedure and expenses in the Blisworth
Cutting have been calculated upon the evidence and appearances now
before us; but it is not improbable that, in the undersetting, our
plans may require modification, as indicated by circumstances at the
time. Such cases will necessarily increase the cost beyond what was
last estimated; but the quantity of materials now remaining in the
cutting being small, and a considerable portion of the space for
undersetting being exposed already, the additional expense cannot,
it is thought, be very considerable. Three miles of permanent way
remain to be laid.
“In the Bugbrook contract the excavations and embankments throughout
are closed; but it will he necessary to deposit an additional
quantity of material upon one of the embankments, in which there has
occurred a very extensive slip. About two miles and a half of
permanent way remain to be laid.
“The Stowe Hill contract is in a satisfactory state, as regards the
prospect of completion. The tunnel has been finished some time. A
small quantity of excavation is yet to be brought from the south end
of the tunnel to the embankment at the north end of the contract. There are about 600 yards of permanent road to be laid.
“In the Weedon contract the excavations and embankments are
completed. There are about 1,100 yards of permanent road to be laid,
and the greater portion of ballasting is on the ground.
“The Brockhall and Long Buckby contracts are under the same
contractors, and have been worked conjointly; they may, therefore,
be regarded as one with reference to completion. The works are in a
more backward state than they ought to be. There is an excavation at
each extremity: one near Weedon, containing 70,000 cubic yards; the
other, at the south end of Kilsby tunnel, containing 80,000 cubic
yards. From these two excavations one intermediate embankment is to
be formed, requiring 97,000 cubic yards; the redundancy of the
excavations is to be deposited in spoil. With moderate exertions
these works may be closed in four months. There remain about four
miles and a half of permanent road to be laid.
“Kilsby Tunnel is at present in a very satisfactory state, and the
monthly progress as regular as can be expected, considering the
nature of the operations. No new difficulty has recently occurred,
except the capricious appearance and disappearance of water in some
of the shafts, both in and beyond the quicksand. Between these
shafts the junction of the respective portions of the tunnel has
consequently become rather uncertain, — the actual rate of progress
in tunnelling through the intermediate space, falling short of what
was estimated. To remove this source of contingency as much as
practicable, it has been found necessary to sink additional shafts,
for the purpose of dividing those unfinished portions which would
require the longest time to execute, or in which our average rate of
progress was most likely to be interrupted by water, or a change in
the nature of the strata. On the 20th of January inst. a careful admeasurement was made, to determine accurately the distance
unfinished between with pair of shafts, and the time of completion
for each calculated upon an average which there are no reasonable
grounds for doubting.
“The avenge of progress adopted in the table may appear to be
scarcely borne out by reference to the reports of progress in some
particular shafts; but such instances are accounted for, either by
the occurrence of a fallen length (which was the case in one of the
quicksand shafts), or by the proximity of the face of the tunnel to
the shaft, which lessens the room for working, and invariably
reduces the rate of progress below that which ought to be taken as a
guide.
“The circumstances requiring the adoption of the expedients
explained above (in order to avoid disappointment by the further
protraction of the time fixed for final completion), have
necessarily caused the expense of prosecuting this work to he
materially augmented beyond what was estimated last year; and in
addition to this, it has been found absolutely indispensable to
increase the prices of mining, timbering, and brickwork formerly
paid to the sub-contractors, and which expense was proved to be
altogether inadequate. In the quicksand especially, although
effectually drained, the utmost caution in mining has been required,
and an expenditure of timber unavoidably occurred, which would
appear excessive and lavish to any one whose experience has been
confined ordinary tunnelling. The present plans of proceeding have
been arrived at by close observation and mature reflection, and
cannot with safety or propriety be altered for the purpose of
economising. Several circumstances have occurred demonstrating that
none of our precautions or expenses have exceeded what the magnitude
of the difficulties attending this work imperatively demanded.
“The Rugby contract, having been given up into the hands of the
Company, is now proceeding under the direction of the engineers. A
considerable proportion of the excavations, embankments and
permanent road is already executed, and there now remain two
excavations to complete; one of them at the north and of Kilsby
Tunnel, containing 143,000 yards — the other near Rugby, containing
102,000 yards. The quantity to be conveyed from each to the Hillmorton Embankment is almost 60,000 yards, which will occupy four
months, making the period for completing this contract extend to
July; and to this we must add one month for the permanent road,
making it the beginning, or say the middle, of August.
“The works of the station at this point are at present in rather a
backward state, owing to the severe and continuous frost, which has
almost entirely put a stop to the brickwork and permanent road. The
booking-office walls are built, the timbering of the roof put on,
the engine and tank-house in a forward state, as also the huts for
the engine-men. The turnplates will be fixed in a few days. The
completion of the permanent road will occupy a fortnight after it is
practicable to commence laying it.
“From this station to Birmingham one line of permanent road is laid
throughout, and the other, with the exception of a short distance
(about one hundred and fifty yards) in the Church Lawford cutting. Though laid, however, the road is not in a fit state throughout to
be travelled upon by engines and trains; for, on some of the
principal embankments, it requires to be raised and adjusted. But
this is a work which, with a proper number of men, can easily be
completed before those other points, already specially alluded to,
as regulating the approaching opening.
“In the Birmingham station the large turnplate in the locomotive
engine house is completed, and the necessary rails fitting it for
the reception of engines will he laid in a few days. The lines of
rails in the passenger sheds are laid, and the requisite sidings
will be completed in a fortnight.
“From the foregoing remarks on the respective contracts throughout
the line, it will he perceived, that the works now remaining to be
executed are not only confined to a few points, but also limited in
magnitude. Blisworth alone appears to involve difficulties which may
possibly interfere with our calculations and prospects. From Denbigh
Hall to Blisworth the works are now rapidly approaching to a close.
The great feature of that portion of the line — the embankment over
Wolverton valley — will he joined to the viaduct in about a month;
and the line virtually finished and prepared for passengers as far
as Roade, in the course of May next. The unfinished portion of the
line will then be confined to the distance of twenty-three miles
between Blisworth and Rugby; but the greatest portion of this length
is at present nearly complete, and the only works of any magnitude
remaining are —
“l. The Blisworth Excavation, now containing not more than 100,000
cubic, yards of materials to be removed.
“2. The Long Buckby contract, with two excavations, both of which
may easily be executed in less than four months.
“3. The Kilsby Tunnel, with 400 yards of tunnelling to be done,
divided into portions so limited in extent, that the calculated
periods for the junctions being formed between the shafts (as
detailed in the table given under the proper head), may be looked
forward to with almost entire confidence; — and
“4. The Rugby contract, now in a very forward state, the unfinished
works being confined to two excavations, favourably situated and
circumstanced for suitable measures being adopted to secure their
expeditious completion.
“Of these four points there are two — the Long Buckby and Rugby
contracts — which involve no difficulty whatever, the works being
quite of an ordinary character; of the remaining two, Kilsby and
Blisworth, it is only the latter which need be regarded with
particular anxiety, and this work it does not appear impracticable
to complete in time should the approaching season prove favourable. Unless there should be impediments to the undersetting of the rock
with masonry exceeding what is at present anticipated, we may reckon
on an opening through it in six months from the first of March next,
which would make its completion almost, if not actually,
simultaneous with that of Kilsby Tunnel.”
On the first of January, 1838, the expenditure was £3,981,829; and
the loans, and cash advanced by proprietors in advance of their
calls, amounted to £1,828,797.
From the continually increasing difficulties which from time to time
presented themselves, an enlarged outlay of money was rendered
unavoidable; and it became evident that the existing capital of four
millions and a half would not be sufficient; but it was expected
that it would suffice to open the whole line for passenger traffic,
from end to end — hence any addition to the capital which might
eventually be required would principally arise out of further
preparations, on an increased scale, for the goods department.
The state of the weather was such that it was found impossible to
open the line, up to Denbigh Hull, and from Birmingham to Rugby,
till the 9th of April; from that day passengers have been conveyed
regularly between London and Birmingham, travelling seventy-seven
miles on the railway, and thirty-five, between Rugby and Denbigh
Hall, in coaches, furnished under a contract by Messrs. Horne and
Chaplin, at £7. 14s. 6d. per double journey, of 37 miles, including
all expenses. There were unfortunately not enough of them, which
occasioned many persons to be refused their passage, and occasioned
both loss and inconvenience. As far as the railway was concerned,
any number of passengers could he taken; but when the middle ground
was to be got over, the coaches of course, had a limit, beyond which
no person could be booked, yet at the above price, coach masters
ought to have jumped at the chance of furnishing conveyances to any
extant.
For several days before the coronation every place was taken, and
£10 offered and refused for a seat; at last the people went in
hundreds to Rugby, on the chance of getting to Denbigh Hall how they
could, ― when wagons, carts, donkey chaises, or anything else were put
in requisition, at enormous prices, up to a shilling a mile, to get
them along; and some speculators, who got stages down there by the
railway during this glut, charged £4 inside and £2. 10s. out, for
the distance from Rugby to Denbigh Hall.
The line of railway between London and Tring was too far distant
from the Holyhead road to hold out sufficient inducement to coach
proprietors to abandon their accustomed track, for the chance of a
comparatively small saving of time; the certainty, also, that a few
weeks would make a complete alteration in the passenger traffic, on
all the roads parallel to the railway, effectually checked the
establishment of new lines of communication for coaches from Tring
to the north; hence it happened, that, from the time when the season
for excursions had passed, and the curiosity of the public had been
partially gratified, the railway travelling was limited to the
purposes and accommodation of the immediate district. This afforded
an opportunity of practically ascertaining the effect of the
ordinary passenger traffic on that portion of the railway; and it
was found to exceed the amount, which had been calculated on,
considerably; thus affording encouragement to all parties concerned,
as to the future prospects of the undertaking. Between the 20th of
July, 1837, and the 14th of February, 1838, there had been no less
than 162,216 passengers conveyed along the Railway, without an
accident to any individual, except one elderly lady who lost a front
tooth, ― but, upon strict enquiry, it was clearly ascertained to
have been loose before.
It was considered of more importance that passengers should be able
to rely on a certain and safe conveyance to and from the stations
where the trains stop, than that they should, in the first instance,
travel at the highest possible speed: the chief aim of the
directors, in the regulation of the trains, was to ensure a uniform
precision of movement on the Railway. In this endeavour they were
ably seconded by their contractor for locomotive power, Mr. Bury;
and a degree of punctuality in the arrivals and departures has, for
some time past, been attained at all the stations, which,
considering the unavoidable imperfections of a road so recently
formed, and the many difficulties to be surmounted in every new
undertaking, could scarcely have been anticipated, and, it may be
added, which has not been accomplished upon any other Railway. The
only thing, in fact, which prevented this regularity from being
universal, was the delay consequent on the coaching between Rugby
and Denbigh Hall, and the circumstance that some of the trains have
to wait the arrival of the passengers by the Grand Junction Railway.
The preparations for the carriage of goods have occupied much
attention; and the directors, aware of the advantages of combining
experience with system, in the management of a business so extensive
and complicated as the future goods traffic will most probably be,
have engaged the valuable services of Mr. Baxendale, of the
well-known firm of Pickford and Co., to conduct this department,
under a contract which is to take effect from the opening of the
Railway for this branch of business.
An agreement has been entered into, by which this Company rent the
Aylesbury and Tring [Ed. ― for 'Tring' read 'Cheddington'] Railway, at £2,500 per annum, being five per
cent. on the estimated cost, for five years certain; and looking to
the importance of the traffic from the fertile vale of Aylesbury,
and the communication which this branch will open with Oxford and
other places, this agreement must be considered a very advantageous
one. The inhabitants of Banbury have also, at a general meeting,
resolved to make a new road to the Railway, by the shortest route,
at Weedon, where a first class station will be made; and the same
may be expected at all other towns which do not possess the
requisite commodious means of getting to the Railway. In fact, from
Northampton to Blisworth a line of railway has been projected; and
the promoters applied to the directors to place the making of it in
the hands of the Company’s engineer, ― to which an assent has been
given, and the works are forthwith to be commenced.
In August, 1838, the expenditure was £4,592,698, and the loans
amounted to £2,119,000; the land amounted to the sum of £622,507. From January the 1st, to April the 8th, when the line was only open
from London to Tring, the number of passengers conveyed amounted to
36,024, being a daily average of 244 for the whole thirty-two miles,
and the receipts amounted to £7,272, while the expenses were no less
then £8,049; but from the 9th of April to the 30th of June, the
number of passengers was 122 ,814, being an average for the
seventy-seven miles of 715; the receipts, deducting the expenses of
the intermediate coaching, were £41,324, and the expenses £16,098
only.
It was proposed, for the accommodation of passengers by the Railway,
that an hotel and dormitories should be established on an extensive
and unappropriated piece of ground belonging to the Company, in
front of the Euston Station, leaving sufficient space for a handsome
entrance, the hotel to be erected on the east side, and the
dormitories on the west, according to at plan prepared by the
Company’s architect.
The directors of the Railway Company for the time being, are
trustees of the land at a nominal rent, and have formed a company
with the requisite capital, to be raised in shares of £25 each; the
trustees are to have the entire control of all the buildings, and
are to agree with one or more respectable tenants for the
occupation, at rents calculated to afford ample remuneration to the
shareholders for their outlay. The building on the east is to he
arranged for all the purposes of an hotel, with a spacious
coffee-room for the accommodation of the inmates of it, and of the
persons in the dormitories who may he desirous of availing
themselves of the hotel coffee-room.
The building on the west is to be arranged for dormitories, and
divided into as many rooms, of convenient dimensions, as the
allotted space will admit of, — a proportion of the number to have
small sitting or dressing-rooms attached to them, so that passengers
on their arrival may be accommodated with a sleeping-room, and if
required, a sitting-room; each of the apartments to be charged at a
price varying according to the floor and scale of accommodation. A
coffee-room is to be also established in the same building, for
breakfast and refreshments; but the house is not to be licensed for
wine or spirits; the dormitories are to be altogether a separate
establishment from the hotel. Convenient baths will be erected in
each building; and it is further intended that a space of ground,
situated near these establishments, should be appropriated to a
mews, for the convenience of persons requiring post-horses, and for
the minding of horses and carriages at livery.
The charges of every description, including attendance in the hotel,
dormitories and mews, are to he regulated according to a scale which
every person will have an opportunity of inspecting. The shares were
all offered, in the first instance, to the Railway proprietary, to
accept or not as they thought proper; and the buildings were
commenced forthwith. It is a pity the same thing is not done at the
Birmingham end; although passengers can there be accommodated with
breakfast and luncheon, at a fixed charge, including servants. The
main object of the undertaking being to promote the success of the
Railway, by providing for the comforts of the families and
individuals who travel on it, there is evidently as much reason for
it at the one end as at the other.
On the whole of the passenger and parcel traffic, to the 30th of
June, 1838, the receipts were £83,234, and the disbursements,
including £16,755, paid for intermediate coaching, amounting to
£53,380, leaving a balance in the Company’s favour of £29,854; which
was certainly more than there was any reason to expect, through the
drawbacks arising from various causes. In fact, the principal end
and aim in opening the two ends of the line was not profit, but
advantage, to the concern, in getting every one drilled to his duly
prior to the final opening for the whole length; as it turned out,
however, it was both useful and profitable.
At the general meeting in February, 1838, the directors adverted on
a far more extended scale in the goods department than was
originally contemplated; and the enquiries which they made, in the
next six months, sufficiently demonstrated the necessity of a large
and immediate outlay, not only as respects the proposed arrangements
for this description of traffic, but for some additional
accommodation in the passenger department. The central station for
engines and goods at Wolverton, the goods stations at Birmingham and
London, and along the line, required to be at once commenced. The
additional stock of engines already contracted for, and an increased
number of wagons and trucks, were also urgently required; and it was
seen that further sums would be wanted, to complete the works of the
road, and to wind up the accounts of the contractors.
The directors always felt it to be a part of their duty not to
restrict the proper outlay of capital, when satisfied it would
secure the convenience of the public, the stability of the works,
and the efficient management of the traffic; and they felt persuaded
that a perseverance in this course, to the completion of the
undertaking, would be found most economical in the end, and best
calculated to ensure the permanency of that successful result which
is now happily placed beyond the reach of doubt.
At the general meeting in August, 1838, the difficulties at
Wolverton, Blisworth, Kilsby, &c., having been successfully
overcome, and a single line of rails having been laid, on which a
train, with several of the proprietors, had passed over, from end to
end, the engineer-in-chief reported that the entire opening of the
line might be expected in September; but that he was prevented from
fixing the day, as a portion of the work remaining to be done
depended, in some degree, on the state of the weather.
The above train went the whole distance, exclusive of stoppages to
examine the works, in five hours; but the directors have always
looked at safety so much more than speed, that they limited the
trains to six hours on the opening, till the winter months are got
over, and the embankments become more consolidated.
A great deal of the increase in the cost of the work arises from the
extension given to the plans of the stations, on which so much of
the good working of the Railway will consist. They may be made on
almost any scale, and in the original estimates were taken very low
— namely, at £19,600; whereas our estimate is that they will cost
£460,000. When the original calculations were made there existed
hardly any guide whatever for any one to make an estimate, and but
little former experience to lead the way, there being no other line
in operation from which could be derived the means of coming at an
accurate conclusion, in a concern of such magnitude, — so on this
account there is less blame to be attached to any party than would
at first be supposed.
The Company have never found the least difficulty in borrowing money
on their credit, and they were doing so in August, 1838, till they
could apply to Parliament for power in raise more capital, which
will be granted as a matter of course, when it is seen that
£5,000,000 has been bona fide expended in carrying out the works,
and that they are now so far advanced towards a final completion,
that the line has been in constant operation with passengers for
some months.
The engines at present employed upon the line are as follow:—
1 |
Made by Mr. Bury, Liverpool |
20 |
Made by by Mr. Hawthorn, Newcastle |
2 |
―――― |
21 |
―――― |
3 |
―――― |
22 |
Made by the Haig Foundry Company, Wigan |
4 |
―――― |
23 |
―――― |
5 |
―――― |
24 |
―――― |
6 |
―――― |
25 |
Made by Rothwell & Co., Bolton |
7 |
―――― |
26 |
―――― |
8 |
―――― |
27 |
―――― |
9 |
―――― |
28 |
―――― |
10 |
Made by Hicks & Co., Bolton |
29 |
―――― |
11 |
―――― |
30 |
―――― |
12 |
―――― |
31 |
Made by Mather Dixon & Co., Liverpool |
13 |
―――― |
32 |
―――― |
14 |
―――― |
33 |
―――― |
15 |
―――― |
34 |
―――― |
16 |
Made by Mr. Hawthorn, Newcastle |
35 |
―――― |
17 |
―――― |
36 |
―――― |
18 |
―――― |
|
|
19 |
―――― |
|
|
A very superior engine was also made by Robert Stephenson, for
carrying the trains up the inclined plane from the Euston Square
station to Camden Town, till the fixed engines were completed; and
the performance of the whole has been most satisfactory, as may be
judged from the following instances.
The average of fourteen trips, of twenty-three miles, up 1 in 440,
with the engine No. 16, was twenty-two miles an hour, with a gross
weight, including the tender, of seventy-five tons, — viz., fourteen
carriages and one hundred and forty-eight passengers: the
consumption of coke was 148 lbs.
The average of fourteen trips, of three-quarters of a mile, up 1 in
90, from Euston Square to Camden Town, with the large engine built
by Robert Stephenson and Co., was fifteen miles an hour, with
seventy tons, — viz., fourteen carriages and one hundred and
forty-eight passengers. The engine No. 7 built by Mr. Bury, went ten
miles in ten minutes with only one cylinder working, four of which
miles were up an incline of 1 in 660. Comets are said to be only
young planets navigated by steam, and occasionally going to the sun
for a few more sacks of coke; and we shall, by-and-by, rival the
American Locomotionist, who is going to put a handful of chips in
his pocket, borrow a tea-kettle, and set off for the moon.
It is to he noted, that although the London and Birmingham engines
are made by different persons, they are constructed exactly alike,
in all their parts, and of an exact size every where, being entirely
made from working drawings given out by Mr. Bury of Liverpool, who
contracts to work the line. This will, eventually, conduce to great
economy, as every individual part of an old and disabled engine,
which is worth preserving, can be used in the formation of at new
one.
Whether the mode of contracting for locomotive power, or that of the
Company’s working their own engines, will be the best, is not yet
known — the method of contracting not having been sufficiently
tried. Mr. Bury has only commenced since the line has been opened
the whole length. In fact, we are yet so much in our infancy with
respect to all railway operations, that we may say we have every
thing to learn, and to learn by the most expensive of all processes
— experience.
It was matter of great doubt, at an early period of the railway
system, how it would act when the snow laid so deep upon the ground
as to interrupt the ordinary communications on the common roads:
they have, however, completely triumphed over all difficulties of
this sort. This was strikingly proved on the Newcastle and Carlisle
Railway, where the possibility of so working was fairly put to the
test on the 26th of December, 1836; and the utility of railways
demonstrated in the fullest manner. In the deep cutting through the Cowran hills, the snow had drifted to the depth of four or five
feet; and when the ‘Hercules’ engine came down, on the morning of the
above day, great numbers of the country-people assembled to see how
it would act in such an emergency, and to render any assistance
which might he required. On arriving at the spot, however, the
engine made no bones of the matter, but dashed right into the drift,
clearing its way through, apparently without the slightest
difficulty; the snow, at the same time, flying over the top of the
engine chimney like foam from the broken waves of a violent sea; and
notwithstanding this and similar obstructions, the train came down
from Greenhead, twenty miles, in one hour and a quarter. The trains,
in fact, continued to keep their times, while all communications by
common roads were more or less seriously obstructed, if not entirely
out off.
Before a railway can be opened even partially, cursory observers
would hardly credit the number of small items which have to be
provided, the procuring of which coats in the aggregate no sum of
money; and in a concern of such magnitude as the London and
Birmingham Railway the expense was commensurately great, as it was
no use to incur an additional outlay, when the line was completed,
by fitting out the two ends previously to their opening in a
temporary way; the plan pursued was, therefore, one which would
harmonize with the whole arrangements when the line was entirely
finished.
The preparations for lighting the Euston Square, Camden Town, and
Birmingham stations, took up considerable time and labour. These
stations are all supplied with gas, by contract, on very fair terms,
from the Gas Companies whose works are adjacent to them; large mains
being laid throughout the whole of them, from one end to the other,
in situations which admit of smaller mains being brought into all
the various buildings; from these branched pipes of different sizes,
so as to convey the gas into all the various rooms and offices,
passenger sheds, engine houses, coke vaults, carriage sheds, &c., as
well as generally about the ground, in sufficient numbers to give an
efficient light, and at the same time with a due regard to economy. It was also found necessary to light up the whole of the extension
line between Camden Town and Euston Square, and at the Birmingham
end provision is made for the lights to be continued to the end of
that noble structure, the Lawley-street Viaduct: proper gas meters
are fixed in places which ensure the quantity burned being correctly
ascertained. The locomotive and goods departments having each
separate meters to show their respective consumption.
In the department of the resident engineers, there had to be
provided ballast engines, ballast wagons, hand trucks, and
implements of all kinds, every railway requiring to be constantly
rose with ballast on the embankments for a long time after its
construction. Land was purchased in situations where the requisite
materials could be excavated; and, at stated hours, so as not to
interfere with the regular traffic along the line, the ballast is
brought in the wagons to convenient spots near where it is required,
and then distributed in the hand trucks, which, from their small
size, can always be readily lifted off the rails, to allow the
passage of the trains.
All the requisite tools for laying and repairing rails, joins,
crossings, eccentrics, turnplates, &c., had also to be provided —
such as chisels, hammers, crowbars, levers for lifting the rails and
blocks, bearers, rammers, drills, gauges, sights, spirit levels, &c.
— to a large extent; the plate-layers being distributed in gangs,
one overlooker being stationed to each district: these districts are
from four to eight miles in length, according to the state of the
road, each having a complete set of tools. Under the overlooker is a
foreman, time-keeper, and from three to six men per mile, who are
continually employed in repairing those various parts of the line
which are found to be most out of order. The resident engineers
receive all their tools, and implements of every kind, from the
store-keeper, by written requisitions which they make on him.
The various inclinations on the line are marked at every change, the
top of the mark showing whether the train is about to go down or up
the inclination, by being cut with a slope. This is reversed for the
opposite line of rails on which the trains travel in the contrary
direction; each quarter of a mile is measured and marked; this is in
accordance with the Company’s Act of Parliament. We are not aware,
however, whether Parliament defined the sort of mile-posts which are
set up.
In order to prevent accidents as much as possible, although men are
properly stationed to all the eccentrics which turn the switches, a
signal has been contrived which must, in all cases, show when they
are wrong; consequently, if the engine-man keeps a proper lookout,
he can never get off the line from that cause. This signal is as
follows: when the sliding-rail is put in a wrong position, it turns
an upright rod round, and this carries on its head a red and white
lamp by night, and a red and white canvass signal by day; in either
case the red is shown to the coming engine when the switches are
wrong, and the white when they are right. The gates at all the paved
crossings along the line show similar signals by night and day,
which are in all cases worked by the opening and shutting of the
gate.
The points and crossings work very well on this line; but there are
so many different sorts in use on the various railways, each having
their firm advocates, that every one must be convinced there is yet
more to be done — certainty and simplicity seem to be the leading
requisites here; and we have no doubt that before long, these
essential things will be moved by the engine itself, which would
effect a considerable saving; a new kind is, however, now being
introduced which is an improvement on the old switch rail and seems
to answer well.
Except at the principal and out-stations, no siding-places have yet
been made; nor can this be done till the nature of the traffic,
viewed as a whole, is seen. So much depends on the quantity of the
goods requiring to be carried, and the degree of speed at which it
is desirable to travel that the longer the construction of the
siding-places are deferred the better. So much is saved in the cost
of locomotive power, by travelling with the goods at a decreased
velocity, from that which the public has a right to expect in the
case of the passenger trains, that a well-organised system, enabling
two to pass each other by means of siding-places, situated according
to a thoroughly matured plan, in unison with the nature of the
traffic, would form a most essential feature in this and every other
railway.
In the locomotive department, preparations of all kinds have been
made to ensure the safe and economical working of the Railway. Each
engine carries a box of tools; the various out-stations where there
are locomotive engine-houses, have them fitted up with forges,
vices, and work-benches, enabling the engines to receive trifling
repairs. In the locomotive engine-houses at Birmingham and London,
more extensive works are carried on; but the whole of the repairs of
consequence which may be necessary, will be done at Wolverton, near
the centre of the line, where preparations have been made on a scale
fully equal to what will be required.
Each station is furnished with an alarum, to give notice of the
approach of all trains, and to summon the whole of the men to their
appointed places. These alarums are so constructed, that a weight is
wound up after they have performed their office; this prepares them
to perform it again. On the policeman, stationed at them, seeing the
forthcoming train has reached the proper spot, he pulls a trigger,
and the weight begins to descend, ringing a loud gong-shaped bell by
means of internal machinery: this leaves the policeman at liberty to
watch and attend to the safety of the train. Bells are also hung, so
as in a few seconds to collect together the whole of the men
belonging to the station, for any required purpose.
Large wagons will be prepared, on which engines or carriages can be
carried: these will he furnished with all sorts of implements
requisite to enable them to bring in damaged engines or coaches,
such as tackles, shears, ropes, winches, levers, screw-jacks,
slings, chains, &c., together with all the requisite tools. These
wagons will be kept ready to be dispatched at a moment’s notice, so
as to enable damaged engines or carriages to be immediately removed
from off the line, and taken to a proper place for being put into a
state of repair. This will be much aided by the system which has
been adopted, of having every thing to one exact scale, so that what
will fit one engine will fit all the others — a system which has
also been carried out in the manufacture of the carriages to a great
extent.
In the coaching department, a great number of implements have been
required, in order to ensure ready working of the line, such as
short ladders, or getting on and off the arrival and departure
stages; long ladders, for loading the luggage on the roofs or the
carriages, and other purposes; steps, for loading luggage at the
departure stage; shoots, for letting the luggage run off the
carriages at the arrival stage; circular stands, to receive the
luggage when taken off the carriages, so as to enable the passengers
to select their own; trucks, for wheeling about luggage, parcels,
&c.; notice boards, to direct passengers to the various booking
offices, waiting-rooms, refreshment rooms, &c.; luggage gauges, for
the carriages to pass under when loaded, in order to see that the
load is not too high to pass under the bridges; lamp boxes, grease
boxes; stands for coupling bars; sentry boxes for the policemen, the
watchman, and the gate-keepers: together with a great variety of
other things, too numerous to mention, were all requisite before the
line could be correctly worked.
Where the turnplates are opposite the arrival or departure stages,
large bays are obliged to be cut out, to enable the carriages to be
turned, otherwise the buffers would not admit of their going round:
sliding platforms had to be made for these, so as to draw back on
rollers, to admit of the turnplates being used, and yet, when rolled
forward again, to leave no break in the continuity of the stage. Proper places for the embarkation and disembarkation of horses and
carriages, with the requisite means of connecting the boxes and
trucks, which were to convey them, with the road on which they came
down to the station, together with the proper fastenings and means
of securing them, had all to be brought into working order, before
any precision or regularity could be arrived at.
The best modes of lighting the carriages, and instituting the
necessary signal lights, had also to be put into operation. The
lights necessary for these purposes are, for the carriages, a simple
means of giving to the inside of the carriage, a soft and mellow
light, sufficient to enable the passengers to read with ease, and
yet not to dazzle the eyes. This has been effected by a lamp
invented in London; and we think still better by one which we
ourselves have invented (it would be odd if we did not think so). In
size, mode of fixing, and appearance outside the carriages, both
lamps are nearly similar. They are fitted in a hole cut through the
roof; the part remaining above the roof is protected by a box; that
part which comes through the roof, has the appearance, to a person
sitting inside, of a glass saucer; in the London one the glass is
plain, which occasions a dazzling to the eyes of those who are at
all weak in that organ; in the Birmingham ones this is obviated by
the saucer being made up of ground glass. By an improved
construction of the fountain principle, the latter lamp is rendered
as nearly shadowless as makes no matter — the body of the lamp being
entirely above the flame, and the connection between the two
consisting of a tube, not more than 3/16ths of an inch in thickness,
which should always be turned towards the door of the carriage. These lights are used by day as well as night, to illuminate the
carriages while they are going through the tunnels.
It is requisite that the trains show as a head light a white light,
and as a tail light a red one. We have proposed, as a substitute for
these, an arm revolving between two uprights on the centre carriage
or thereabouts of the train; the arm to revolve on a pivot through
its centre, and to carry a lamp at each end; this arm being
connected by a simple drum and strap with the axle of the coach,
may, of course, be made to revolve at any required velocity; the
number of revolutions which it makes in any given number of seconds
being known at all the stations. It is an indicator directly it
becomes distinctly visible, not only of the approach of the train,
but of its rate of speed; when the train stops it is, of course,
stationary, and if the train backs astern it moves in a reverse
direction; thus informing any person either before or behind a train
of all its motions, and the rate at which it is travelling. Powerful
lenses should be used both for the fore and back lights, either of
which can show a red light at pleasure; — both these and the
roof-lamps are patented.
Fitting out the store department, and furnishing it with a
sufficient stock of articles for the supply of all the various
branches of consumption along the line, was a work of no little
labour, and of the greatest importance. To ascertain what was
required, in what quantities, at what times — to ascertain the
current prices, so as to be able to check the contractors — to issue
and close the necessary contracts — and to find storage for the
whole, where it would not only be preserved from damage, but he at
all times easily accessible, required no small share of
consideration; even the stationary branch alone contains several
hundred books, forms, and papers of various kinds, branching out
into all the various departments, and as yet no regular storehouse
has been built either at London or in Birmingham; temporary
accommodation being all which it has been possible to procure: for
some time yet, every nerve having been strained to effect the entire
opening of the Railway, and all other objects rendered subservient
to this.
The fittings of various kinds to the buildings at the principal
stations amounted to a considerable item. When these buildings were
delivered over by the contractor, of course they consisted of
nothing but the bare walls; and they had then to be put into such a
state of equipment, as to furniture, as would fit them for their
various uses. The locomotive engine-houses had to be supplied with
forges, workbenches, vices, tools of every kind, with a reserve of
each in store; a large stock of coke had to be provided — coke
cranes had to he erected, — materials for cleaning the engines to be
procured — together with a thousand minutiae gathered together,
which are only known to practical men, but all of which require
time, attention, and money, to set in order before work could he
attempted.
The superintendent of police is responsible for the general good
conduct and order of all the men under his charge, and he is
required to reside where he is appointed, and to make himself well
acquainted, by frequent personal intercourse, with the character and
conduct of every man under his orders, and to take care that all
orders and regulations issued from time to time are promptly and
strictly obeyed, and that clear and concise instructions are given
to each man, so as to insure the correct performance of all their
duties, he being held responsible that they are properly understood. He furnishes a daily report of occurrences, detailing every instance
of neglect, and every complaint which has been made to him, from
whatever quarter; and he may at once, if the nature of the offence
requires it, suspend the offender, or take any other precaution
which may appear to be necessary. He has also the charge of
examining all the weekly pay-sheets, previous to their audit, the
men being paid under his especial superintendence; and he also takes
care that each man’s signature is attached to his amount.
There is one inspector of police at each station, who has to reside
wherever he may be appointed and to attend at all hours when
required. He is directly responsible to the superintendent of
police, from whom he receives all his instructions, and to whom he
makes a daily report of every thing which occurs; and in the case of
any neglect of duty, or misconduct on the part of any of the men
under his orders, and in every ease of a complaint against a man,
he, without delay, communicates the particulars to the
superintendent, sending the offender to head quarters; if the case
requires it, as soon as possible; he sees that all orders, as they
are given out from time to time, are promptly and strictly attended
to throughout his district, the limits of which are of course
defined.
He has the control of all the policemen at his station and in his
district, and is held responsible for their attention, good conduct,
and efficiency. He has also under his charge all the switches, to
which the most vigilant attention is required. It is his business to
render every assistance in his power to the clerks and guards, and
supply as quickly as possible any wants which they may communicate. He also regulates the weekly payments — paying the money, and
obtaining every man’s signature to the amount — and transmitting a
weekly completed pay-sheet to the superintendent, comprising the pay
of all the men in his district.
The men receive their money weekly, on an appointed day, being paid
from lists which are all regularly audited; and any debts which they
contract, if not immediately paid on orders to that effect being
given, the amount is deducted from their salary. They are not to
leave the Company’s service without giving one month’s previous
notice of their intention; and in case they quit without such a
notice being given, all their pay then due is forfeited. If any
articles in their charge are damaged, or improperly used, a
deduction from any pay then due is made, sufficient to make good the
damage or to supply a new article. Each man is liable to immediate
dismissal for disobedience of orders, negligence, or other
misconduct; and every man dismissed from the Company’s service, or
who may resign his situation, must, before he quits their employ,
deliver up every article of dress, and of the appointments which
have been supplied to him.
No instance of intoxication in ever overlooked, and may seem missed
from the Company’s employ on this account is also liable to be fined
before a magistrate. Any case of rudeness or incivility to the
passengers is promptly punished. All the men are also considered
liable for damages done through negligence, and they are at all
times ordered to appear in their proper uniform, in a state of
neatness and cleanliness. One shilling per week of their pay is
deducted to form a sick fund. The pay of men sick, or absent without
leave, is always suspended for the special orders of the committee
on the case.
There are two guards to each train, the under guard obeying the
directions of the upper, who carries the time-piece slung by a belt
across his shoulder, and he is required to reside wherever the
arrangements of the trains render it necessary. The guard receives
his instructions from the head station-clerk, and he reports when
the train is ready to start. The train is entirely under his
control, and the passengers and their property under his protection,
and he is responsible for the safety and regularity of the whole,
taking care, previously to starting, that the carriages are properly
coupled, — that the requisite number of brakes are in the situations
assigned for them, and that they are in proper working condition, —
that an adequate number of tarpaulins are provided, and the luggage
[Ed. — carried on the carriage roofs] properly covered up.
He has also to see that the signal lamps are attached, and the roof
lights in proper condition, and that the carriages are in a fit
slate of cleanliness and efficiency; — reporting every deficiency to
the chief inspector, to ensure an immediate remedy. He is not to
allow any of the passengers to stand upon the coaches while the
train is in motion, nor in any other manner endanger themselves by
imprudent exposure; and in case of accident or obstruction to the
train, he must consider the speedily forwarding of the passengers of
the first importance, or whenever this proves to be impracticable,
he must adopt the quickest mode of communication to the next station
and to head quarters.
He keeps an exact record of each journey, with the fullest
particulars of every occurrence on the road, the times of arriving
at, and starting from, each station, and the causes of any detention
which may arise; and, in case any persons show a pass, he must
obtain and report their names on his arrival. On reaching London, at
the Camden Town station, he is instantly to communicate the number of
coaches in the bankrider, who takes charge of the train down the
inclined plane — he is to inform him of the number of efficient
brakes, and surrender the whole into his charge, to be conducted to
the Euston station — himself acting under the bankrider’s
directions.
The bankrider has the entire control and management of the inclined
plane from Camden Town to Euston Square, and of every thing which
passes up or down; he attaches the rope to every train of carriages
which is drawn up the plane, and suffers nothing to descend but that
which is conducted by him, — every man upon the plane implicitly
following his directions. He carefully inspects into the condition
of every train, and ought never to attempt to move it till he is
perfectly satisfied of the safety of every part. He sees that the
rope and sheaves are kept in proper condition, and the sheave axles
well greased; he uses all the vigilance in his power to prevent any
rubbish being placed on the inclined plane, or any obstruction of
any kind, and reports any omission to convey the requisite signals,
at the top or bottom of the plane, by the persons employed to do so;
he gives constant attention, not only to the brakes, but to the
wheels, grease-boxes, and other parts of the machinery of the
carriages coming under his notice, and reports any negligence or
imperfections he may have observed, and he is constantly supplied
with signal flags, or well-trimmed lamps, to give the necessary
signals.
The police are placed along the line, at distances varying from one
to three miles, according as local circumstances render it
necessary. Each man has his beat and duties defined in all cases;
and is provided with two signal flags, one of which is red and the
other white; the white flag is held out when the line is clear, and
no obstruction exists to the passing of the train; and, on the
contrary, the red flag indicates that there is danger, and the train
must not pass this signal till it is ascertained that the cause of
danger is removed. When the pole is dropped horizontally on the
shoulder, it indicates that the policeman wishes to communicate with
the train.
Each policeman is likewise furnished with a revolving signal lamp to
be used after dark, which shows, at the will of the holder a white
light when the line in clear from all obstruction, a green light
when it is necessary to use caution and the speed of the train must
be diminished, and a red light to intimate the necessity of
stopping.
The constables placed on a beat, when they first come to their
stations every morning, immediately walk the whole length of their
beat, to see that the line is in all parts perfectly clear; the
constable on the first beat from London comes on the south end of
his beat and walks north, and the constable on the second beat comes
on the north end and walks south, and the two meeting, where their
beats join, communicate to each other the state of the line. The
same rule is observed all along the line, the constables acting by
pairs, and they are required to meet where they relieve each other
for meals. The gate-keepers, switchmen, and others, at particular
posts, are not included in this arrangement, in consequence of their
being fixtures. In case of any obstruction, which it is not in the
power of the constable himself to remove, he may summon the nearest
assistance, and refer the party for remuneration to the inspector of
the district, to whom he is to report all the circumstances as
promptly as possible.
The foreman porters at London and Birmingham, and the collectors of
tickets at the out-stations, have the control over the other
porters, and are responsible that the carriages are in proper
condition, the luggage properly stowed, and every thing ready for
the train going at the appointed time, — informing the inspector
when the train is prepared to start that he may give the signal at
the proper time. They also have the charge of all stores belonging
to the coaching department.
The whole of the men on the permanent establishment are identified
by numbers, are clothed in a green uniform, and receive annually the
following articles of dress and appointments:—
Inspectors. — One body coat, two pair of trousers, two pair
of boots, and one hat, with a great coat every two years.
Porters. — Two jackets, two pair of cord trousers, two pair
of laced boots, one cap.
Guards. — Two frock coats, two pair of trousers, two pair of
boots, and one hat, with a great coat and cape every two years.
Police. — One body coat, two pair of trousers, two pair of
boots, one hat, and one stock, with a great coat and cape every two
years.
The process of auditing the books and cash documents connected with
the passenger and parcels is as follows, (and a similar mode is
adopted of auditing the accounts of all the other departments, all
vouchers remaining in the audit office):— Every book in any way
relating to cash is kept in duplicate, one set being in use for the
week, while the set used the previous week is sent up for
examination at the audit office; and at the end of the week the
audited set are sent out to the various stations to be used, while
they send up to the audit office those last used and so on,
alternating the sets every week.
A storekeeper has the supervision of all stores, materials,
utensils, coke, stationary, books, tools, and all other articles
required for the use of the coaching, engineering, and all the other
several departments throughout the line, of the whole of which he
has the custody and distribution; his accounts exclusively comprise
quantities, without having any reference to money. Whenever an
article is required for the use of any department, a requisition
note or indent is addressed to the storekeeper by the principal of
the department, which is the storekeeper’s voucher for the demand.
If in store the article is immediately supplied and a receipt note,
descriptive of the article, and stating its delivery, is taken by
the storekeeper, which is his voucher for its delivery.
At the passengers’ booking offices, at the termini, the cashier has
the sole charge and control of the office, and of the persons
employed therein, and he has the sole custody of all money received
for passengers, parcels, horses, carriages, or any other thing, the
cash being transmitted to him by all the other booking clerks after
each train. The money taken at the out-stations being also sent in
to him, and the whole is by him placed in the bank, — all the
receipts, including excess fares, and every other bunch of revenue,
passing through his hands only. He is also responsible for the
accuracy of the accounts, and for the punctual dispatch of the
business of the office; he prepares the daily statement of the
passengers and fares, also the weekly account current; he also makes
the necessary calculation of the Government duty on the passengers,
paying it monthly at the Stamp Office.
The ticket books are originally sent from the audit office for each
station, carefully numbered and registered, and when transmitted to
the audit office at the close of each week, they are rigidly
examined, and every ticket which has not been accounted for in the
summary, or shown to have been destroyed, is placed against the
principal booking clerk of the station where the omission has taken
place; this is for the traffic from the termini which is all done by
tickets, but the traffic from one out-station to another, is carried
on by means of cards, a number of which, proportioned to the
traffic, or to the avenge issue, are sent weekly to each station,
numbered and stamped with a private mark, as well as with the names
of the stations through which they are intended to pass.
The principal booking clerk of each station, has placed to his
account the number of cards transmitted to him, and receives a
deduction for all he issues, taken from the summaries at the end of
the week; the cards not issued or remaining on hand, are then
returned to the audit office, and if they do not accord with the
number in the card issue book, the principal booking clerk is held
responsible for the difference.
A schedule of errors is prepared weekly, referring to each station,
in which all errors and negligence, of whatever description, during
the previous week, arc recorded, and explanations are in each case
required of every irregularity, all cash errors being amended in the
succeeding week’s account current. An excess and deficiency of the
cash-book, is kept at each out-station, and this is transmitted with
the weekly accounts to the audit office; this either establishes or
impeaches the accuracy of the principal booking clerk’s cash
account.
The irregularities in the ticket collections, if any, are also
noted; and, in general, every transaction is rigidly and thoroughly
examined. The objects attained by these searching enquiries in the
audit office being as follows; — every card and ticket issued is
accounted for, or the principal booking clerk has to pay for its
value; no ticket or card is ever issued for less than its value, or
the clerk at the out-station pays for the difference, and every cash
transaction is correctly calculated and traced from its origin, till
the money is paid into the banker’s hands. The examining clerk is
assisted by lads, who are principally occupied in classifying,
numbering, sorting, and stamping the cards and tickets under his
superintendence.
The business at the out-stations requires great attention and
accuracy. On the clerk commencing his business in the morning, he
first makes out his passengers way-bill or docket, this is always
taken forward by the guard of the train; it is made out in
duplicate, one for up the line and the other for down, each being
printed on different coloured paper. These tickets state all the
particulars relative to the train, with the number of passengers,
their fare, and every other necessary information.
A summary of each departure train is made out as soon as it has left
the station, showing the number of passengers, parcels or goods and
their fares, and a statement of the excess fares, and the reason of
them; a classification of the daily totals is also made and sent in
to the audit office, on which is also stated the money received for
goods, parcels, horses, carriages, cattle, and booking, all of which
is sent to the principal booking clerk, who sends it away by the
last train to London and Birmingham, so that no money ever remains a
night at any station except the termini.
The tickets are printed on coloured paper; they require four
colours, yellow and blue for instance, for the up trains, the first
class being yellow, and the second class blue; the different classes
down being distinguished by white and pink; these tickets are all
collected by the guard at the last station before arriving at London
or Birmingham, and the whole for the day are transmitted to the
audit office by the first train the next morning: this is the method
with passengers going the whole length of the line, and for those
who get down at the out-stations, they are admitted one at a time at
it wicket where their tickets are taken, and it is ascertained
whether they have paid their fare to the right place; the tickets
are not collected by the guards, till all the passengers have got
into the carriages, who are going from that station to the terminus,
by which means he gets theirs also. The tickets taken at the wicket
are also sent to the audit office on the following morning, with a
statement of their number and amount, a statement of those issued,
and a return of the number of cards collected and issued; those
cards are used between one out-station and another instead of
tickets, but the same steps are taken with them as are made use of
with the tickets.
In all papers of any kind, throughout every department, nothing that
can be printed or stamped is written; this very much conduces to
precision and accuracy.
In the same manner, way-bills are made out for the parcels, each
package having a ticket pasted on it of coloured paper. These are of
a different colour when the package is to go the whole length of the
line, to that which they have if they are to be left at any of the
out-stations, as a guide to the guard. At the termini, there are
separate offices for goods and parcels distinct from the passenger
office.
In the above slight sketch which we have given of the manner in
which the railway is worked, it will be sufficiently seen that the
system which has been established aims at affording safety, and as
much accommodation, as present circumstances will allow, to the
passengers, and a perfect check on the money transactions of the
Company. The latter is a most difficult point, and will require some
time to perfect in all its various details, which is by no means to
be wondered at in a concern of such magnitude; the wonder is, that
the business has been conducted so satisfactorily as it has, and it
now only requires simplification.
The entire line was opened to the public on the 17th of September,
1838; and the problem will now soon be solved, to which so many
anxious hopes have been directed — namely, what will be the
dividend? The standing joke on railway estimates has long been —
“double the expenses and halve the profits.” We rather think, on the
London and Birmingham line, one half of the prophecy will receive a
tolerable defeat.
No one has watched the expenditure on this line more narrowly than
we ourselves have done; yet although we were till lately far ahead
of every one else in our prediction of its cost, it was not till two
years after we began to estimate the outlay, that we come
sufficiently near the ultimate sum; and this only by making use of
an entirely new method of working out the estimates. We drew these
up every six months, and the following are the minimum amounts which
we successively calculated would be necessary to complete the work
February,
1835 . . . . |
£3,742,000 |
August,
1835 . . . . |
£3,770,823 |
February,
1836 . . . . |
£3,886,227 |
August 1836
. . . . |
£4,232,486 |
February,
1837 . . . . |
£4,929,197 |
August,
1837 . . . . |
£5,228,620 |
February,
1838 . . . . |
£5,278,302 |
August, 1838 . . . . |
£5,288,155 |
It is now nearly two years since we affirmed that the cost of the
work would not, without difficulty, be kept on the right side of
five millions; and since that time we have had to endure, divers
rubs, manifold quizzings, sundry jokes, and various jeers — of all
sorts and sizes, from a kitten’s ears to a horse’s collar — we have,
in fact, been rubbed up, and than rubbed down again, both wet and
dry, all in good humour, of course, poetical effusions included; and
now, having beaten our adversaries at all points, we are entitled to
a gentle joke in return.
Nothing could equal the vagaries which were played with these
unhappy estimates of ours —“This can’t be allowed,” — “This must be
reduced one half,” — “This must be knocked out altogether,” — “This
is full four times too much,” — and away went the pen across the
figures, like the boys playing at ducks-and-drakes on their slates,
till, heaven help us for our sins, they were in several instances
reduced to about a million and a quarter; if we had been at all
addicted to nervousness, we should have certainly fallen into
jigsterics [sic.] on more than one occasion: we were sure to be
wrong which ever way we went, like the unfortunate French actors,
whom the Bishop of Arras, in 1695, prohibited by an edict from
marrying, and afterwards anathemised for living avec les concubines;
or like Mr. Murphy, who is always either weather-wise, or
other-wise. Now, however, the expenditure being on the wrong side of
the five millions, we will just quietly recommend our worthy
friends, on a similar occasion, to remember the honest advice of the
patron, “We are all very smart at finding out the handspikes in
other people’s eyes, but we don’t say much about the capstan bars in
our own.”
The enormous price paid for the land we have before given some idea
of, and this system of robbery is not confined to one part of the
country or another, but seems general. The following remarks, from
the Railway Times, will amply bear out this opinion: ―
“The
extortionate claims of land-holders for compensation, in respect of
property required by railway companies, have again and again been
animadverted upon by us, as any attempt more glaring than usual
chanced to come to light. The subject is one to which the press
ought frequently to recur, — as being the only means of shaming
these wholesale plunderers into a more honest course.
“The extent to which the system has been carried is scarcely
credible. We have had the curiosity to cast up the total amount of
claim and award, in a dozen cases lately decided on by juries, and
find, that while the sum of the former falls little short of
£100,000 the latter scarcely reaches £20,000, or about one-fifth of
the modest demands made on the companies! In individual instances
the disproportion is still more striking, in the sum received being,
to the sum sued for, as one to seven, eight, or nine! Whence arises
this vast discrepancy? Juries, if they have any leaning at all,
invariably lean to the side of a private individual, rather than to
that of a public corporation; and show a disposition (a very
excusable feeling, by-the-way,) to give the most ample compensation,
that honesty and justice will allow, for injuries done to private
property, even when those injuries are in it great measure
imaginary. To what, then, if not to barefaced attempts at extortion,
are the extravagant sums, claimed by the owners of property required
for railway purposes, to be ascribed?
“It has long been a most convenient and peace-preserving practice,
to discriminate between the public and private characters of certain
eminent individuals, — to denounce a man, for example, as the most
corrupt and venal of politicians, and, in the same breath, laud him
as the most estimable and exemplary of mortals in private life.
Probably, the gentlemen land-holders imagine, that some such
distinction will be observed in their case, and that they will be
looked upon as altogether incapable of over-reaching their
neighbours, although they omit no opportunity of picking the pockets
of railway companies, as far as the law will permit. For our own
part, we acknowledge no nice distinctions of this kind, and scruple
not to call that man an extortioner, who seeks to use his own power,
and to call in the omnipotence of the law, to drive a bargain which
he knows to be unjust, whether the party with whom he deals be a
private individual, or a public body. It is fitting that all cases
of the kind be placed on record, that posterity may know who the men
were who did their best to crush the railway system in its birth, by
a series of attacks hitherto unprecedented, upon the purses of its
promoters. In that black list will be found the names of not a few
who would feel highly indignant were their piety or their patriotism
called in question, but who, nevertheless, have not scrupled to make
claims, and to bring forward others to substantiate them on oath,
knowing all the time, that these claims were most grossly and
flagrantly unjust. Nor are the cases which have come before the
public a tithe of those which are fairly within the description of
extortionate; every advantage, even the meanest and most despicable
that low cunning could suggest, has been taken of the difficulties
in which companies have been placed, to swell, by private agreement,
the rapacious demands of these land sharks, and, in too many
instances, they have boon successful.”
Hear also what the Irish railway commissioners say on the same
subject: —
“It is notorious that the consent of men of great
influence has frequently been obtained, as a matter of policy, by
agreements to pay amounts totally out of proportion to the value of
the land or premises required, and when the assents of individuals
will preclude the necessity of recurring again to Parliament, as in
some cases of proposed deviation, the matter to be considered is
sometimes a calculation, not of the real value of the required
property, but of the amount which the undertakers of the measure can
afford to pay in preference to applying for an amended bill.
Occasionally, even the alternative has proved so onerous, that it
has been judged better to abandon altogether a useful improvement.”
— “To make the assent of proprietors necessary for obtaining the
power to establish one of these great undertakings, is in reality to
abandon the high principle that private rights (liberally paid for)
must give way to great public interests. The purpose which this
formality is most usually made to have at the present time, is to
enhance, by pretended dissent, the amount of compensation; many a
dissent being purchased off by what can only he denominated a
bribe.”
“The bill is presented to Parliament, and if it be strenuously
opposed, particularly by a rival company, then commences the rich
harvest of counsel, solicitors, engineers, and persons summoned and
retained in London for the purpose of giving evidence; discussions
are entered into respecting every professional matter connected with
railways, the principles of curves, and gradients; of friction and
gravity, are investigated; questions on which, in many cases, the
counsel, the witnesses, and the court, are all equally ignorant.
Then a formal effort may be made, and perhaps with success, to
reject a measure after an expenditure of tens of thousands of
pounds, not on account of some very essential grounds of objection,
but frequently for some such trivial cause as that notice to the
proprietor of a small piece of waste land was left at No. 23 instead
of No. 24 in a given street. Thus a project, though possibly of
great value (for that does not alter the case), may be defeated for
two or three sessions of Parliament, having the whole to recommence
each time.” “After the Company has once battled its way, at an
enormous expense, through Parliament, it has still to contend, under
many disadvantages, with the landed proprietors and others, to whom
compensation is to be made; after which it has its own way, and is
in a condition to make reprisals upon the public for all these
unnecessary delays and vexations.”
These hardships and robberies are so truly and graphically
described, that we could almost imagine the eloquent writers had
been behind the scenes in company with ourselves, and that they had
in view the £72,868 13s. 10d., the memorable . . . .
“Payment for obtaining the Act of Incorporation,”
. . . . and the £630,000 for land, and “compensation,” coming from
the London and Birmingham Railway Company, as part of the price at
which they were allowed to commence one of the greatest public works
every yet undertaken in the world; but, alas! we know other burnt
children too. Things are managed better than this on the other side
of the Atlantic; there juries have awarded payments to railway
companies from landholders, when the road has been carried through
their property.
Notwithstanding the many untoward circumstances which have beset the
path of this gigantic enterprise, it has gone on with steady
perseverance, till the object has been achieved in spite of every
difficulty. At the last meeting of the proprietors, in August, 1838,
it was admitted that it must cost at least five millions, whereas
the Company had no power to raise more than four and a half
millions, till they could again apply to Parliament. The effect of
this announcement was, that without any appeal to the public for
loans, the half million was subscribed for by the directors,
proprietors, &c., in about two days, and tenders for a million more
have been offered and refused, simply on the credit of the
undertaking, and without any other guarantee.
Large as the outlay must eventually be, that on common roads will,
in some cases, present a tolerable approximation, for they are iron
roads to a more considerable extent than is generally supposed.
A stage coach horse wears out 4 lbs. per lunar month from off his
shoes, and a wagon horse 4.8 lbs.; the former travels about 270
miles in that time, at ten miles per hour, and the latter twenty-six
miles per day, and four days per week, or 416 miles, at two miles
and three quarters per hour; taking each and all upon an average,
and it is known that the proportion of loss was just ten times as
great twenty years ago. The tires of a wagon which went 6,048 miles
in five months lost 309 lbs., and a set of stage coach tires are
worn out in travelling from 1,500 to 2,500 miles, losing 210 lbs.
now, and formerly double that quantity; this, and all other repairs,
including the hire of the coach, were formerly contracted for at
sixpence per double mile, but they are done now for
twopence-halfpenny -- a set of four coach tires weigh one with the
other about 240 lbs. new, and 30 lbs. when worn out; they were
formerly only five-eighths of an inch in thickness, but are now
seven-eighths: the contractors always replace them quick enough in
order to run no risk.
The number of four-horse coaches which would have been required to
carry all the traffic, for short and long distances, on the direct
roads between London and Birmingham, reduced to a distance of 110
miles, would be about eighty per day one way. The number in 1832 was
exactly seventy-five. In the same way the equivalent number of vans
would be five, of wagons ten, and of market carts twenty-six. None
of these are at all connected with farming; if we, therefore, double
the two latter quantities for the farm carriage, we shall have, as a
general equivalent, for the long and short distances,
80 four-horse coaches, 20 five-horse wagons,
5 two-horse vans, 52 one-horse carts |
making each open journey of 110 miles per day; and from the data we
have given above, which is taken partly from evidence laid before
the House of Commons, and partly from the statements of the actual
contractors, it may be found that, in the last fifty years, there
has been deposited on the direct roads between Birmingham and London
the enormous quantity of 47,616 tons of iron, while the whole of the
rails, chairs, and spikes on the London and Birmingham Railway only
weigh about 35,000 tons, including those in the stations.
We have no means of ascertaining whether these latter articles will
last fifty years, although a late writer on the subject informs the
world that a rail one inch thick in the head, and wearing away
one-eighty-fourth of an inch per annum, will consequently last
eighty-four years! We suspect the said head would have rather an
unique appearance towards the latter end of December in the
eighty-third year, and perhaps a little sooner.
The Grand Junction Railway Company’s station, in Curzon Street, is
now finished, and the trains which arrive by the London and
Birmingham Railway, in the latter town, run into the Grand Junction
station, where those passenger who are going forward to Liverpool,
Manchester, &c., are put down in readiness for the next train, which
is arranged to start after allowing a reasonable time for
refreshments. In like manner, the Grand Junction trains from
Liverpool and Manchester run into the London and Birmingham station,
where the passengers for London are forwarded with a similar
attention to speed and convenience. Both these stations were built
by those enterprising contractors Messrs. Grissell and Peto, of
London.
While on the subject of convenience and comfort, we may just
observe, that although more remains to be done in these respects, we
ought in fact to say, much more; yet we have arrived, at all events,
so far towards perfection at present, in railway travelling, that
Ladies can be readily accommodated, under even extraordinary
circumstances, as it appears was done on the Paisley railway, where
on a late occasion, soon after a train had started, the passengers
were much alarmed by the guard calling out to the engine man to stop
the carriages immediately, for “some person is in ----;” the order
was so quickly attended to, that the last word was lost amidst the
unmusical sound of the brakes; but the alarm continued, as the guard
kept running to every carriage asking for a surgeon; dreading that
some serious accident had occurred, many persons alighted to enquire
what was wrong; they were however very agreeably disappointed, to
find that it was merely an additional passenger, who had no ticket,
raising up its voice in the most approved manner, on its first
introduction to the world. This could by no means be called a mis-carriage,
because first of all, both mother and infant were found to be doing
as well as could be expected, and secondly because the intruder was
a young gentleman. There is no doubt but that the printed
regulations of the Company would clearly define what his fare ought
to be, but to correctly ascertain his parish, would most probably be
a matter of somewhat greater difficulty.
Such comforts as the above, were but little thought of when the
outcries were first risen against railways, several years ago; the
tirades which were then issued against the system, were quite
ludicrous enough certainly, and were happily taken off in the
following sketch, which appeared in an American New York paper,
about the time of their first introduction in that country — we have
heard much worse arguments seriously put forth in England against
their adoption; —
A canal proprietor is supposed to speak —
“I see what will be the effect of it, — the whole world will be set
a gadding,— twenty miles an hour, sir, — why you will not be able to
keep a single ‘prentice boy at his work, — every Saturday evening he
must take a trip to Ohio, to spend the Sunday with his sweetheart, —
grave plodding citizens will be flying about like comets, — all
local attachments must be at an end, and not only that, but it must
encourage flightiness of intellect; and all kinds of people, will,
in spite of themselves, be turned into immeasurable liars,—their
very conceptions will be exaggerated by their munificent notions of
distance — ‘Only a hundred miles off, my dear madam! I’ll step for
your fan, and have it here in one minute.’ — ‘Pray, sir, will you
dine with me today at my neat little box at Alleghany?’ ‘Why,
indeed, I don’t know. Let us see, I shall be in time for the
railroad. Very well, I’ll come; but you must let me off in time to
be back for the theatre.’ And then, sir, there will be barrels of
pork, and chaldrons of coals, and cargoes of flour, ay, and even
lead and whiskey, and such like sober things that have always been
used to decent travelling — running away like a set of mad
skyrockets. It will upset the whole gravity of the nation. And then,
sir, think of flying for debt! a set of bum bailiffs, if even
mounted on bomb shells, will stand no chance whatever of capturing
an absconded debtor, only give him a fair start. The whole thing is
a pestilential, topsy-turvy, harem scarum, whirligig. Give me the
old, solemn, straight-forward, regular, Dutch Canal, three miles an
hour for expresses, and two for quick business-like journeys, with a
yoke of oxen for a heavy load. None of your hop, skip, and jump
whimsies for me. I go for beasts of burden — it is more primitive
and scriptural, and suits a moral and religious people like us for
beyond all this teakettle nonsense.”
It is all very well to laugh at these things now, when the fight is
over and the battle won, but when we remember the obstacles thrown,
and thrown successfully, in the way of these great improvements,—
the falsehoods, the ribaldry, the corruption and bribery, together
with the other foul manoeuvres which were set to work, only seven
years ago, in the case of the London and Birmingham Railway, and by
which, after all the evidence which could by any possibility, be
required, the Bill, for enabling this great work to be constructed,
was thrown out by a committee of our hereditary legislature; we
confess our faces ought rather to wear the contour of Heraclitus
than that of Democritus, especially as we have also to recollect,
that on the fate of this bill, in all probability, depended, for
some time to come, that of such works in general, — especially long
lines.
The Liverpool and Manchester Railway had, in all conscience, hard
fighting enough, before they were allowed to answer the question for
posterity — are railways useful and advantageous or not? When they
had, to the admiration of the world, triumphantly resolved this
question in the affirmative, the opponents of the “abominable
innovation,” as it was called, directly shifted their ground, and
grave and learnèd counsellors in the law, were readily at hand, who,
notwithstanding they were receiving fees, on the same day for
arguing in favour of as well as against railways, both in general
and particular, and, in at least one instance, fee’d first, by the
opponents of a great company, to declare such works were utterly
uncalled-for, and afterwards fee’d by the same company, to show
cause, of course, that there was nothing like railways and leather:
— were ready to declare, and did declare, and there were hereditary
legislators who listened, and agreed with them, that the proposition
of a railway from London to Birmingham was absurd, was monstrous,
that it savoured of nothing but an indirect species of insanity —
that because a railway had been constructed under the most
particular and peculiar local circumstances, between such towns as
Liverpool and Manchester, where the existing state of traffic was
such as could be found between no other two towns in England — that,
therefore, a railway between London and Birmingham, places between
which nothing but the most ordinary, everyday, “Dutch canal
express-boat at three miles an hour” communication could, by any
possibility, be required, was, in fact, equivalent to — as our
friend from the other side of the Atlantic wittily observed —
running the risk of converting, in spite of themselves, the whole
people of the country into “immeasurable liars.” Alas, that such
things should exist! but it is so; “the wisdom lies in the wig.”
When the Irish railway commissioners picked up the straggling
embellishments, adorning their second report, we know not, but they
do contain a number of home truths; — for instance, when they refer
to opposition being got up against railway companies, for the entire
and sole purpose of being bought off, their admirable description
can only have been based on a knowledge of facts.
For instance, after all the decided hostility paraded against the
bill for the London and Birmingham Railway, and the witnesses
examined as to the utter uselessness and inefficiency of such an
undertaking, at least as a matter of profit to the shareholders, and
after all the iniquitous loss and damage which such a mad-brained
project was to inflict on the line of country through which it was
to pass. and this was, by one well-fee’d speaker, (the wisdom again
lying in the wig,) compared to hardly anything short of an
earthquake; and although the opposition to the measure was of course
made on public grounds, with only a very little private interest in
the matter — a mere modicum — what was the upshot of all this
public-spirited feeling, this patriotism, this unheard-of
loving-kindness for the “country,” under the heroic influence of
which they had fought so many hard hours, by Tewksbury clock, and
with just exactly as much truth as Falstaff did.
This is one result:— a distinct proposition was made, from these
very same public-spirited people, to the directors of the London and
Birmingham Railway Company, offering that, if they (the Company)
would pay their opponents the small sum of £10,000, the opposition
should be withdrawn! The directors indignantly scouted such a
disgraceful transaction, and, in consequence of their honesty, they
lost their bill.
We will give one more little occurrence which distinguished the
period about which we are now writing, and but one, — not that we
want more, nor that we want many more; we have a certain
brown-covered memorandum-book, tolerably well known to our friends,
which contains a few trifling additions, which may be had when they
are “wanted,” like YORK was. A person who
spoke of himself as an accredited agent from influential parties,
rode in at certain stage-coach with us, not a very long time after
the London and Birmingham Railway Bill was lost, and the
conversation happened to turn on that subject, our companion
interested us not a little, as he evidently knew intimately some of
the tactics of the Company, which were of that description generally
considered confidential. What particularly struck us was, his
assertion, repeated several times, that the bill was lost entirely
through not taking his advice; that he both could and did show the
directors how it might have been gained to a certainty; that his
opinion was not a mere conjecture, but amounted to a positive matter
of fact, of which he had laid before the directors the absolute
proof; but they had refused to act according to the advice which he
had thus given them, and which would have conduced so much to their
interests, and that of the proprietors at large, and that they had
consequently nobody to thank but themselves.
Our conversation with this person extended to a considerable length,
but the above extract from the notes we made at the time, is
sufficient for our present purpose, which is to state, that an agent
answering the description of our above fellow passenger, did offer
to the directors to secure them six or seven votes, in the very
place were they were ultimately found to be wanted, and that for
this essential piece of service, he only required to have previously
placed in his hands, the small sum of a few thousand pounds. We need
hardly add the proposition was rejected with well merited scorn; and
thus through common honesty, the bill was, very probably, a second
time lost. We know the name of the person who made the above offer
to the directors; but we do not know the name of our stage coach
companion, consequently we are unable to state whether they are one
and the same; we have given the facts, and that is all our business
in the matter.
Now the railway is made, we have a right to amuse ourselves with
some of the speculations which appeared in print some seven years
ago; when in the midst of public meetings held by the nobility and
gentry, unanimously voting that railways were wholly unnecessary;
and particularly between London and Birmingham, and after a due
comparison with animal magnetism, metallic tractors, St. John Long,
Bedlam, &c. we find the cost of that work stated at £7,793,727,
there are no shillings, pence, or farthings. In this sum, after
purchasing the land, making the railway, including ballasting, and
paying for the blocks and rails, there is a small item of only
£3,069,887, for “Machinery and all other costs;” for 70 miles out of
the 112 which compose the line; and this is stated to be calculated
“on the most legitimate deductions, from the best existing data,”
and as “altogether independent of some other contingencies.”
The returns are then stated at £131,670 per annum less than the
yearly expenses; “thus upon the most favourable view that it is
possible to take of the railway between London and Birmingham, that
is, granting the Company all the trade, they must in spits of any
effort they can make, much more in spite of any words that they can
utter, borrow £130,000 the first year, in order to pay the interest
on their capital; they must borrow £136,000 the second year, and at
the end of fifteen years, they would have the pleasant prospect of a
debt of fifteen millions; give them time and it would creep up and
up, till it exceeded the national debt.”
Our author then astonished at his own liberality, in merely saddling
the Company with a debt of some 800 millions, declares that the view
he has taken of the case is “much too favourable to be possible” and
“we must now,” he says “examine what would be the expectation of
rational men;” before he begins his rational reform, however, he
just quietly let us know, that “if the nine figures of arithmetic be
faithful to their forms, a tunnel from Birmingham to Mexico has a
chance of being completed in the same year as this Railway;” after
which we have it in black and white printers’ ink, that the Railway
travelling is to be “absolutely slower than the coaches,” and that
“a velocity of fifteen miles an hour is in itself a great source of
danger.” At the inclement season of the year it will follow, of
course, that we shall frequently receive the intelligence,
communicated by the witty editor of a London newspaper — “the mails
can’t get in, to the delight of Miss Martineau.”
“Commercial travellers,” he informs us, (doubtless from “the most
legitimate deductions,”) “would, as a matter of course, never by any
chance go by the railroad, and the occasional traveller, who went
the same route for pleasure, would go by the coach road also.“—“Not
one of the nobility, or gentry, or those who travel in their own
carriages, would, by any chance, go by the railway.”—“Even if a man
had no carriage of his own, what inducement could he have to take so
ungainly a conveyance?” — Hence, “one-fourth of the passengers would
never go by the railway;” nor “one-third of the goods;” and scarcely
a “nameable fraction of the intermediate trade.”
Then comes his nationality proposition, which is also to be
“extravagantly liberal.” This consists in showing, (of course, if
the nine figures of arithmetic be faithful to their forms,) that
instead of the income being only £130,000 per annum less than the
working expenses, it must be £258,220 less, or that the railway will
be “losing a quarter of a million a year,” and this is in all
probability still too favourable, for none but “the solitary
stranger who had nobody to tell him better, would go swinging at the
tail of an engine.”
He appears to have at one time intended to be both “serious” and
“learned,” on the “mischief that this railway, if executed, would
produce to the country,” but “as the execution appears to us an
utter impossibility, we deem that unnecessary;” we should have
considered this as tantamount to an admission, that he had been
laughing at his readers, and making a fool of himself, all through
the preceding parts of his publication, but he winds up by
recommending the “facts and arguments” contained in his pages, “to
the solemn and patient examination of these who, like ourselves,
wish well to the interests of Old England.” We think this comes up
to, if it does not beat, brother Jonathan’s Dutch canal.
We must new draw to a conclusion, and shall only notice another
singular mistake which Mr. Roscoe has been led into, viz., that the
expense of the stone blocks for “the whole line,” may be divided
into three parts, one of which is for freight to the Thames. The
blocks on the Birmingham half of the line, ought not to have been
accused of this iniquity, they are totally guiltless of having been
freighted into the Thames, and the directors at that end of the
Railway, would have strangely misused the Company’s money, if they
had purchased their blocks in places where they would have had to
travel by that route, while the quarries of Derbyshire were close at
their hand.
――――♦――――
LONDON AND BIRMINGHAM
LOCOMOTIVE ENGINES.
Locomotive Engines are matters of such interest at the present day
that almost every person must be anxious to understand some little
about them; we have, therefore, written the following matter as an
Appendix to our History of the London and Birmingham Railway.
We have no space to enter into any enlarged statement respecting the
engines used on this line, although much might be said on that
subject which is not to be found in print up to the present time;
but we shall give a short and popular account of their general
features and construction, to as to enable every one to comprehend
the use of their various parts; at any rate as they appear
externally. If any of our readers wish to follow our description,
they will find the departure stage at Birmingham the best place for
examining the engines; for which purpose, however, they must not
leave the stage without permission. They do not accompany the
carriages to the terminus at the London end of the railway, the
trains descending from the Camden Town to the Euston square station,
by the effect of gravity. The Wolverton station will also afford a
similar opportunity.
The external appearance of the body of the engine may he divided
into three parts, which may be called the fire box, the smoke box,
and the boiler; which last connects the former two. In the domed
part is the fire box, which almost entirely occupies the whole space
from a few inches above the door, which opens out on the platform on
which the engine-man stands, down nearly to the bottom, where there
is a small space occupied by the grate. The fire box is encompassed
both on the top and round the sides by water, except at the part
where the door is fixed, this water communicates with that in the
boiler. A plug of lead and tin, fusible at a dangerous heat, is
placed on the top of the fire box; this melts if the water is let so
low as to leave the head of the fire box dry, and the steam then
rushes into the furnace. The part of the engine between the smoke
box and the dome is entirely taken up with the boiler; of which all
the upper part of the dome also forms a portion; it is filled with
water up to about half way between the top of the fire box and the
axis of the regulator. The handle of the regulator is seen about a
foot above the door of the fire box. It is by this handle that the
passage of the steam to the cylinders is opened and shut. The boiler
in cased with wood, to prevent, at much as possible, the radiation
of heat, and consequent loss of fuel in maintaining the steam at its
requisite pressure, which is about 50 lbs. on the square inch.
That part of the boiler which is above the top of the fire box is an
entirely open space, but the lower half of the boiler has, between
the upper and back part of the fire box and the nearest plate of the
chimney end, about 86 tubes, 2 inches in diameter, running through
it, one end of them opening into the fire box, and the other end
into that compartment of the engine called the smoke box; this is
the circular headed box painted black, from the middle of which the
shaft of the chimney takes its rise. These tubes form one of the
most essential requisites to the success of the modem locomotive
engines; they are surrounded entirely by the water in the boiler,
and the flame and heated air from the fire box being forced to go
through them, there being no other passage to the chimney. They
expose so great a surface to the action of the heat, that steam is
generated in a very rapid manner; although, in the first instance,
it takes nearly two hours after the fire is lighted before the steam
is properly up, there being very little draft to inflame such a fuel
as coke, while the engine is standing still.
In the upper part of the boiler, which, above the water, forms the
steam chamber, is the horizontal pipe which conveys the steam to the
cy1inders, by means of a vertical pipe attached to the horizontal
one, immediately under the centre of the dome, and open at the upper
end. This pipe rises nearly to the top of the highest part in the
centre of the dome, in order to prevent the bubbling or jolting of
the engine throwing the water into the steam pipe. It is up at the
top of this vertical pipe that the steam is admitted by means of the
regulator, which consists in some engines of two circular discs,
with apertures in them, one being fixed and the other turning round,
by means of the handle outside the engine, the effect of which is
that the apertures are brought either opposite to ouch other,
admitting the whole force of the steam, or placed one by the side of
the other, in which position no steam can pass; or they may vary the
passage to any degree required, between these two limits. In other
engines a cock, instead of discs, is used for the same purpose, and
in these on the London and Birmingham line the effect is produced by
it screw valve, on the smoke box side of the vertical pipe; in
either case the handle of the regulator is that which completely
controls the admission of steam, according to the quantity which the
handle is turned round.
The smoke box contains the cylinders, one end of those may be seen
in the front of the engines, nearly behind the wooden framing, with
the oil cups and cocks for admitting oil into them; it also holds
the slide valves, by which the steam is allowed to enter the
cylinders, the steam supply pipe, and the steam exit pipe; also a
small pipe for conveying condensed water out of the cylinders. There
is a passage in the smoke box completely round the cylinders, by
which means, when the engine is at work, the heated air and ashes
can encompass them in every part to keep them hot; when the engine
stands still, this takes place but in a very small degree, through
there being then but little draft, and a partial condensation of the
steam in the consequence; this enters the small pipe above
mentioned, and runs off at a cock in the front of the engine, below
the framing, the iron handle of which is to be seen just above the
framing. This cock is kept open as long as possible, its handle than
pointing directly forward from the engine; and just before the train
starts the engine man shuts it, the handle then is across the
engine. A large door surrounded with a brass frame in the front of
the engine, can be opened when required, in order to allow the
workmen to take to pieces or repair the parts inside the smoke box;
and a smaller door in the larger one, being only latched, can be
opened at any time, for the purpose of examining the interior.
The steam is admitted in and out of the cylinders by what are called
slide valves, which are fitted to each; these valves are worked by a
pair of rods attached to eccentrics fixed on the axle, and when the
engine is required to go backwards, another pair of eccentrics, also
on the axle, are set in motion; by those means the slide valves are
drawn backwards and forwards; the action of these rods may be seen
at the back part of the smoke box. When the valves are placed in
their first position, the steam is admitted at one and of the
cylinder and on one side of the piston, while at the same time the
way is opened for it to got out from the other end. When the valve
moves to the opposite position it reverses this -- namely, it shuts
the two former passages, and opens two others, letting the steam in
and out of the cylinder at the opposite ends respectively to what it
did before, its entrance being, of course, on the contrary side of
the piston. There are in reality but three passages to each
cylinder, two for the entrance of the steam, and one which, by the
motion of the slide valve, answers the double purpose of allowing it
to escape from either end of the cylinder.
Under the boiler will also be seen the piston rod working in and out
of the cylinder; being attached to the piston at one end, and joined
to the crank kale by the connecting rod at the other; it is this
which gives motion to the engine. The small brass dome towards the
chimney end of the boiler contains a safety valve, locked up from
the engine man. On the top of the dome, over the fire box, is
another which he regulates at pleasure. The long arm of the lever of
this is 17½ inches, the short 4½, and the valve has a diameter of 2⅜
inches at the bottom, the shape being conical. The spring balance
attached to the end of the lever of the safety valve, may by means
of the screw at the top, be regulated to let off the steam at any
point up to 60 lbs. per square inch; and it is generally worked at
50 lbs. Between the safety valve and the balance, on the top of the
dome, is the steam whistle, for warning the workmen on the road and
others that the engine is approaching. This upper and small part of
the dome covers what is called the man hole, from its size just
admitting a man to get in to clean and repair the interior of the
boiler or the works within it.
On the left hand side of the dome is the water gauge, composed of a
glass tube communicating with the water and steam in the boiler; it
has three cocks, two between the glass tube and the dome, and one at
the bottom of the glass tube. When this lower one is shut and the
other two opened, the water enters the tube through the lower of
these two cocks, and the steam through the upper. The water then
stands in the glass tube at the same height as it does in the
boiler, and can be constantly examined by the engine man; the use of
the third cock, at the bottom of the tube, is to empty it by when
required. Near the water gauge are three other brass cocks, in a
slanting direction, one above the other; these, which are called the
gauge cocks, all communicate with the boiler, and afford an
additional means of examining the quantity of water in it, by
opening them and noting whether water or steam comes out. The water
should on no account ever be allowed to get below the head of the
fire box, not only because less steam would be generated, but also
that the head of the fire box would be injured by the heat.
On each side of the dome, close down to the platform, is a brass
handle, turning an iron rod, which opens and shuts what is called
the pet cock; this is connected with the force pump by which the
boiler is filled; these pumps are worked by the straight part of the
piston rod, not far from the cylinder, their plungers being the
outside moving part on each side at that end of the engine. They
are, of course, always at work when the engines are going, but water
is only admitted to them when the boiler requires it; this is
regulated by a cock to each supply pipe from the tender, the iron
lever handles of which may be seen on the top and front of the
tender, one on each side. The copper tubes been under the engine and
tender, form the communication by which the water is conveyed to the
pumps; and the two tubes, when the tender is attached to the
engines, are connected by a third, which is flexible. The use of the
pet cock is to inform the engine man whether the force pumps are in
order; if this is the case when they are working, and he opens the
pet cock, water instantly rushes out; if it does not, he immediately
tries the other side, and if both pumps are disabled he must examine
and repair them directly, or put out the fire. Near the handle of the
pet cock, on the right hand side of the dome, is an iron handle
close to the platform and parallel with it. This turns a brass cock
under the platform, by which the water is let out of the boiler, and
by which the engines are blown off; that is to say, the water forced
out when the steam is up, which is done every five or six days or
otherwise -- according to the quality of the water -- to clean the
boiler.
On the right hand side of the dome, just above the pet cock, is an
iron lever handle, which, by means of a long rod attached to it,
throws the eccentrics off the connection which they have with the
slide valves; the cylinders are then no longer supplied with steam,
and the engine if left to herself would gradually loss her velocity,
and come to a standstill; this effect is produced by putting the
handle in the middle of the sliding arm against which it moves, when
it is put to the top of the arc, the eccentrics are thereby so
disposed that the engine goes backwards; and when it is put to the
bottom, the engine on the contrary, will go forward; a notch in the
iron arc retains it in either of these two latter positions. These
handles are made to act directly opposite to this by some
manufacturers, the position of them being purely a matter of choice. When the eccentrics are put out of connection with the slides, or
out of gear as it is technically termed, the engine may then be
worked by the two long upright handles, above that which has just
been described, which will move the slides at the will of the engine
man; so that if the eccentrics or their rods are completely broken,
the engine can still go on; and it is by these handles, technically
called the head gear, that the engine is moved very small distances,
so they can be regulated better for that purpose than the eccentrics
can be; they also admit the steam with an impulse, by being pulled
quick, whereas the motion of the eccentrics is slower; some makers,
however, dispense with these.
Underneath the fire box is the ash pit, this forms the lowest
portion of the dome, it is open to the whole front of the engine,
and closed at the bottom, sides, and back, accept where the door is
seen. The fire bars in the bottom of the fire box, run quite across
the box, and are in separate divisions, with about six or seven bars
in each; these can be taken in and out, and when the fire is required
to be suddenly extinguished, the engine man, by turning the iron
turn handle close to the top of the door of the ash pit, can trip
them out so that the fire and the bars fall into the road.
The various parts of the machinery are generally oiled by means of
brass cups, having a small tube running from nearly the top of the
interior of the cup through the bottom, down close to the part to be
oiled; in this tube is a cotton wick, the lower end of which
communicates with the part to be oiled, and the upper end hangs over
the top of the tube into the oil in the cup, and thus forms a siphon
for conveying the oil in small and equal quantities to the part
which requires it; other makers do this by cocks and pipes, leading
to the various points from a common receptacle. In the front of the
engine, extending close down to the rails, is a guard iron, which is
fixed there for the purpose of clearing the rails of any thing laid
on them, either through carelessness or wilfulness; this is s most
useful contrivance, and has prevented serious accidents on more than
one occasion; for instance, on the 1st of October, 1838, one of the
engines on her arrival with the train at Birmingham, was found to
have this iron on one side wretched round, in a manner which could
only have happened by its coming in contact with some very hard
substance, in all probability purposely laid on the rails.
The tender which carries the supplies of coke and water needs no
particular description. It has a brake attached to it, for checking
the speed, the long handle of which may be seen on the right hand
side. The supply of coke carried in the tender is about 21 cwts.,
and of water about 700 gallons. The engine consumes at about the
following rate -- water, 1400 gallons per 70 miles -- coke, if good,
about 14 cwts. for the same distance; but the quantity of coke
depends on its quality and the weight of the load, and the quantity
of water depends also on the weight of the load.
――――♦――――
A SKETCH OF THE GEOLOGICAL
FEATURES OF THE LINE.
THE science of geology would be often materially assisted, if the
railway companies were to correctly ascertain, and publish, the
nature of all the various material through which their excavations
are made. This can only be done while the works are preceding, as
the slopes ought to be turfed as speedily as possible, in order to
assist in preventing slips. We have collected the following account
of the strata on the London and Birmingham line, from information
arising out of the various surveys, borings, &c.; and, although it
is not so full nor so perfect as we could wish, we offer it, as an
example, with the hope of inciting persons connected with other
lines to present to the public more enlarged and complete accounts
of their respective works.
We shall commence at the London end, from which, the first 13 miles
runs through the London clay, a very bad material for any kind of
engineering operations. There is much diversity of opinion about the
slope at which it will stand, for on the Southampton railway
embankments made of it are formed with one base to one
perpendicular; several of these, however, have slipped.
0 to 13 miles . . . . London Clay.
14.5 mile trial shaft, —
Yellowish Clay . . . . 3 feet
Darkish Clay . . . . 18
Yellowish sandy loam . . . . 5
Black Clay . . . . 7
16.63 mile trial shaft. —
Rubble . . . 4 feet
Clay . . . . . 8
Blue Clay . . . . . 8.5
Chalk and Marl . . . 7
16.5 mile. Chalk quarry. |
The chalk formations, the upper part containing flints and the lower
without, extends from the above quarry to 34.17 miles from London.
Watford Tunnel is in the upper formation, with a thick irregular
covering of gravel; this part of the chalk has occasional fissures,
as much as 100 feet deep, filled with clean gravel, which, when
worked into, rushed down with such violence, as to plough the walls
of the tunnel as if bullets had been shot against it.
34.17 miles — Chalk Marl and Green sand.
39 miles — Iron Sand formation, consisting of ferruginous sand and
sandstone.
41.83 miles — Oxford Clay formation.
44.17 miles, trial shaft — Blue clay mixed with chalk fragments, 28
feet; query, if not diluvial?
45.25, trial shaft — Blue Clay, 18 feet.
From 41.83 to 53.5 miles is principally the Oxford or Clunch clay,
consisting chiefly of beds of grey, blue, and black shale, nearly
destitute of water.
48.25 miles, trial shaft —
Brownish-yellow clay, with fragments of chalk, 13 feet
Grey, blue, and blackish clay 17 |
The material was proved here, by a well at Denbigh Hall, to 70 feet
below the above, and was without water.
52 miles, trial shaft —
Mixed Brown earth . . . 16 feet
Dark Brown clay . . . . 29 |
52.17 to 53.17 — from 7 to 10 feet of yellow and blue clay.
53.17 miles — the upper part of the great Oolite formation is
considered to commence here, and to extend to 61.7 miles.
59 miles — this excavation contains: —
Soil and loose stones . . . . 3 feet.
Yellow lime stone . . . . 11
Ditto ditto . . . . 6.5
Blue shale, getting very hard . . . . 10.5
Ditto no water . . . . 17
59.5 miles — this excavation contains: —
Gravel and soil . . . . . . 4 feet
Yellow limestone . . . 5.5
Blue shale . . . . . 13.5
Bluerock. . . . . . . . 1.5
No water. |
We now come to the large cutting, and the general features of this
consist of beds of clay, from the surface downwards, laying in a
basin formed by the rock, which dips from the surface, at each end
of the cutting, towards the centre, where it reaches the bottom of
the excavation. Under the rock is blue shale, and the details of the
whole cutting are as follows—
59.83 to 60.17 miles —
Sand and Loam . . . . 5 feet
Clay . . . . 2
Yellow limestone . . . . 14
Blue limestone, very hard, mixed with thin beds of shale
. . . . 13
Blue shale . . . . 5
Very little water 1 foot lower . . . . 8
60.17 to 60.75 miles —
Soil and clay . . . . 2 feet
Stoney yellow clay . . . 9
Blue clay . . . . 14
Yellow limestone . . . . 16
Soft yellow limestone and some water . . . . 1.5
Hard yellow limestone and some water . . . . 0.25
Blue shale . . . . 0.75
Blue limestone, very hard . . . . 2
Blue shale and sand vein . . . . 2
Stronger shale . . . . 1.5
Very hard blue limestone rock . . . . 4.25
Strong blue shale . . . . 4.25
61 miles.
Sand and loose stones . . . . 3 feet.
Yellow limestone . . . . 13
Soft limestone . . . . . 0.25
Yellow limestone . . . . 2
Strong brown clay . . . . 4
Yellow limestone with a 3-inch parting, at little water
. . . . 4
Blue shale . . . . 14.5
Very hard blue limestone, with a soft 3-inch parting . .
. . 6.75
Very dark blue shale . . . . 2.75
Brown sandy loam; water below . . . . 4
Rather soft greenish stone with hard beds . . . . 3.5
Green rock . . . . 1.5
Blue shale . . . . 0.25
61.75 miles.
Loose shivery limestone . . . . 2.25feet
Yellow marl . . . . 1.5
Shivery limestone . . . . 1.5
Limestone . . . . 8
Yellow marl . . . . 7 |
This ends the Blisworth large excavation.
61.7 to 61.9 miles. Ferruginous sandy marl.
61.9 to 64.33 miles. Fullers’
earth bed of the inferior Oolite.
64.33 to 66.75 miles. Marl-stone
and shale, forming the fullers’ earth bed of the inferior Oolite,
with an irregular bed of limestone.
66.75 to 69.5 miles. A bed of calcareous sand-stone, in a thick
shale strata, from 15 to 90 feet above the level of the canal. Stowe
Hill Tunnel was altogether through shale, and perfectly dry.
69.5 to 71.5 miles. Inferior Oolite and Marly Sandstone, with thick
beds of Gravel and Sand.
71.5 to 86 miles. Generally the upper Shales of the Lias formation.
71.5 miles. A line of Springs about this part, considered to issue
from the top of the Lias beds.
73.7 miles. Sand Hill in Lord Spencer’s property.
76.5 to 77.75 miles. Kilsby Tunnel. The top of this hill is
considered to be formed of the lower beds of the Inferior Oolite,
consisting of alternate beds of Rock and Marle; anti passing into
the Lias formation. The strata at the London end consists of,
Soil . . . . 2.5 feet
Yellow Clay . . . . 5.5
Brown Clay . . . . 2.5
Blue Shale . . . . 17
Blue Marl . . . . 19 |
The Birmingham end consists of Soil 5.5 feet, of Yellowish Clay 9,
of Blue Shale 6.5, of Brown Iron Stone 1.74, of Blue Marl, with
three beds of Blue Stone 22.75.
Near the London end of the Tunnel a bed of Quicksand was found to
lie in the shape of a basin, the bottom of which extended, in some
cases, nearly to the springing of the arch over a length of about
400 yards.
79.75 miles. Sand Hill.
86.5 miles. Lias, Limestone and shale, being from the top Blue Clay,
apparently diluvial, 4 feet 9 inches; Brown Clay, with beds of
Ochreous matter, 6 feet three inches; Blue Shale, in beds of 9 to 12
inches, 6 feet 6 inches; Yellow and Blue Limestone, 5 feet 8 inches;
Blue Shale to the bottom of cutting, about 25 feet.
87.5 to 88.5 miles. Lower Marl, and Shale, of the Lias formation.
88.5 miles to Birmingham. The line passes through the New Red Sand
Stone and Marl formations.
88.5 mile stone. Soil, 2 feet; Blue Clay and Gravel, resting on Red
Sand Stone, 10 feet.
90 miles. Very dry Sand and Gravel.
90.75miles. Sand resting on Red Marl.
92 miles. Clay and Sand, 8 feet; Red Clay, 11 feet; Strong Red Clay,
9 feet; Very strong and Marly, 2 feet.
93.75 miles. Soft Yellow Sand-stone.
98.5 miles. Beechwood Tunnel.—Red Sand-stone.
99.5 miles. Sand, 2 feet; Red Clay, 10 feet; Rocky Red Marl, 38
feet.
101.5 miles. Sharp Gravel, forming an extensive tract in this
valley.
102.5 miles. Blue and red Marl, dry and hard, 70 feet.
103.5 miles. Blue Marl.
106 miles. Gravel and Sand.
107.5 miles to 109.5 miles. The cuttings are Red Marl, overlaid by
gravel.
110.5 miles. Yellowish Sand, 11 feet; Red Clay, 9 feet; Rocky Red
Marl, with irregular beds of Blue Marl, 17 feet.
110.75 miles. Red Clay, 12 feet; Rocky Red Marl with irregular beds
of Blue Marl, 28 feet. — This formation extends to the Birmingham
terminus.
――――♦――――
LIST OF THE DIRECTORS OF
THE LONDON AND BIRMINGHAM RAILWAY,
FROM THE PASSING OF THE ACT OF INCORPORATION,
TO THE
COMPLETE OPENING OF THE LINE.
Those marked * were in office when the Act was obtained. Those
marked † were in office when the line was completely opened.
----------------
Chairmen:
* Issac Solly, Esq. † G. C. Glyn, Esq.
Deputy Chairman:
† J. F. Ledsam, Esq.
Directors:
*†
*
†
*†
*
†
*
†
*
*†
*
†
*†
*
†
†
*
*
*†
*
† |
G. P. Barclay, Esq.
G. Bacchus, Esq.
J. B. Boothby, Esq.
E. Calvert, Esq.
W. T. Copeland, Esq.
J. Cooke. Esq.
J. Corrie, Esq.
E. Cropper, Esq.
H. Earle, Esq.
J. Foster, Esq.
W. Francis, Esq.
G. C. Glynn, Esq.
J. Gibson, Esq.
R. Garnet, Esq.
P. St. L. Grenfell, Esq.
W. Hawkes, Esq.
D. Hodgson, Esq.
H. Holdsworth, Esq.
A. Kenrick, Esq.
J. S. Lefevre, Esq.
J. F. Ledsam, Esq.
D. Ledsam, Esq.
T. Lowe, Esq. |
*
*
*†
*
*†
*
*
†
*
*
*
*
*
*†
*
*†
*
*†
†
*
† |
G. Larpent, Esq.
Sir W. Lubbock, Bart.
W. Phipson, Esq.
J. Pearson, Esq.
J. L. Prevost, Esq.
T. Price, Esq.
Edmund Peel, Esq.
T. Rathbone, Esq.
H. Rowles. Esq.
T. Smith, Esq.
C. Shaw, Esq.
H. Smith, Esq.
J. Solly, Esq.
W. H. Sparrow, Esq.
John Sturge, Esq.
Joseph Sturge,
J. Turner, Esq.
T. Tooke, Esq.
H. Warre, Esq.
J. Walker, Esq.
E. Wilson, Esq.
A. Wilson, Esq.
T. Young, Esq. |
Secretaries:
*† Richard Creed, Esq. *† Capt. C.R. Moorsom, R.N.
――――♦――――
ENGINEERS
Engineer-in-Chief:
ROBERT STEPHENSON,
ESQ.
G. W. Buck |
Charles Fox |
|
John
Birkenshaw |
|
Timothy
Jenkins |
|
F. Young |
|
Capt.
Cleather, R.S.C. |
John
Crossley |
S. S.
Bennett |
|
E. Jackson |
|
J. Gandell |
|
M. Farrell |
F. Forster,
and |
H. Lee |
afterwards |
E. Dixon |
G. H.
Phipps |
C. Lean |
|
S. Meek |
J. L.
Gooch, and |
J. Brunton |
afterwards |
S. Meek |
F. Forster |
John Reid |
|
B. L.
Dickenson |
|
M.
Monteleagre |
|
R. B.
Dockray |
|
Lieut. P. Lecount, R.N. |
|